National Highways Authority Of ... vs Hindustan Construction Co. Ltd
2017 Latest Caselaw 401 Del

Citation : 2017 Latest Caselaw 401 Del
Judgement Date : 24 January, 2017

Delhi High Court
National Highways Authority Of ... vs Hindustan Construction Co. Ltd on 24 January, 2017
$~
*     IN THE HIGH COURT OF DELHI AT NEW DELHI

+                        OMP No. 260 of 2015

                               Reserved on: December 03, 2016
                               Date of decision: January 24, 2017

NATIONAL HIGHWAYS AUTHORITY OF INDIA        ..... Petitioner
                Through: Mr.. Rajiv Kapoor & Mr.. Srikant
                         Sharma, Advocates

                                  versus

HINDUSTAN CONSTRUCTION CO. LTD               ..... Respondent
                Through: Mr.    Dayan    Krishnan,      Senior
                         Advocate with Ms. Malavika Lal,
                         Mr.. Karan Luthra & Ms. Aakashi
                         Lodha, Advocates.

      CORAM: JUSTICE S.MURALIDHAR

                         J U D G M E NT
%                           24.01.2017

1. The challenge in this petition by the National Highways Authority of India (NHAI) under Section 34 of the Arbitration and Conciliation Act, 1996 („Act‟) is to an Award dated 29th November, 2014 as well as its corrected version dated 15th December, 2014 passed by the Arbitral Tribunal (AT) by a 2:1 majority in the disputes between NHAI and the Respondent, Hindustan Construction Co. Ltd. („HCC‟).

2. The background facts are that an Agreement dated 29 th January, 2004 was entered into between the parties whereby the work of Development of

Adequate Road Connectivity to Paradip Port (4-laning of Chandikhol- Paradip km 0.0 to km 77.0 Section of NH-5A) in the State of Orissa (Contract Package-OR-PARADIP) was awarded by NHAI to HCC.

3. It is not in dispute that the work could not be completed within the stipulated time limit of thirty six months. HCC, from time to time, applied for extension of time ('EOT') on account of 'compensation events' which it notified to the Engineer. However, NHAI was not in a position to hand over the land for the Chandikhol Intersection.

4. After review and consideration of the compensation events, the Engineer gave his recommendation for EOT from time to time. The Engineer treated the whole of the work as substantially completed as on 15th June, 2009. However, NHAI was not in a position to hand over the land for the Chandikhol Intersection. The Engineer recommended EOT till 27th August, 2009 for completion of whole of the remaining work during the Defect Liability Period („DLP‟). This included the work at the Chandikhol Intersection. The Engineer issued a substantial Completion Certificate („CC‟) to that effect. Based on the CC, NHAI approved the EOT till 15 th June, 2009 in terms of Clause 28 of the General Conditions of Contract (GCC).

5. That the works under the contract were completed under the DLP is not in dispute. HCC submitted its claim for payment of additional costs incurred on account of EOT. With no response from the Engineer, HCC issued a notice of dispute to NHAI and thereafter had the matter referred to the Dispute Resolution Board („DRB‟). When the DRB failed to issue its

recommendations within the specified period, HCC issued a notice invoking arbitration and that is how the AT came to be constituted.

6. The three-member AT comprised the Presiding Arbitrator, one Member nominated by NHAI and the other by HCC. The impugned Award was in respect of Dispute No. 6. i.e., "payment of additional costs incurred/losses suffered in the extended period of the contract from 19th February, 2007 to 15th June, 2009" on account of delays and compensation events not attributable to HCC.

7. In the impugned Award by the majority of the AT, it was noted that the whole of the work was divided into three milestones as under:

"Milestone-1: Complete minimum length of 25 Km (anywhere in the entire stretch) in all respects of new carriage way within 18 months from the start date excluding major bridges falling in between i.e. on 18.08.2005.

Milestone-2: Complete a length of 25 Km of old carriageway in all respect of Milestone No.1 and additional 20 Km length of new carriage way in all respect so that total completed stretch would be 45 km of new carriage way and 25 Km of old carriage way within 28 months from the start date. This also excludes major bridges i.e. on 18.08.2005.

Milestone-3: Remaining length including all Bridges (complete work) shall be completed by the end of the contract period i.e. 36 months from the start date i.e. on 18.08.2005."

8. The case of the HCC was that it was prevented from completing the work due to „compensation events‟. The majority Award noted that while EOT was not approved by NHAI as regards Milestones 1 and 2, EOT for 848 days till 15th June, 2009 was approved for Milestone 3. It was further

pointed out by HCC that EOT was granted under Clause 28 of the contract i.e. on account of compensation events not caused by HCC. It was contended by HCC that as a result of the EOT, it was compelled to remain at the project site with all its manpower, equipments, machineries and other resources to complete the balance works in the extended period. Thus, HCC had to incur additional costs which were not compensated for in the contract price. On completion of the work, HCC submitted a claim for additional costs for the extended period in the sum of Rs. 142.73 crores.

9. The majority Award held as under:

(i) Clause 47.1 provided for price adjustment in respect of the inputs to the works based on the agreed formulae. However, once the time was set at large on account of delay and default of NHAI, the disclaimer clause would not be binding on HCC. Further, the time-related costs in the contract price such as equipment ownership charges, overhead expenses, financing charges etc. could cater only to the original time of 36 months and not for the extended period. With the EOT, HCC was exposed to losses and injuries. Since HCC was tied down at the project site due to the delays and defaults of NHAI, it lost the opportunity to move to other work sites and earn revenue. The events causing extension of intended completion period of the work from 19th February, 2007 to 15th June, 2009 was on account of compensation events in terms of Clauses 21.1 and 44.1. The reasons for the EOT were not attributable to HCC.

(ii) As regards the delay in handing over of the site, after discussing the statutory provisions of the contract, the majority concluded that HCC‟s

responsibility was limited only to comply with certain procedures. Its claim on account of compensation events was not barred under Item No. 110. 6 of BOQ as well as Item No. 18 of the contract data. The plea of NHAI that under Item No.18 and No. 1.06 of BOQ the responsibility was of HCC to coordinate in the cutting of trees, shifting of utilities and removal of encroachments etc. and that if any of these works get delayed HCC would not be entitled to any compensation was negatived by the majority Award because delay in removal of the encumbrances was attributable only to NHAI. In this the majority found such a stipulation in the said clause to be void in terms of Sections 53 and 73 Indian Contract Act 1872 (ICA) and contrary to Clauses 21, 28 and 44 of the contract.

(iii) On the question of the issuance of an earlier warning by HCC, the majority was of the opinion that HCC had duly warned the Engineer even though it was not required to do so. The majority then found that there was no shred of evidence to support the argument of NHAI that the contract was extended not on account of compensation events but only to keep it alive. The majority further found that HCC had taken action to ensure that additional costs on account of compensation events were mitigated to the extent possible.

(iv) The majority Award also rejected the plea of NHAI that HCC had failed to submit adequate evidence required for the assessment of its claim. Nevertheless, the majority undertook its own assessment based on the documents submitted to it in that regard.

(v) Ultimately the majority Award held that NHAI should pay HCC Rs.

69,98,36,300 along with interest of Rs. 44,50,95,800 under various sub- heads of claims on additional costs totalling Rs. 1,14,49,32,100. The said sum was to be paid within 90 days failing which simple interest at 18% per annum was payable on the principal amount of Rs. 69,98,36,300 from the date of the Award till the date of payment. Further NHAI was to pay HCC Rs. 3,30,000 within 15 days failing which simple interest at 18% per annum was payable thereon. The counter -claim of NHAI was rejected.

10. The present petition by NHAI confines the challenge to the impugned majority Award in respect of Claim sub-head Nos. 1, 2 and 3 and the rejection of its counter-claim. The amounts claimed by HCC, the amounts determined as payable by the Engineer and the amount awarded by the AT in respect of the above claims are depicted by it in a tabular form as under:

Subhead Particulars            Paragraph of Amount       Amount              Amount
No.                            Award        claimed by   determined by       awarded by
                                            HCC (Rs.)    the Engineer        AT
                                            (crores)     (Rs.) (crores)
Claim     Additional           27.3.2(a)    62.119       27.3898             32.527
Sub-      overhead             28.1.1,                   Accepted       in
head      expenses             28.1.2                    principle     by
No. 1     incurred over the                              the Engineer
          extended period
Claim     Additional           27.3.2(b)    37.95        17.58           32.96
Sub-      expenses       on    28.2                      Accepted     in
head      account        of                              principle    by
No. 2     extended stay of                               the Engineer
          plant         and
          equipment      on
          site during the
          extended period
Claim     Financing            27.3.2(c)    8.96         Rejected     in 4.49
Sub-      charges (interest)   28.3                      principle    by
head      on account of                                  the Engineer
No. 3     delayed recovery
          of overheads and





           profits
Claim     Claim of loss of 27.3.2(d)    25.35        2.74           Nil
Sub-      earning capacity 28.4                      accepted    in Rejected
head      and profits                                principle      since HCC
No. 4                                                               had     been
                                                                    awarded the
                                                                    interest for
                                                                    the delay in
                                                                    the recovery
                                                                    of the profit
Claim     Claim          of             6.75         Rejected       Allowed.
Sub-      additional labour                                         However,
head      cost    in    the                                         no amounts
No. 5     extended period                                           awarded
                                                                    since     the
                                                                    interest on
                                                                    the delayed
                                                                    recovery of
                                                                    profits was
                                                                    granted in
                                                                    Claim sub-
                                                                    head No. 1.


11. On 21st April, 2015, this Court passed a detailed order dismissing the petition. The first part of the said order dealt with the challenge to the majority Award by NHAI on the ground that there was no consultation or meeting of mind of the three Arbitrators at the time when the majority Award was rendered. This Court rejected the said ground of challenge. The second part of the order dealt with the challenge to the impugned Award on merits. The Court rejected that challenge as well.

12. The order dated 21st April, 2015 of this Court was carried in appeal by NHAI to the Division Bench (DB) in FAO(OS) 383/2015. By its judgment dated 17th February, 2016 the DB affirmed the conclusion of this Court that the challenge to the majority Award on the ground that there was no

consultation amongst the three Arbitrators must fail. However on merits the DB was of the view that the findings were "token in nature" and that the Court had failed to deal with the challenge to the majority Award on merits as is warranted in proceedings under Section 34 of the Act. Consequently, this petition was restored for adjudication afresh on merits.

13. Mr. Rajiv Kapoor, learned counsel for NHAI made the following submissions:

(i) The grant of EOT by NHAI did not necessarily warrant increase in the contractual price on the ground that NHAI was responsible for causing delay in completion of work at various stages. Reliance was placed on the observations in the decision of the Supreme Court in Kailash Nath & Associates v. New Delhi Municipal Committee 2002 (3) Arb. LR 631 (Del) (DB) to urge that mere grant of EOT could not lead to the inference that it was NHAI that was responsible for the delay. Reliance was also placed on the decision in M/s Chugh Kathuria Engineers (P) Ltd. v. Delhi Development Authority 2012 (1) RAJ 64 (Del).

(ii) Paras 1, 3 and 6 of the terms of the Bill of Quantity (BOQ) provided that the contractor shall cover all risks and activities express and implied. Referring to Item No. 18 of the Contract Data and replies given to question Nos. 39, 59 and 60 of the pre-bid meeting, it was pointed out that the replies given thereto were limited to the question of land acquisition. The word „unencumbered‟ was used in relation to a particular clause and not the shifting of utilities. In particular, it is submitted that the shifting of utilities, counter press etc. do not constitute a „compensation event‟. The process of

shifting of utility/cutting of trees and removal of „encumbrances‟ were the contractual activities of the contractor and cannot, therefore, be termed a 'compensation event'.

(iii) Referring to Clause 1.06 of the Technical Specification („TS‟), it was pointed out that HCC had tendered for a lumpsum amount per km or part thereto for coordination, which was deemed to cover all coordination work including any risk associated with the delay under the disruption and even the need to adjust the programme due to delay including cutting of trees, shifting of utilities, removal of encroachment etc. In other words, the latter would not qualify as a „compensation event‟.

(iv) In terms of Clauses 10, 11 and 12 of the contract, in case some event occurred that was not foreseen or some activities took a long time, the consequent effects were to be borne by HCC. In any event, there was no certificate by an independent chartered accountant (CA) in relation to the notification of the claims of HCC. The claims were based on unsubstantiated numbers and the data submitted by HCC was without evidence as no logbooks were supplied to support the claims. The managerial reports were administrative, managerial reports and could not form the basis for financial claims.

(v) The AT failed to notice that Clause 110.3 made it clear that the Respondent was the one responsible for coordination and also for obtaining and making requisite permission from the service provider and making the site unencumbered, and yet the majority AT awarded compensation on account of delay and shifting of utilities.

(vi) Both parties had agreed that the supplementary agreement would be a separate contract. This amounted to revocation of the main contract concerning the project. Under the supplementary agreement, there was no question of the delay being a compensation event.

(vii) The majority had also failed to note that the wording of Clause 44.1 with „and/or‟, which meant that there could either be extension of time or increase in the contract price or both.

(viii) The majority failed to appreciate the contention of NHAI that in a situation beyond the control of the parties the responsibility for site management continued to be that of HCC alone and that the grant of extension of 878 days on this count by NHAI on sympathetic grounds was not on account of any delay or breach of the contract by NHAI.

(ix) There was no occasion for the majority to come to the conclusion as it did that Item No. 18 of the contract data would be hit by Section 23 of the ICA and that in such event, NHAI would be liable to compensate HCC. This amounted to rewriting the contract which is impermissible in law.

14. Mr. Dayan Krishnan, learned senior counsel for HCC submits that the finding of the AT as regards Item No. 18 of the contract data being hit by Section 23 ICA had no effect on the conclusion in the impugned majority Award since, in any event, HCC had not claimed compensation on account of the delay caused in getting approval for the shifting of the utility/cutting of trees. He points out that the EOT determined by the Engineer, LEA

Associates, was on 14th May, 2009. The Engineer‟s letter dated 18th February, 2010 of the determination of the account pointed out to HCC as per the EOT granted on 14th May, 2009 would reveal that although HCC has claimed EOT of 1142 days which included 242 days of delay in removal of encumbrances due to operation of Item No. 18 of the contract, the Engineer, in fact, had only approved EOT for 848 days. Thus, the EOT on account of the delay of 242 days due to the operation of Item No. 18 of the contract data was rejected by the Engineer. Accordingly, the Engineer had extended the period of completion of work only from 19th February, 2007 to 15th June, 2009 which determination was accepted by HCC, and it had not asked for compensation for the 242 days relatable to Item No. 18 of the Contract Data.

15. The above submissions have been considered. Clause 44.1 of the Condition of the Contract stipulates as to what would be a compensation event. Sub-clause (a) thereof prescribes one compensation event as when an employer does not give access to a part of the site from the possession date stated in the contract data. In case the employer or service provider organization is restrained by a court from cutting of trees/shifting of utility/removal of encroachment etc., it shall be a compensation event.

16. Clause 21.1 provides that the employer "shall give possession of all parts of the site to the contractor. If the possession of a part is not given by the date stated in the Contract Data the employer is deemed to have delayed the start of the relevant activities and this will be compensation event". The AT, on a harmonious reading of the above two clauses, came to the conclusion that "if the cutting of trees, shifting of utilities and removal of encroachment

is delayed and the site is not made unencumbered by the employer, it shall be considered that the work is delayed by the employer" i.e., NHAI. In addition, Item No. 18 of the Contract Data provided that "the contractor will not be entitled of any compensation for the delay in cutting of trees/shifting of utilities and removal of encroachment by the service provider/concerned authorities, arranging approvals and clearances from various authorities including the Railways".

17. HCC appears to have been conscious of the permissions required for the cutting of trees and shifting of utilities and wrote to the concerned department for expediting and facilitating the process. Queries in this regard were raised by it at the pre-bid meetings. The queries at serial number 39, 40, 59 and 60 related to Item No. 18 of the Contract Data. After noting the clarifications/replies to the said queries, the majority came to the conclusion that the clarifications were also made part of the contract by NHAI. The majority further noted that Clause 110.3 of the TS was more or less similar to Item No. 18 of the Contract Data. It was in the above context that the AT undertook a further analysis and came to the conclusion that the contractor could not be denied compensation on account of the delay caused in completion of the work by NHAI.

18. The core issue is the extent to which HCC was entitled to compensation as a result of the EOT granted. As rightly pointed out by Mr Krishnan appearing for HCC, the Engineer had, in fact, not approved of the entire EOT of 1142 days as claimed by HCC. The extended period of completion was only from 19th February, 2007 to 15th June, 2009. Para 2.9 of the of

Statement of Claim filed by HCC makes it clear that HCC accepted the reduced EOT for completion of Milestone 3 and whole of the works. Paragraphs 2.9, 2.10 and 2.11 of the Statement of Claim make this plain:

"2.9. In the meanwhile, the Claimant completed the whole of the works except Chandikhol intersection, which was getting delayed due to delay in acquiring land/handing over of site for work. The Respondent was desirous of putting the completed works for commercial use. In this regard, the Respondent and the Claimant entered into a supplementary agreement to treat the Chandikhol intersection as outstanding work to be completed during defect liability period, and to issue the substantial completion certificate for whole of the works. Accordingly, the Engineer had issued the Substantial Complete Certificate for whole of the works with effect from 15.06.2009. Taking the above into consideration, the Respondent reduced the Extension of Time determined by the Engineer and approved the Extension of Time determined by the Engineer and approved the Extension of Time upto 15.06.2009 for completion of Milestone 3 and whole of the works. Even though the Claimant was to incur additional cost for the balance works, the Claimant had agreed as a goodwill measure and accepted the same to give quietus to the issue.

2.10. Thus, the Extension of Time determined by the Engineer till 15.06.2009 for the delay/compensation events. which has been also approved by the Respondent was on account of the events not attributable to the Claimant. Thus the same has become admitted/agreed position in the present dispute.

2.11. As a direct consequence of the delays/compensation events, the Claimant was compelled/forced to stay at the project site with all his manpower and various other resources to ensure satisfactory completion of the works in the extended period. This had resulted in the Claimant

incurring substantial huge losses and additional costs, which could not have been reasonably foreseen and or provided for in the contract price at the time of bid submission. But for the delays and preventions caused by the Respondent, the Claimant would not have incurred these huge additional costs."

19. The majority proceeded on the basis of the documents and calculations produced by HCC which were supported by the certificate of a Chartered Accountant (CA). In that view of the matter, the Court accepts the contention of HCC that the observations of the AT that Item No. 18 of the Contract Data was hit by Section 23 of the Contract Act makes no difference to the decision on this aspect. The fact of the matter is that both NHAI and HCC accepted the Engineer‟s determination of the EOT. It was not open to NHAI to later challenge the determination of the EOT by the Engineer and the compensation claimed on that basis. The decisions in Kailash Nath Associates v. New Delhi Municipal Committee (supra) and M/s Chugh Kathuria Engineers (P) Ltd. v. Delhi Development Authority (supra) relied upon by Mr Kapoor turned on their own facts. Here there is no automatic presumption that NHAI was responsible for the delay on account of the grant of EOT. The majority Award is based on what was approved by the Engineer as well as by the NHAI.

20. As explained by the Supreme Court in Kailash Nath Associates v. DDA (2015) 4 SCC 136 and Associate Builders v. DDA (2015) 3 SCC 49 the threshold for review of the arbitral Award by the Court with an Award in exercise of its powers under Section 34 of the Act is high. Unless the Award is perverse to the extent of shocking the judicial conscience, it should not be

interfered with. The challenge by the NHAI to the impugned majority Award on this aspect fails to meet this threshold. The Court, therefore, does not find any merit in the contention of NHAI as regards the grant of compensation to HCC consequent upon the EOT as determined by the Engineer.

21. The next ground urged by Mr. Kapoor, learned counsel for NHAI, was that the majority Award failed to appreciate that the disputes raised were barred under the provisions of Order II Rule 2 of the Code of Civil Procedure (CPC). In particular, he pointed out that the AT in a earlier Award had granted EOT for all the three milestones. Therefore, the claim to compensation arising out of the same cause of action would be hit by Order II Rule 2 CPC.

22. On the other hand, Mr. Dayan Krishnan, learned Senior counsel for HCC pointed out that the earlier arbitration was with respect to Dispute No. 3. By the Award dated 12th August, 2013, the AT had taken the EOT as 1349 days. That Award became necessary as a result of the failure of the Engineer to determine the EOT. As far as the present arbitration was concerned, it was after completion of the works and the determination by the Engineer of the compensation to which HCC was entitled. A wrong determination of such cost led to the present arbitration. Reliance is placed on the decision of the Supreme Court in Infrastructure Leasing & Financial Services Ltd. v. BPL Ltd. (2015) 3 SCC 363.

23. The Court is of the view that the entire submission of NHAI as regards Order II Rule 2 CPC is misconceived. The majority has in paragraphs 14.2

and 14.3 of the Award dealt with the above issue and rejected it after finding that Dispute No. 6 related to a claim for the additional extended period for completion of the whole works. This claim arose only after the final determination of the EOT for the whole of the work on 14th May 2009. Dispute No.3 on the other hand arose as a result of the failure to determine EOT for the whole works. HCC had gone before the Dispute Resolution Board (DRB) who decided the EOT only in respect of Milestones 1 and 2. Since the works under Milestone 3 were still in progress and impediments still existed, the DRB directed the Engineer to determine the EOT for the whole of the work after removing the impediments. Being dissatisfied with the above recommendations of the DRB, NHAI invoked the arbitration and that is how Dispute No. 3 was referred to arbitration. The reference of Dispute No. 6 to arbitration was made much thereafter on 18th March, 2011.

24. The decision of the Supreme Court in Infrastructure Leasing & Financial Services Ltd. v. BPL Ltd. (supra) supports the contention of HCC in this regard. In the said decision the Court noticed its earlier decision in S. Nazeer Ahmed v. State Bank of Mysore (2007) 11 SCC 75 and held that for Order II Rule 2 CPC to apply, the cause of action in the two suits should have been similar. The Court, therefore, concurs with the majority of the AT that the cause of action for Dispute No. 6 is distinct and different from Dispute No. 3 and, therefore, not be hit by the principle governing Order II Rule 2 CPC.

25. Lastly, NHAI has challenged the quantification of claims of HCC as not being based on any acceptable or credible evidence. As regards the claim

under sub-head No. 1 for Rs. 62.11 crores towards overhead costs for the extended period, the Engineer had accepted the claim only to an extent of Rs. 27.38 crores on the basis of the percentages of the overheads as specified in the MORT&H data book. The majority reviewed the above quantification by relying on the CA‟s certificate. The majority compared the overheads against the value of the total work done. It allowed only 26% of the base cost of the work done.

26. The claim under sub-head No. 2 was for additional expenses on account of extended stay of plant and equipments for the extended period. HCC had produced the extracts of the minutes of the meeting of the progressive reports issued by the Engineer showing the list of equipments deployed at the site on a month-to-month basis. NHAI did not question the veracity of the above documents. The Engineer relied upon these documents to arrive at the figure of Rs.17.58 crores. This was modified by the AT and after rejecting HCC‟s head of claims and expenditure, the AT determined the amount at Rs. 32.96 crores.

27. As regards the claim under sub-head no. 3, the AT considered overheads at 26% and worked out the amount payable as Rs. 4.47 crores.

28. In examining each of the above claims, the majority has discussed the evidence on record in great detail and arrived at a reasoned conclusion. There is nothing pointed out by NHAI which even remotely meets the threshold requirement of interference with the majority Award viz., the Award having to be opposed to the fundamental policy of Indian Law.

29. On the issue of interest, Mr. Krishnan relied on the decision of this Court in NHAI v. ITD Cementation Ltd. (2008) 100 DRJ 431 which was upheld by the Supreme Court in NHAI v. ITD Cementation Ltd (2015) 14 SCC 21 dismissing NHAI's appeal. There, the interest granted was 12% to be compounded monthly whereas in the present case, the AT has granted HCC simple interest at 12% per annum.

30. For the above reasons, the Court is not persuaded to interfere with the impugned majority Award on merits. The petition is, accordingly, dismissed with costs of Rs. 50,000 which will be paid by NHAI to HCC within four weeks.

S.MURALIDHAR, J JANUARY 24, 2017 rd

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter