Citation : 2016 Latest Caselaw 6163 Del
Judgement Date : 21 September, 2016
$~26
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ O.M.P.(I) (COMM.) 377/2016
ZILLION INRAPROJECTS PVT LTD ..... Petitioner
Through : Mr Saurabh Kirpal, Mr Naveen
Sharma, & Ms Swati Bhushan
Sharma, Advocates.
versus
ALSTOM SYSTEMS INDIA (P)
LIMITED & ANR. ..... Respondents
Through : None.
CORAM:
HON'BLE MR. JUSTICE VIBHU BAKHRU
ORDER
% 21.09.2016 VIBHU BAKHRU, J IA No.11700-01/2016 1. Allowed, subject to all just exceptions. 2. The applications are disposed of. O.M.P.(I) (COMM.) 377/2016
3. The petitioner (hereafter 'ZIPL') has filed the present petition under
Section 9 of the Arbitration and Conciliation Act, 1996 (hereafter 'the Act'),
inter alia, praying as under:-
"(i) Grant Ad-interim ex-parte Stay and Suspend the enforcement of the letter dated 16.09.2016 issued for the
termination of the sub contract until the resolution or adjudication of disputes between the parties by way of mediation or arbitration ; and
(ii) Direct the Respondent No. 1 to maintain status quo at the work sites and permit the petitioner to proceed further with the execution of the project which is of a national importance until the resolution or adjudication of disputes between the parties and;
(iii) Restrain the Respondent no. 1 from encashing the Performance Bank Guarantee BG - 1003 dated 14.12.2015 for an amount of Rs.20,000,000/- (Rupees Two Crores only) and;
(iv) Restrain the Respondent No. 1 from encashing the Performance Bank Guarantee BG - 17115 Dated 14.12.2015 for an amount of Rs.30,000,000/- (Rupees Two Crores only) and;
(v) Restrain the Respondent No: 1 from encashing the Performance Bank Guarantee BG - 0013 dated 16.12.2015 for an amount of Rs. 91,06,047/- (Rupees Ninety One Lacs Six Thousand Forty Seven only) and;
(vi) Restrain the Respondent No. 1 from encashing the Bank Guarantee BG - 3116 dated 17.02.2016 for an amount of Rs. 59,06,047/- (Rupees Fifty Nine Lacs Six Thousand Forty Seven only) and;
(vii) Restrain the Respondent No. 1 from encashing the Bank Guarantee BG - 0000124 dated 18.02.2016 for an amount of Rs. 90,00,000/- (Rupees Ninety Lacs only) and;
(viii) Restrain the Respondent No. 1 from encashing the Bank Guarantee BG - 3516 dated 18.02.2016 for an amount of Rs. 14,100,000/- (Rupees One Crore Forty One Lacs only) and;
(ix) Restrain the Respondent No. 1 from encashing the Bank
Guarantee BG - 0001 dated 19.02.2016 for an amount of Rs. 30,100,000/- (Rupees Three Crores One Lac only)."
4. Briefly stated, the controversy in the present petition arises in the
following context:
4.1 Respondent no.2, a Public Sector Undertaking, had entered into a
contract with respondent no.1 (hereafter 'Alstom') on 21.07.2015, for
performance of works relating to design, construction, supply, installation,
testing and commissioning of 2 x 25 KV AC 50 Hz electrification signalling
7 telecommunication and associated works of double track railway lines
under construction for Bhaupur Khurja section of eastern dedicated freight
corridor.
4.2 Alstom in turn entered into a contract with ZIPL on 24.09.2015
(hereafter 'sub-contract agreement') whereby the works agreed to be
performed by Alstom under the contract dated 21.07.2015 with respondent
no.2, were sub-contracted to ZIPL. In terms of the sub-contract agreement,
ZIPL submitted bank guarantees - 7 in number - for an aggregate sum of
`11,82,12,094/-. Three bank guarantees were furnished as performance
securities and four bank guarantees were issued to secure the mobilisation
advance advanced by Alstom to ZIPL. The details of the bank guarantees are
as under:-
S. BG Date BG Number Amount Type of BG
No.
1. 14.12.2015 0480315BG0001003 20,000,000 Performance
Security
2. 14.12.2015 1988ILG017115 30,000,000 Performance
Security
3. 16.12.2015 003GT02153500013 9,106,047 Performance
Security
4. 17.02.2016 1988ILG003116 5,906,047 ADVANCE
5. 18.02.2016 0480316BG0000124 9,000,000 ADVANCE
6. 18.02.2016 0007BGR0083516 14,100,3000 ADVANCE
7. 19.02.2016 499INGL160500001 30,100,000 ADVANCE
4.3 Alstom alleges that the ZIPL had offered "unethical inducement" to
the Deputy Team Leader. It is also alleged that ZIPL had delayed the
performance of the sub-contract agreement. And, for the aforesaid alleged
reasons, Alstom has - by a letter dated 16.09.2016 - terminated the sub-
contract agreement with effect from 23.09.2016. According to ZIPL, Alstom
is also threatening to invoke the bank guarantees furnished by ZIPL and this
has led ZIPL to file the present petition.
Submissions
5. Mr Saurabh Kirpal, the learned counsel appearing for ZIPL contended
that the termination of the sub-contract agreement by Alstom was wrongful
and would irretrievably prejudice ZIPL. He further submitted that the
invocation of the bank guarantees would also cause an irretrievable harm to
ZIPL. He referred to Minutes of Meeting held on 15.09.2016 under the
Chairmanship of the director of respondent no.2 and drew the attention of
this court to the following paragraph:-
"Question was put up to ASIPL representative by Director (DFCCIL) for the delay in the Design & drawings submission to SAI TYPSA and discussed regarding the progress of Slice 101, Slice 102 and Slice 103 and replied by ASIPL that they have completed the excavation work at Khurja, Daud Khan, Hathras, Bhadan and Layout at Makhanpur and Bhaupur has been done and excavation will be started at these stations by 19th September, he also confirmed that all the three slices are mobilized and already for starting the construction as soon as the drawings are finalized. SAI TYPSA also stated that they have already cleared the excavation drawings submitted by ASIPL for Khurja, Daud Khan, Hathras, Bhadan, Makhanpur, Kanchausi & Bhaupur. ASIPL also confirmed that they are starting the PCC at Bhadan Crossing Station on 17.09.16.
ASPIL also confirmed that Architectural Drawing for OCC Site is ready for submitting and they will submit the same to SAI TYPSA on 15.09.16 and complete set with CD on 19.09.16."
6. He submitted that it is apparent from the above that Alstom had
admitted that ZIPL had mobilized its resources and had also completed part
of excavation works at certain sites; and, therefore, there could be no dispute
that ZIPL had mobilized its resources. He contended that in the
circumstances, there was no ground for Alstom to invoke the bank
guarantees furnished to secure the mobilization advance and such invocation
would be fraudulent.
7. He further submitted that both the performance bank guarantees and
bank guarantees furnished for securing mobilization advance, could not be
invoked simultaneously. He submitted that the performance bank
guarantees could be invoked only if ZIPL had not performed the sub-
contract and the bank guarantees for mobilization advance could be invoked
only if the ZIPL had failed to mobilize its resources. He submitted that if
the Alstom invoked the mobilization advance, it was obvious that the
question of performance of the contract, which would be at much later point
of time, had not arisen. Similarly, if Alstom invoked the performance bank
guarantees, it would imply that the stage of mobilisation had been
successfully cleared.
Reasoning and Conclusion
8. In terms of the sub-contract agreement, ZIPL was to submit the
drawings, which were to be finalised by Alstom. In its petition, ZIPL has
stated that Alstom did not have any competent technical staff to provide the
requisite inputs for designing and subsequent submission of drawings. It is
further pleaded that although ZIPL had submitted its designs and drawings,
the same were not approved by Alstom for the aforesaid reason.
9. ZIPL has further stated that it was the responsibility of Alstom to
handover the sites free from all hindrances for carrying out the works under
the sub-contract agreement but it had failed to do so. According to ZIPL, it
had mobilised all resources, however, the same remained idle for want of
unhindered sites. It is stated that ZIPL had also raised claims for idling of
staff and equipment which was mobilised at site. ZIPL alleges that from the
very inception, Alstom had the intention of cheating ZIPL. It is further
alleged that Alstom fraudulently released an advance mobilisation amount of
only `5.91 crores as against the total expenditure of `10.43 crores
(approximately) incurred by ZIPL. ZIPL further claims that despite ZIPL
mobilising the resources and commencing works, Alstom has fraudulently
chosen to terminate the contract by the letter dated 16.09.2016. It is claimed
that this has been done by Alstom to hide its lack of capability and
competence and to make ZIPL a scapegoat for non performance of the sub-
contract agreement and Alstom's contract with respondent no.2.
10. A plain reading of the petition as well as documents annexed with the
petition indicates that there are disputes between the ZIPL and Alstom with
regard to performance of the sub-contract agreement. In its communications
- particularly letters dated 13.05.2016 and 07.07.2016 - Alstom has alleged
that ZIPL has failed to perform the sub-contract agreement in accordance
with its terms. The letters on record also indicate that Alstom had sent other
letters, presumably to the same effect, however the same have not been
placed on record. According to Alstom, ZIPL is responsible for delay in
performance of the sub-contract agreement as it is alleged that ZIPL had (a)
delayed submission of the project document and design; (b) delayed
carrying out site surveys and geo-technical investigation; and (c) delayed
commencement and progress of construction activity. ZIPL does not dispute
that the execution of the sub-contract has been delayed but disputes
Alstom's allegation that the delay in execution of the sub-contract
agreement is attributable to it; it is ZIPL's case that the delay has been
caused due to various grounds solely attributable to Alstom.
11. It is, thus, an admitted fact that performance of the sub-contract
agreement has been delayed. The question whether ZIPL is responsible for
the delay or whether delay has been caused due to Alstom, is a question to
be decided by the Arbitral Tribunal as and when constituted. However, this
dispute cannot be the ground for restraining invocation of the bank
guarantees. It is well settled that bank guarantees can be interdicted only in
exceptional circumstances such as egregious fraud, special equities and
irretrievable injury.
12. In Svenska Handelsbanken v. M/s. Indian Charge Chrome and
Others: (1994) 1 SCC 502, the Supreme Court had held as under:-
"...in case of confirmed bank guarantees/irrevocable letters of credit, it cannot be interfered with unless there is fraud and irretrievable injustice involved in the case and fraud has to be an established fraud...
...irretrievable injustice which was made the basis for grant of injunction really was on the ground that the guarantee was not encashable on its terms... ...there should be prima facie case of fraud and special equities in the form of preventing irretrievable injustice between the parties. Mere irretrievable injustice without prima facie case of established fraud is of no consequence in restraining the encashment of bank guarantee."
13. The aforesaid view was reiterated by the Supreme Court in Larsen &
Toubro Limited v Maharashtra State Electricity Board and Others: (1995)
6 SCC 68.
14. In U.P. Cooperative Federation Limited v. Singh Consultants and
Engineers Pvt. Ltd.: 1988 (1) SCC 174, the Supreme Court had held as
under:
"The nature of the fraud that the Courts talk about is fraud of an "egregious nature as to vitiate the entire underlying transaction". It is fraud of the beneficiary, not the fraud of somebody else."
15. Although, in Hindustan Steel Works Construction Ltd. v. Tarapore
& Co. and Anr.: AIR 1996 SC 2268 the Supreme Court has held that fraud
could be at subsequent stage also, the law that the fraud must be of
egregious nature affecting the underlying transaction has not been differed
with. In that case, the Court held as under:
"We are, therefore, of the opinion that the correct position of law is that commitment of banks must be honoured free from interference by the courts and it is only in exceptional cases, that is to say, in case of fraud or in a case where irretrievable injustice would be done if bank guarantee is allowed to be encashed, the court should interfere. In this case fraud has not been pleaded and the relief for injunction was sought by the contractor/Respondent 1 on the ground that special equities or the special circumstances of the case required it. The special circumstances and/or special equities which have been pleaded in this case are that there is a serious dispute on the question as to who has committed breach of the contract, that the contractor has a counter-claim against the appellant, that the
disputes between the parties have been referred to the arbitrators and that no amount can be said to be due and payable by the contractor to the appellant till the arbitrators declare their award. In our opinion, these factors are not sufficient to make this case an exceptional case justifying interference by restraining the appellant from enforcing the bank guarantees. The High Court was, therefore, not right in restraining the appellant from enforcing the bank guarantees."
16. The allegation that Alstom intended to cheat ZIPL from the inception
cannot be readily accepted. Further, it is also not disputed that Alstom had
provided the mobilization advance to ZIPL and thus, would be entitled to
recover the same. Merely stating that the invocation of the bank guarantees
is fraudulent or that Alstom intended to cheat ZIPL from the inception is not
sufficient. It is necessary that particulars indicating an egregious fraud are
pleaded and a prima facie case of such fraud is established for securing an
order interdicting an unconditional bank guarantee. The present case is,
plainly, one of contractual disputes as to which party has delayed the
performance of the works to be executed under the sub-contract agreement.
The entire purpose of insisting on an unconditional bank guarantee would be
frustrated if the beneficiary is required to have such disputes adjudicated as
a precondition for invoking the bank guarantee.
17. Mr Kirpal's contention that the bank guarantees furnished for
securing the mobilization advance and for securing the performance of the
sub-contract agreement cannot be invoked simultaneously, is also bereft of
any merit. Clearly, the bank guarantees for mobilization advanced were
furnished for securing the recovery of the mobilization advance, which in
terms of the sub-contract would be recovered through deductions from the
amounts payable to ZIPL against its invoices. In the present case, Alstom
has terminated the sub-contract agreement and, therefore, the question of
adjusting any amount from ZIPL's invoices does not arise. The
performance bank guarantees have been furnished for performance of the
sub-contract agreement and according to Alstom, ZIPL has failed to perform
the sub-contract agreement. Thus, there is no intrinsic conflict or
repugnancy in invoking both kinds of bank guarantees. The contention that
invocation of performance bank guarantees and bank guarantees furnished
against mobilization advanced are mutually exclusive cannot be accepted.
18. Mr Kirpal's contention that the bank guarantees furnished to secure
mobilisation cannot be invoked as ZIPL had mobilized its resources at site is
also unmerited. Even if it is assumed that ZIPL had mobilized its resources,
the fact that the contract has been terminated, would entitle Alstom to
recover the advance provided by Alstom by invoking the bank guarantees
notwithstanding the dispute whether the termination is wrongful on not. In
U.P State Sugar Corporation v Sumac International Limited: AIR 1997
SC 1644, the Supreme Court had held that:
"12. The law relating to invocation of such bank guarantees is by now well settled. When in the course of commercial dealings an unconditional bank guarantee is given or accepted, the beneficiary is entitled to realize such a bank guarantee in terms thereof irrespective of any pending disputes. The bank giving such a guarantee is bound to honour it as per its terms irrespective of any dispute raised by its customer. The very purpose of giving such a bank guarantee would otherwise be defeated."
19. In Hindustan Construction Co. Ltd. v State of Bihar & Ors.: (1999)
8 SCC 436, the Supreme Court observed as under:
"8. Now, a Bank Guarantee is the common mode, of securing payment of money in commercial dealings as the beneficiary, under the Guarantee, is entitled to realise the whole of the amount under that Guarantee in terms thereof irrespective of any pending dispute between the person on whose behalf the Guarantee was given and the beneficiary. In contracts awarded to private individuals by the Government, which involve huge expenditure, as, for example, construction contracts, Bank Guarantees are usually required to be furnished in favour of the Government to secure payments made to the contractor as "Advance" from time to time during the course of the contract as also to secure performance of the work entrusted under the contract. Such Guarantees are encashable in terms thereof on the lapse of the contractor either in the performance of the work or in paying back to the Government "Advance", the Guarantee is invoked and the amount is recovered from the Bank."
20. Insofar as the prayer for staying the letter of termination dated
16.09.2016 is concerned, the same would not be permissible. Admittedly,
the sub-contract agreement is a determinable agreement and in terms of
Section 14 of the Specific Relief Act, 1963, the sub-contract agreement
cannot be specifically performed.
21. For the reasons stated above, the petition is dismissed.
22. Dasti under signatures of the court master.
VIBHU BAKHRU, J SEPTEMBER 21, 2016 RK/MK
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!