Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Ganga Contracts And Projects Ltd. vs Indian Railway Welfare ...
2016 Latest Caselaw 6051 Del

Citation : 2016 Latest Caselaw 6051 Del
Judgement Date : 16 September, 2016

Delhi High Court
Ganga Contracts And Projects Ltd. vs Indian Railway Welfare ... on 16 September, 2016
$~50
*      IN THE HIGH COURT OF DELHI AT NEW DELHI
+      OMP 36/2016
       GANGA CONTRACTS AND PROJECTS LTD. ..... Petitioner
                          Through:     Mr Salar M. Khan, Mr Changhel
                                       Khan, Mr Abhishek Kumar and Mr
                                       Ausaf Malik, Advocates.
                          versus
       INDIAN RAILWAY WELFARE ORGANISATION ..... Respondent
                    Through:
       CORAM:
       HON'BLE MR. JUSTICE VIBHU BAKHRU
                    ORDER
       %            16.09.2016

VIBHU BAKHRU, J (ORAL)

IA No. 11433/2016

1. Exemption is allowed, subject to all just exceptions.

2. The application stands disposed of.

OMP 36/2016

3. The petitioner has filed the present Petition under Section 9 of the

Arbitration & Conciliation Act, 1996, praying as under:-

"A. Issue ex parte direction, to be confirmed after notice of motion, to the respondent to maintain status quo, in respect of the contract dated 20.07.2015, awarded to the petitioner for construction of single storied row houses including 2 Nos. Community buildings, guard room,

shops and all external services at IRWO's Rail Vihar, Kota (Rajasthan) (Agreement dated 20.07.2015).

B. Issue ex parte direction to the respondent, to be confirmed after notice of motion, that the Bank Guarantee of Rs. 66, 69,000/-, submitted by the petitioner, shall not been cashed;

C. Direct the respondent to attempt settlement of dispute through mutual settlement/conciliation m terms of the agreement dated 20.07.2015."

4. The petitioner, Ganga Contracts and Projects Limited, claims to be a

reputed contractor and had bid for award of contract for "CONSTRUCTION

OF SINGLE STOREYED ROW HOUSES INCLUDING 2 NOS

COMMUNITY RUILDINGS, GUARD ROOM , SHOPS, AND ALL

EXTERNAL SERVICES AT IRWO'S RAIL VIHAR, KOTA

(RAJASTHAN)" (hereafter „the Project‟) pursuant to bids invited by the

respondent (hereafter 'IRWO').

5. The petitioner's bid was accepted and consequently IRWO entered

into a contract dated 20.07.2015 (hereafter 'the Contract') for the

construction of the Project. The petitioner states that right from the start its

relationship with officials of IRWO was "not smooth"; the officials raised

frivolous objections and made unreasonable deductions. It is stated that

issues pertaining to delay and unreasonable deductions from running bills

persisted and that in turn affected the petitioner's discharge of payment

obligations to its staff, workers and other suppliers.

6. The petitioner further states that an incident took place on 27.06.2015,

where the Site Engineer was stopped by certain workers, who demanded to

know the status of payments by IRWO to the petitioner. IRWO alleged that

the Site engineer had been gheraoed by the petitioner's labourers. The

learned counsel for the petitioner submits that the said incident was

exploited by certain vested interests and the relationship between the

petitioner and IRWO deteriorated considerably.

7. It is stated that thereafter, IRWO sent a letter dated 12.07.2016

alleging that the progress of works at site was slow. It is stated that the

aforesaid letters were followed by letters - five in number as listed in

paragraph IV (x.) of the petition - alleging that the progress of work was

poor. It is petitioner‟s case that the said letters were not responded to on the

advice of IRWO's officials.

8. Thereafter, IRWO sent a letter dated 31.08.2016, inter alia, stating

that the work of the petitioner was not satisfactory and further alleging that

petitioner had abandoned the work for more than two months. The letter

clearly indicated that it was a notice in terms of clause 6.3 (vi, vii & viii) and

clause 6.4 on IRWO General Conditions of Contract. The petitioner was put

to notice that if he did not show progress of work during the period of seven

days, IRWO would terminate the contract as per conditions of the Contract.

9. The petitioner responded to the aforesaid letter on 1.9.2016 admitting

the delays in execution of the work but attributed the same to heavy rains in

the locality and deductions made by IRWO in the last RA (running) Bill

submitted by the Petitioner. The petitioner also assured IRWO that it would

speed up the progress of the works.

10. Thereafter, on 7.9.2016, IRWO sent a notice in terms of clause 6.4 of

the Contract. It was alleged that the work had been stopped since 26.06.2016

and despite the notice dated 31.08.2016, the work had not commenced.

IRWO disputed that there were abnormal rains in the locality, which

affected the mobilisation of resources at site. The notice clearly stated that

on expiry of the 48 hours, the Contract would stand rescinded with the right

to IRWO to forfeit the whole security deposit and encash the performance

bank guarantee in terms of clause 7.1 of the Contract. This letter was

responded to by the petitioner on 10.09.2016. The petitioner stated that it

had commenced work on the project site under protest and had mobilized

the labour at site.

11. Thereafter, the petitioner has communicated to the Managing

Director, IRWO seeking his intervention and also for conciliation

proceedings to resolve their disputes.

12. Mr Khan, the learned counsel for the petitioner submitted that the

termination of the Contract was not in terms of the Contract as no attempt

had been made for resolution of the disputes by conciliation proceedings as

contemplated under clause 7.1 of the Contract. He contended that if status

quo as to the Contract is not granted, the petitioner‟s right for resolution of

its disputes by conciliation proceedings in terms of clause 7.1 of the

Contract would stand frustrated. He further contended that the termination of

the Contract was malafide and, therefore, IRWO ought to be restrained from

giving effect to such termination. Lastly, he contended that in terms of

clause 7.1 of the Contract, petitioner had a right for attempting resolution of

the disputes by reconciliation and therefore, IRWO ought to be directed to

commence such proceedings.

13. I have heard the learned counsel for the petitioner.

14. It is apparent from the above narrated facts that there are disputes

between the parties as regards the progress of the work. It is IRWO's stand -

as evident from its letters as referred above - that the Petitioner's progress of

the work was poor and therefore, the IRWO had proceeded to terminate the

Contract. Admittedly, several letters written by IRWO pointing out that the

petitioner‟s work was not measuring up to the progress required, were not

responded to. The disputes as to whether the petitioner had justifiable

reasons for delay in execution of the works and whether the termination was

wrongful are matter of disputes which would require to be adjudicated. At

this stage, it is difficult to take a prima facie view that the termination of

Contract was wrongful.

15. What the petitioner essentially wants is an order directing IRWO to

continue with the Contract. It is difficult to understand as to how such relief

can be granted.

16. Furthermore, the Contract is a determinable one and, therefore, by

virtue of Section 14 of the Specific Relief Act, 1963, the Contract is not

specifically enforceable. In the circumstances, an order injuncting IRWO

from giving effect to its termination cannot be granted.

17. The contention that the IRWO has not followed the procedure for

termination in as much as it has not resorted to conciliation procedure prior

to termination of the Contract, in terms of clause 7.1.1 of the Contract, is

also without merit. Clause 7.1.1 of the Contract is set out below:

"7.1.1 Conciliation

7.1.1.1 It is a term of this contract that Arbitration of disputes shall not be commenced unless an attempt has first been made by the parties to settle such disputes through mutual settlement / conciliation within a period of thirty (30) days.

7.1.1.2. If the Contractor is not satisfied with the settlement by the IRWO on any matter in question, disputes or differences, the Contractor may refer to the Managing Director of IRWO in writing to settle such disputes or differences through conciliation provided that demand for conciliation shall specify the matters, which are in question or subject of the disputes or differences as also the amount of claim, item wise. Only such disputes or differences in respect of which the demand has been made, together with counter claim of IRWO shall be referred to Conciliator as the case may be and other matters shall not be included in the reference.

7.1.1.3. Managing Director of IRWO may himself act as a Sole Conciliator or May decides to appoint another person as Conciliator as the case may be.

7.1.1.4. If one or more Conciliator(s) appointed as above refuses to act or a bitrarily withdraw from his office as Conciliator or vacates his/their office or offices or is/are unable or unwilling to perform his functions as

Conciliator(s) for any reasons, whatsoever or dies or in the opinion of Managing Director, IRWO fails to act without undue delay, the Managing Director IRWO shall appoint new Conciliator(s) in his/their place. Such reconstituted tribunal may, at its discretion, proceed with the reference from the stage at which it was left by the previous Conciliator(s).

7.1.1.5. The demand for conciliation is subject to Arbitration and Conciliation Act, 1996 and the rules there under and any statutory modification thereof shall apply to the Conciliation proceedings under this clauses"

18. As is apparent from the above, clause 7.1.1 provides that the parties

must, in the first instance, make an attempt to settle the disputes by mutual

settlement/conciliation before proceeding to refer the disputes for

arbitration; this is a part of dispute resolution mechanism agreed to between

the parties. The said clause does not preclude IRWO from terminating the

contract in terms thereof, without referring the disputes to conciliation.

19. In so far as the relief of injuncting encashment of the performance

bank guarantee is concerned, the correspondence on record indicates that it

is an admitted position that the performance of the work was slow; the

disputes essentially relate to whether the work suffered on account of

wrongful deduction from the running bills or on account of force majeure

events. The said dispute cannot be examined in the present proceedings. The

law as relating to interdicting invocation of bank guarantees is now well

settled.

20. In Larsen & Toubro Limited v Maharashtra State Electricity Board

and Others: (1995) 6 SCC 68, the Supreme Court referred to the earlier

decision in Svenska Handelsbanken v. M/s. Indian Charge Chrome and

others: (1994) 1 SCC 502 and held as under:-

"5. Before we adjudicate the rival pleas urged before us by counsel for the parties, it will be useful to bear in mind the salient principles to be borne in mind by the court in the matter of grant of injunction against the enforcement of a bank guarantee / irrevocable letter of credit. After survey of the earlier decisions of this Court in United Commercial Bank v Bank of India, U.P. Coop. Federation Ltd. v Singh Consultants & Engineers (P) Ltd., General Electric Technical Services Co. Inc v Punj Sons (P) Ltd. and the decision of the Court of Appeal in England in Elian and Rabbath v Matsas and Matsas and a few American decisions, this Court in Svenska Handelsbanken v. Indian Charge Chrome AIR 1994 SC 626, laid down the law thus:

"...in case of confirmed bank guarantees/irrevocable letters of credit, it cannot be interfered with unless there is fraud and irretrievable injustice involved in the case and fraud has to be an established fraud... ....irretrievable injustice which was made the basis for grant of injunction really was on the ground that the guarantee was not encashable on its terms... ...there should be prima facie case of fraud and special equities in the form of preventing irretrievable injustice

between the parties. Mere irretrievable injustice without prima facie case of established fraud is of no consequence in restraining the encashment of bank guarantee.""

21. The petitioner has also prayed that IRWO be directed to attempt

settlement of dispute through mutual settlement/conciliation in terms of the

Contract. Clearly, the petitioner would be entitled to insist that parties make

an attempt to mutually settle the disputes as agreed under the Contract. The

parties have agreed that arbitration would not be commenced unless a

demand is made by the parties to settle the disputes through mutual

settlement/conciliation within a period of 30 days. The petitioner has, by a

letter dated 12.09.2016, called upon the Managing Director of IRWO to act

as a sole conciliator or to appoint any other person for the conciliation

proceedings.

22. In the circumstances the Managing Director of IRWO is directed to

ensure that a fair attempt is made to settle the disputes by mutual settlement/

conciliation within the specified period of 30 days as agreed under the

Contract.

23. The present petition is disposed of with the aforesaid observation.

24. Order Dasti under the signature of Court Master.

VIBHU BAKHRU, J

SEPTEMBER 16, 2016 pkv

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter