Citation : 2016 Latest Caselaw 6042 Del
Judgement Date : 16 September, 2016
*IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of decision: 16th September, 2016
+ W.P.(C) No.3821/2014.
ROSA POWER SUPPLY CO. LTD. .... Petitioner
Through: Dr. A.M. Singhvi, Sr. Adv. with Mr.
Sujit Ghosh, Mr. Shashank Shekhar, Mr.
Nakul Mohta, Ms. Parul Shukla and Mr.
Rishi Aggarwal, Advs. for Review
Petitioner.
Versus
UNION OF INDIA & ORS. ..... Respondents
Through: Mr. Sanjay Jain, ASG with Mr. Dev P.
Bhardwaj, CGSC and Mr. Vidur Mohan,
Adv. for UOI.
Mr. Sujit Ghosh with Ms. Kanupriya
Bhargava, Advs. for applicant in CM
No.23810/2015.
CORAM:-
HON'BLE THE CHIEF JUSTICE
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
RAJIV SAHAI ENDLAW, J
Review Petition No.542/2014.
1. The petitioner filed this petition impugning the four orders, all dated 21st
March, 2011 of the respondent no.3 Zonal Joint Director General of Foreign
Trade, intimating to the petitioner the decision taken in the meeting of the
Policy Interpretation Committee held on 15th March, 2011 under the
Chairmanship of the Director General of Foreign Trade, of denying Deemed
Export Benefits (DEB) "if the Bill of Entry is in the name of the project
authority", as was in the case of the petitioner and accordingly denying the
DEB to the petitioner. The petition also impugns the minutes of the said
meeting dated 15th March, 2011 and seeks a direction to the respondents to give
the DEB in the sum of Rs.72 crores to the petitioner.
2. Arguments on the petition were heard on 21st July, 2014 and judgment
reserved.
3. Vide detailed judgment dated 12th August, 2014, the petition was
dismissed.
4. The petitioner seeks review, inter alia pleading that Special Leave to
Appeal (C) No.28644/2014 was preferred before the Supreme Court against
our judgment dated 12th August, 2014 and which was disposed of as withdrawn
on 7th November, 2014 with liberty to the petitioner to file review petition and
with a request to this Court to consider the review petition in accordance with
law and with the clarification that if the review petition fails, the petitioner will
be at liberty to question not only the judgment dated 12 th August, 2014 but also
the order in the review petition.
5. Notice of the review petition was issued and a reply thereto filed and to
which a rejoinder has been filed by the petitioner.
6. The senior counsel for the petitioner/review applicant was heard on 21st
April, 2015 and 11th September, 2015.
7. CM No.23810/2015 has been filed by M/s Simplex Infrastructures Ltd.
for intervention in the review petition pleading that it has filed W.P.(C)
No.3200/2015 and W.P.(C) No.3257/2015 in this Court making the same
challenge as made in this petition and the hearing of which has been deferred
till the disposal of this review petition filed by the petitioner and seeking
intervention therein.
8. The senior counsel for the petitioner/review applicant and the learned
Additional Solicitor General (ASG) appearing for the respondents were heard
further on 22nd July, 2016 and order reserved.
9. We had vide our judgment dated 12th August, 2014, of which review is
sought, dismissed the writ petition for the reasons (i) that the claim in the
petition was in the nature of a monetary claim and the writ petition was not
maintainable; (ii) that the limitation for a suit for recovery of amount illegally
appropriated by the Government is governed by Article 62 of the Schedule to
the Limitation Act, 1908 corresponding to Article 24 of the Limitation Act,
1963; (iii) that the claim of the petitioner was not of illegal recovery of tax or
other monies by the Government but of denial by the Government of monetary
benefit to which the petitioner claimed to be entitled; (iv) thus Article 113 of
the Limitation Act, 1963 would apply and as per which the claim in the writ
petition was barred by time; (v) that repeated representations made by the
petitioner and rejection thereof neither extends the period of limitation nor is a
satisfactory explanation for delay; (vi) that the petitioner was satisfied with the
rejection of its claim and cannot be permitted to revive a stale claim merely
because someone else similarly situated had succeeded; and, (vii) that normally
a petition under Article 226 of the Constitution of India will not be entertained
to enforce a civil liability and no exceptional ground had been made out by the
petitioner.
10. The emphasis of the senior counsel for the petitioner/review applicant
has been that there is an error apparent on the face of the judgment dated 12 th
August, 2014 in as much as though in para 1 of the judgment it has been noted
that the petition also impugns the minutes of the meeting dated 15 th March,
2011 but in para 11 of the judgment it has been observed that "it is not the case
of the petitioner that the decision dated 15th March, 2011 was by an authority
which was not competent to take the decision". It is argued that in fact it was
the plea of the petitioner in the petition that the decision dated 15th March,
2011 was not of a competent authority.
11. In support of the aforesaid contention, the senior counsel for the
petitioner/review applicant has taken us through the pleadings in the petition
and the review petition and the reply thereto; Section 16 of The Foreign Trade
(Development and Regulation) Act, 1992; the judgment dated 26th February,
2014 of the Division Bench of this Court in W.P.(C) No.4455/2013 titled
Simplex Infrastructure Ltd. Vs. Union of India and encouraged whereby the
petitioner had filed this petition.
12. On the aspect of delay, the senior counsel for the petitioner/review
applicant contended that the petitioner had preferred this petition in May, 2014,
soon after the judgment dated 26th February, 2014 and thus there was no delay.
13. It was further argued that once another person similarly placed as the
petitioner namely Simplex Infrastructure Ltd. had succeeded, the claim of the
petitioner could not have been barred by delay in laches. Reliance was placed
on para 16 of Rajender Singh Vs. Lt. Governor, Andaman & Nicobar Islands
(2005) 13 SCC 289 laying down that the power of review extends to correct all
errors to prevent miscarriage of justice and it was argued that there would be
miscarriage of justice, in Simplex Infrastructure Ltd. succeeding and the
petitioner failing, qua the same claim.
14. Error was also sought to be found in the reasoning in the judgment under
review as to the maintainability of the petition by referring to para 25 of ABL
International Ltd. Vs. Export Credit Guarantee Corporation of India Ltd.
(2004) 3 SCC 553.
15. Reliance was also placed on paras 15 and 16 of Competent Authority
Vs. Barangore Jute Factory (2005) 13 SCC 477 to contend that non-
consideration of material on record is a ground for review.
16. Reference was also made to Bharat Heavy Electricals Ltd. Vs. Union
of India 2015 (316) ELT 466 (Cal.) where a Single Judge of the High Court of
Calcutta also set aside the decision supra dated 15 th March, 2011 and
consequently held that the petitioner therein would not be required to pay back
the DEB already received.
17. Per contra, the learned ASG contended that the argument of the
petitioner/review applicant, of the competence of the authority which had
taken the decision dated 15th March, 2011 is irrelevant as the reason which
prevailed in the judgment of which review is sought was that the monetary
claim in the writ petition was barred by time. Without prejudice thereto, it is
also argued that the petitioner itself had submitted to the jurisdiction of the
authority which took the decision dated 15th March, 2011 and never challenged
its jurisdiction. Further without prejudice, it is argued that the challenge to the
competence of the authority is misconceived.
18. The learned ASG further argued that the claim of the petitioner in the
petition was based entirely on the judgment dated 26th February, 2014 supra in
the writ petition filed by Simplex Infrastructure Ltd. and that cannot be a cause
of action for the petitioner. It is argued that a judgment in one case cannot be a
cause of action for another case.
19. The learned ASG has even otherwise, on merits also argued that DEB is
only for goods manufactured in India but the subject goods were not
manufacture in India.
20. It was also contended by the learned ASG that ABL International
Ltd. supra has been differentiated in Joshi Technologies International Inc.
Vs. Union of India (2015) 7 SCC 728.
21. The senior counsel for the petitioner/review applicant in rejoinder has
again drawn attention to para 11 of the judgment of which review is sought
and argued that it flows therefrom that had we understood the case of the
petitioner as constituting a challenge to the competence of the authority
which took the decision dated 15th March, 2011 and which has now been
argued, our judgment would have been otherwise. Attention is invited to the
judgment dated 13th February, 2014 of the Division Bench of the High Court
of Gujarat in Special Civil Appeal No.11031/2013 titled Alstom India Ltd.
Vs. Union of India holding that even after making payment of tax either by
misinterpreting the statutory provision or under unconstitutional provision or
under mistake of law, a citizen can challenge the inherent lack of jurisdiction
and if succeeds, the Court can in appropriate case direct refund of the
amount which has been collected without jurisdiction. Reliance is also
placed on para 8 of Sushil Kumar Sen Vs. State of Bihar (1975) 1 SCC 774
to contend that qua an action for recovery of payment made under mistake,
there can be no plea of laches or delay.
22. Both counsels also relied on Salonah Tea Company Ltd. Vs.
Superintendent of Taxes, Nowgong (1988) 1 SCC 401 (para 20).
23. No arguments were addressed by the counsel for M/s Simplex
Infrastructures Ltd..
24. We cannot be unmindful of the fact that we have on an earlier
occasion, after hearing the counsels and reserving the judgment, not found
the petitioner entitled to the relief. We have wondered, whether our judicial
system permits the Courts / Judges to so change their minds / opinions, when
approached in review.
25. In our view, to widen the scope of the review to the extent desired by
the senior counsel for the petitioner/review applicant, may have far reaching
ramifications affecting the justice delivery system.
26. Though we, in the facts of the present case, even after hearing a
different counsel now appearing for the petitioner/review applicant, do not
find any case to take a different view from what we had taken earlier, but it
is well-nigh possible that the same judge, at another point of time far
removed from when he/she had earlier heard and decided the lis, may be
inclined to take a different view. After all we, as Judges, are continuously
evolving and our beliefs and opinions are changing with each day‟s
experience and judgments read by us and cited before us. Inspite of our best
efforts, due to repeated adjournments sought, the review petition has
remained pending for nearly one and a half years. However if it were to be
held that we today are entitled to form a different opinion than what we had
formed earlier, the same in our view is coupled with the danger of eroding
the faith in the judicial system and the consumers of the judicial system
believing that the Judges can be prevailed upon to so change their
opinion/judgments.
27. The power of review, in the Code of Civil Procedure, 1908 (CPC), is
confined to cases of discovery of new and important matter or evidence
which after exercise of due diligence could not be placed by the parties
before the Court at the time of hearing or on account of some mistake or
error apparent on the face of the record.
28. The present case does not fall within the aforesaid limitation. We are
on the basis of the arguments of the senior counsel for the petitioner/review
applicant unable to find any such error apparent on the face of the record.
29. Every one of the arguments now presented before us has been already
considered carefully in the judgment of which review is sought and the
petitioner‟s demand for review is only an attempt to retrieve a lost case. No
fresh facts are brought to our notice by way of discovery of new and
important evidence, which would justify reconsideration of the judgment.
Para 11 of the judgment of which review is sought and to which repeated
reference was made by senior counsel for petitioner/review applicant, in our
view, instead of forming a ground for review, shows that we have considered
the said contention also and decided against the petitioner thereon also. In
this circumstance, if we are to now reach a different conclusion than was
reached earlier, the same in our view will put the credibility of the judicial
system and this court at stake.
30. Supreme Court, in Haridas Das Vs. Smt. Usha Rani Banik (2006) 4
SCC 78 reiterated in S.N.S. (Minerals) Ltd. Vs. Union Of India (2007) 12
SCC 132 held that the parameters of review are prescribed in Order XLVII
of the CPC and permit for a rehearing "on account of some mistake or error
apparent on the face of the records or for any other sufficient reason"; the
former part of the rule deals with a situation attributable to the applicant and
the latter to a jural action which is manifestly incorrect or on which two
conclusions are not possible; neither of them postulate a rehearing of the
dispute because a party had not highlighted all the aspects of the case or
could perhaps have argued them more forcefully and/or cited binding
precedents to the Court and thereby enjoyed a favourable verdict. It was
further held that where the order in question is appealable, the aggrieved
party has adequate and efficacious remedy and the Court should exercise the
power to review its order with the greatest circumspection. The same is the
position here. The petitioner, this time around represented by an eminent
counsel, who has argued with all eloquence at his command and with
reference to a host of judgments, cannot expect a different verdict.
31. Reference may also be made to M/s. Thungabhadra Industries Ltd.
Vs. Government of Andhra Pradesh AIR 1964 1372 also reiterated in
S.N.S. (Minerals) Ltd (supra) laying down that there is a distinction which
is real, though it might not always be capable of exposition, between a mere
erroneous decision and a decision which could be characterised as vitiated
by "error apparent". Review was held to be no means an appeal in disguise
whereof an erroneous decision is reheard and corrected but lies only for
patent error, where without any elaborate argument one could point to the
error and say there is a substantial point of law which stares one in the face,
and there could reasonably be no two opinions entertained about it - only
then a clear case of error apparent on the face of the record would be made
out.
32. The present case by no stretch of imagination falls in the category
aforesaid. The petitioner here seeks review not on the ground of discovery of
new and important matter or evidence which, after the after the exercise of
due diligence was not within the knowledge of the petitioner or could not be
produced by the petitioner at the time when the judgment was passed but
wants a review on the ground that the decision is erroneous. This was held
to be not permissible also in Meera Bhanja vs Nirmala Kumari Choudhury
(1995) 1 SCC 170 and in the State Of West Bengal vs Kamal Sengupta
(2008) 8 SCC 612.
33. We have also considered whether in the light of the order dated 7 th
November, 2014 of the Supreme Court in Special Leave to Appeal (C)
No.28644/2014 supra, we are required to consider the matter afresh.
34. A perusal of the said order shows that the counsel for the petitioner at
the outset only sought permission to withdraw the Special Leave Petition
with liberty to file review petition and which permission was granted. The
fact that the petitioner was also granted liberty to, if remaining aggrieved,
again question the judgment dated 7th November, 2014, does not according
to us entitle the petitioner/review applicant to a wider consideration before
us than is permissible in review jurisdiction.
35. We therefore do not find any ground for review.
36. CM.No.23810/2015 by M/s Simplex Infrastructures Ltd. is also
misconceived.
Dismissed.
RAJIV SAHAI ENDLAW, J
CHIEF JUSTICE SEPTEMBER 16, 2016 „pp‟.,
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!