Citation : 2016 Latest Caselaw 5983 Del
Judgement Date : 15 September, 2016
IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment delivered on: 15.09.2016
+ OMP. (COMM) 93/2016
NATIONAL HIGHWAYS AUTHORITY OF INDIA ..... Petitioner
versus
M/S GAYATRI - ECI (JV) ..... Respondent
Advocates who appeared in this case:
For the Petitioner : Ms Gunjan Sinha Jain and Mr Mukesh Kumar,
Advocates.
For the Respondent : Mr Angad Mehta, Advocate.
CORAM
HON'BLE MR JUSTICE VIBHU BAKHRU
JUDGMENT
VIBHU BAKHRU, J
1. National Highway Authority of India (hereafter 'NHAI') has filed the
present petition under Section 34 of the Arbitration and Conciliation Act,
1996 (hereafter 'the Act'), inter alia, praying that the Award dated
17.12.2015 (hereafter 'the impugned award') passed by the Arbitral
Tribunal (hereafter 'the AT') be set aside.
2. The impugned award was rendered in respect of the disputes raised
by M/s Gayatri - ECI (JV)( hereafter 'GEJV') - a joint venture between M/s
Gayatri Projects Ltd and M/s ECI Engineering & Construction Co. Ltd.- in
relation to the Contract Agreement dated 19.08.2005 (hereafter 'the
Agreement') entered into between the parties for "the work of widening of
existing two lane to four from Km 93.00 to Km 60.00 of Bijni to Assam,
West Bengal NH-31C on section of East West Corridor under Phase-II
Contract Package"(hereafter 'the Works').
3. NHAI invited tenders for the Works and GEJV's bid, submitted on
18.04.2005, in response to the invitation to tender was accepted and
Acceptance letter was issued on 27.06.2005.
4. The disputes between the parties relates to reimbursement of the
additional expenditure claimed by GEJV - under sub clause 70.6 of
Conditions Of Particular Application (hereafter 'COPA') of the Agreement
- on account of increase in the rate of Value Added Tax (hereafter 'VAT').
The rate of VAT in the State of Assam was increased from 4% to 5% by
virtue of Assam Gazette Notification (hereafter 'the Notification') dated
31.03.2012.
5. GEJV requested the Team Leader of NHAI for reimbursement of
1% additional VAT incurred by it on account of the Notification. This was
followed by a similar request to the Project Director of NHAI. Since GEJV
did not receive a satisfactory response, it referred the matter to Dispute
Resolution Board (DRB) on 23.10.2013. Finally, GEJV invoked the
arbitration by a letter dated 04.01.2014, calling upon the NHAI to
nominate its arbitrator. In the meanwhile, DRB submitted its
recommendation directing reimbursement of 1% additional expenditure
incurred by GEJV on account of increase in VAT.
6. In accordance with Clause 67 of COPA, Maj. Gen. S.K. Sahijpal
(Retd.) was appointed as an arbitrator by NHAI and Mr V.S. Karandikar
was appointed by GEJV. Both the said arbitrators nominated Mr N.K.
Bahri as the presiding arbitrator.
Proceedings before the Arbitral Tribunal
7. M/s GEJV submitted its Statement of Claims before the AT,
claiming a sum of `1,30,26,781/- including interest.
8. It was GEJV's case that the twin conditions as mentioned in sub
clause 70.6 of COPA, namely, that subsequent legislation must have been
passed after the base date (22.11.2004) and that such legislation must have
caused the contractor (GEJV) to incur an additional cost, were satisfied;
and, therefore, GEJV was entitled to be reimbursed additional cost by
NHAI. Before the AT, GEJV claimed that sub clause 73.2 of COPA
provided that Contract Price bid submitted by the Contractor is inclusive of
all taxes payable by the Contractor as on base date and therefore, the very
purpose of incorporating sub clause 70.6 of COPA was to account for any
change in the Contract Price due to a subsequent legislation.
9. NHAI contested the claims made by GEJV before the AT; it was
NHAI's case that obligation to pay VAT under Works Contract was based
on the contractor's turnover and was the sole responsibility/ personal
liability of GEJV and NHAI had no role in it. Although, no such defence
was taken in the Statement of Defence, it was urged on behalf of NHAI
that the increase on account of VAT was factored in the variation in the
prices of inputs - such as Fuel, Bitumen and Labour - as the same were
indexed on the basis of Consumer Price Index/Wholesale Price Index
which, according to NHAI, factored in the increase in the cost of inputs on
account of VAT. It was also contended that the retail price of some inputs
was inclusive of tax. And, therefore in terms of sub clause 70.6, no
separate cost was payable to GEJV, which had already been taken into
account while indexing of any input under the price adjustment formulae in
accordance with sub clause (1) to (5) of Clause 70.
10. After the conclusion of arguments before the AT, written
submissions were filed on behalf of NHAI, also enclosing a letter dated
22.06.2015 from Indian Oil Corporation, confirming the maximum retail
price of MS and HSD in Bongaigaon, Assam.
11. After examining the relevant facts and circumstances and after
considering the rival contentions, the AT accepted the claims made by
GEJV and awarded a sum of `1,51,42,692/- including pendente lite interest
and past interest in favor of GEJV. The AT also awarded future interest at
the rate of 14% in favor of GEJV.
12. The AT held that NHAI had failed to adduce even an iota of
evidence to show as to what indexed inputs in the Price Adjustment
formulae are inclusive of VAT. The AT rejected NHAI's contention that
VAT was a personal liability of GEJV and NHAI was not liable to
reimburse the additional expenditure incurred by GEJV and held that the
very purpose for which sub clause 70.6 was inserted into the Agreement
was to prevent the Contractor (GEJV in this case) from being put to loss.
The AT also held that VAT is collected at retail sale point and VAT is not
taken into account while working out the WPI and therefore, additional
expenditure on account of VAT is to be reimbursed to GEJV.
13. The AT held that NHAI had not been able to substantiate as to why
governing portion of sub clause 70.6 of COPA has no operation and
concluded as under:
"After going through the pleadings and evidence, the Arbitral Tribunal finds that the Claimant had incurred additional cost because of the change in rate of VAT pursuant to change in legislation and that the said increase in the rate had not been taken into account in the indexing of any inputs to the Price Adjustment formula in general materials and therefore unanimously rules that there is no merit in the Respondent's contentions."
Submissions
14. The learned Counsel for NHAI, Ms Gunjan Sinha Jain submitted
that the impugned award is liable to be set aside as it is opposed to the
express terms of the Agreement. She submitted that AT had accepted that
any variation in the costs on account of subsequent legislation would not
be separately paid if the same had been taken into account in indexing of
any input to the price adjustment formula. However, the AT had rejected
NHAI's claim that increase in VAT had been accounted for in indexing of
inputs on the ground that NHAI had not produced any evidence in support
thereof. She contended that this was palpably erroneous as NHAI had
submitted a letter dated 22.06.2015 from Indian Oil Corporation Limited
(IOC) clearly indicating that the retail price of HSD and MS was inclusive
of VAT. She submitted that the said letter clearly evidenced that the
increase in VAT had been factored while indexing the input of fuel as per
the specified formula.
15. Mr Angad Mehta, learned counsel appearing for GEJV countered the
submissions advanced by Ms Jain. He submitted that NHAI had not taken
any defence that the increase in VAT, as claimed by GEJV, had been
factored in the price adjustment of fuel in its statement of defence. He
submitted that the said contention was advanced orally at the stage of final
arguments before the AT and this ought to have been rejected on that
ground alone. He further contended that the IOC's letter dated 22.06.2015
was neither a part of the documents filed by NHAI before the AT, nor was
the said letter referred to at the time of oral arguments. The said letter had
been annexed with the written submissions filed after conclusion of the
hearing. He submitted that in the aforesaid circumstances, the AT had
rightly held that no evidence was produced by NHAI to indicate that the
additional cost claimed by GEJV had been factored in any input; first of
all, for the reason that the aforesaid letter could not be considered as part of
the record as GEJV had no opportunity to test its veracity or to make
submissions as to its relevance. Secondly, the said letter did not establish
that additional cost claimed by GEJV had been factored in any price
adjustment formula under clause 70.3 of COPA.
16. Lastly, Mr Mehta contended that the additional cost claimed by
GEJV was on account of increase in VAT, which was payable on the entire
value of works and no part of that VAT had been factored in any of the
inputs as claimed by GEJV.
Reasoning and Conclusion
17. At the outset, it is necessary to refer to the relevant clauses of
COPA, which are set out below:
"Sub Clause 70.1.
The amounts payable to the Contractor and valued at base rates and prices in the Interim Payment Certificates issued by the Engineer pursuant to Sub-Clause 60.1 shall be adjusted in respect of the rise or fall in the index cost for labour. Contractor's Equipment, Plant, materials, and other inputs to the Works, by the addition or subtraction of the amounts determined by the formulae prescribed in this Clause.
Sub Clause 70.2 To the extent that full compensation for any rise or fall in costs to the Contractor is not covered by the provisions of this or other Clauses in the Contract, the unit rates and prices included in the Contract shall be deemed to include amounts to cover the contingency of such other rise or fall of costs.
Sub Clause 70.3
Contract Price shall be adjusted for increase or decrease in rates and price of labour, materials, fuels and lubricants in accordance with the following principles and procedures as per formula given below. The amount certified in each payment certificate is adjusted by applying the respective price adjustment factor to the payment amounts due:
(a) Price adjustment shall apply only for work carried out within the stipulated time or extensions granted by the Employer and shall not apply to work carried out beyond the stipulated time; price adjustment for extensions for reasons attributable to the Contractor, shall be paid in accordance with Sub-Clause 70.5; Price adjustment shall be calculated as per the formula given below:
(b) Following expressions and meanings are assigned to the value of the work done during each month: R = Total of work done during the month. It would include the value of materials on which secured advance has been granted, if any during the month less the value of materials in respect of which the secured advance has been recovered, if any during the month. This will exclude cost of work on items for which rates were fixed under variations Clause 51 and 52 for which the escalation will be regulated as mutually agreed at the time of fixation of rate.
(i) Adjustment for Labour Component.
Price adjustment for increase or decrease in the cost due to labour shall be paid in accordance with the following formula:
VL = 0.85 x P1/100 x R x (Li - Lo)/ Lo
VL = increase or decrease in the cost of work during the month under consideration due to changes in rates for local labour.
LO = the average consumer price index for industrial workers for the place as defined in the Appendix to Bid, in the previous month prior to the closing date of submission of bids as published by Labour Bureau, Ministry of Labour, Government of India.
Li = The average consumer price index for industrial workers for the place as defined in the Appendix to Bid, in the previous month prior to the last day of the period to which a particular interim Payment Certificate is related as published by Labour Bureau, Ministry of Labour, Government of India.
P1 = Percentage of labour component of the work.
Note: For the application of this Clause, index of Industrial Workers has been chosen to represent the labour component.
(ii) Adjustment for Cement Component Price adjustment for increase or decrease in the cost of cement procured by the Contractor shall be paid in accordance with the following formula: Vc = 0.85 x Pc/100 x R x (Ci -C0)/C0 Vc = increase or decrease in the cost of work during the month under consideration due to changes in rates for cement C0 = The all India average wholesale price index for cement in the previous month prior to the closing date of submission of bids as published by the Ministry of Commerce & Industry, Government of India.
Ci = The all India average wholesale price index for cement in the previous month prior to the last day of the period to which a particular Interim Payment Certificate is related as published by Ministry of Commerce & Industry, Government of India.
PC = Percentage of cement component of the work.
(iii) Adjustment for steel component
Price adjustment for increase or decrease in the cost of steel procured by the Contractor shall be paid in accordance with the following formula:
Vs = 0.85 x Ps/100 x R x (Si - S0)/S0
Vs = increase or decrease in the cost of work during the month under consideration due to changes in the rates for steel.
S0 = The all India average wholesale price index for steel (Bars and Rods) in the previous month prior to the closing date of submission of bids as published by the Ministry of Commerce & Industry, Government of India.
Si = The all India average wholesale price index for steel (Bars and Rods) in the previous month prior to the last day of the period to which a particular Interim Payment Certificate is related as published by the Ministry of Commerce & Industry, Government of India.
Ps = Percentage of steel component of the work.
Note:- For the application of this Clause, index of Bars and Rods has been chosen to represent steel component.
(iv) Adjustment for Plant and machinery spares component
Price adjustment for increase or decrease in the cost of Plant and machinery spares procured by the Contractor shall be paid in accordance with the following formula:
Vp = 0.85 x Pp/100 x R x (Pi - Po)/Po
Vp = Increase or decrease in the cost of work during the month under consideration due to changes in the rates for Plant and machinery spares
Po = The all India wholesale price index for heavy machinery and parts in the previous month prior to the closing date of submission of bids as published by the Ministry of Commerce & Industry, Government of India.
Pi = The all India average wholesale price index for heavy machinery and parts in the previous month prior to the last day of the period to which a particular Interim Payment Certificate is related as published by the Ministry of Commerce & Industry, Government of India.
Pp = Percentage of Plant and machinery spares component of the work
Note:For the application of this clause, index of heavy machinery and parts has been chosen to represent the Plant and Machinery spares component.
(v) Adjustment of Bitumen Component
Price adjustment for increase or decrease in the cost of bitumen shall be paid in accordance with the following formula:
Vb = 0.85 x Pb/100 x R x (Bi -B0) /B0
Vb = Increase or decrease in the cost of work during the month under consideration due to changes in rates for bitumen.
B0 = The average official retail price of bitumen at the nearest refinery for the place as defined in
Appendix to Bid, in the previous month prior to the date of submission of Bids.
Bi = The average official retail price of bitumen at nearest refinery for the place as defined in Appendix to Bid, in the previous month prior to the last day of the period to which a particular Interim Payment Certificate is related.
Pb = Percentage of bitumen component of the work.
(vi) Adjustment for Fuel and Lubricants (POL)
Price adjustment for increase or decrease in the cost of POL (fuel and lubricant) shall be paid in accordance with the following formula:
Vf = 0.85 x Pf/100 x R x (Fi - F0)/F0
Vf = Increase or decrease in the cost of work during the month under consideration due to changes in rates for fuel and lubricants.
F0 = The average official retail price of High Speed Diesel (HSD) oil at the existing consumer pumps of IOC for the place defined in the Appendix to Bid in the previous month prior to date of submission of bids.
Fi = The average official retail price of HSD at the existing consumer pumps of IOC for the place defined in the Appendix to Bid in the previous month prior to the last date of the period to which a particular Interim Payment Certificate is related.
Pf = Percentage of fuel and lubricants component of the work.
Note: - For the application of this clause, the price of High Speed Diesel oil at the IOC pumps has been chosen to represent fuel and lubricants component.
* Based price index for Industrial Workers to be published by Labour Bureau, Ministry of Labour, Govt. of India be checked.
(vii) Adjustment of Other Local Materials
Price adjustment for increase or decrease in cost of local materials other than cement, steel, bitumen, plant spares and POL procured by the Contractor shall be paid in accordance with the following formula:
Vm = 0.85 x Pm /100 x R x (Mi - M0)/M0
Vm = Increase or decrease in the cost of work during the month under consideration due to changes in rates for local materials other than cement, steel, bitumen, plant spares and POL.
M0 = The all India average wholesale price index (all commodities) in the previous month prior to date of submission of bids, as published by the Ministry of Commerce & Industry, Government of India.
Mi = The all India average wholesale price index (all commodities) in the previous month prior to the last day of the period to which a particular Interim Payment Certificate is related as published by the Ministry of Commerce & Industry, Government of India.
Pm = Percentage of local material component (other than cement, steel, bitumen, plant spares and POL) of the work.
(viii) The following percentages will govern the price adjustment of the entire contract:
1. Labour - Pl 20%
2. Plant & Machinery Spares - Pp 20%
3. POL - Pf 10%
4. Bitumen - Pb x%
5. Cement - PC y%
6. Steel - PS z%
7. Other materials - Pm 50-(x+v+z)%
Total 100%
(Note: x, y, z are the actual percentage of material of bitumen, cement and steel respectively used for execution of work as per the Interim Payment Certificate for the month.) xxxx xxxx xxxx xxxx
Sub Clause 70.6
If, after the date 28 days prior to the latest date for submission of tenders for the Contract, there occur changes to any National or State Statute, Ordinance, Decree or other Law or any regulation or by-law of any local or other duly constituted authority or the introduction of any such State Statute, Ordinance, Decree, Law, regulation or by-law which causes additional or reduced cost to the Contractor, other than under the preceding Sub-Clauses of this Clause, in the execution of the contract, such additional or reduced cost shall, after due consultation with the Employer and the Contractor, be determined by the Engineer and shall be added to or deducted from the Contract Price and the Engineer shall notify the Contractor accordingly, with a copy to the Employer. Notwithstanding the foregoing, such additional or reduced cost, shall not be separately paid or credited if the same shall already have been taken into account in the indexing of any inputs to the Price Adjustment Formulae in accordance with the provisions of Sub-Clauses (1) to (5) of this Clause."
18. Sub clause 70.1 of COPA provides for adjustment in respect of rise
or fall in the index cost for labour, contractor's equipment, plant, materials
and other inputs in accordance with the formula as prescribed.
19. Sub clause 70.2 of COPA expressly provides that to the extent of
full compensation for any rise and fall in costs is not covered under any of
the clauses, the unit rates and prices would be deemed to have included the
amounts to cover the contingency of rise and fall in costs. In other words,
the increase and decrease in costs are to be compensated only to the extent
as expressly provided under the contract.
20. Sub clause 70.3 prescribes the formula for determining the price
variation in various inputs, that is, the amount to be added or subtracted
from the value of work done on account of price variation in inputs. In
terms of the formula, the variation in the value of labour component is to
be indexed on the basis of average consumer price index for industrial
workers; the price adjustment for cement and steel components is to be
adjusted on the basis of the all India average wholesale price index for
cement and steel respectively; adjustment for plant and machinery and
spare component is to be computed on the basis of all India average
wholesale price index for heavy machinery and parts; adjustment for
bitumen component is to be computed on the basis of average official retail
price of Bitumen at the nearest refinery for the place defined in the
appendix to the Bid; adjustment for fuel and lubricants (POL) is to be
computed on the basis of average official retail price of HSD at the existing
consumer pumps of IOC; and adjustment for other local materials is to be
computed on the basis of all India average wholesale price index (all
commodities) in the previous month prior to date of submission of bids.
21. Sub clause 70.6 provides for adjustment in costs, inter alia, on
account of change in national or state statutes.
22. The dispute in the present case concerns the interpretation of sub
clause 70.6 of COPA. There is no dispute that by virtue of the Notification,
the rate of VAT was increased from 4% to 5%. GEJV had claimed an
additional 1% on "the aggregate value of works contract". In other words,
the GEJV had claimed for additional costs on account of increase in the
rate of VAT imposed on aggregate value of work done. The annexure to
the written submissions filed by GEJV before the AT clearly indicates the
manner in which the additional costs have been computed. The said
annexure indicates that GEJV had sought reimbursement at the rate of 1%
on the gross value of the work done. Thus, it is amply clear that the
additional costs on account of VAT sought to be recovered were not on
account of any increase or partial increase in the cost of inputs resulting
from increase in the rate of VAT, but on account of levy of VAT on the
value of gross work done.
23. It is necessary to understand the basic scheme of VAT. VAT is
levied at different stages on the value of goods including as incorporated in
the Works. Undisputedly, VAT is levied on sale of goods at every point in
a series of sale as is expressly provided under Section 2(56) of the Assam
VAT Act, 2003. However, a dealer is entitled to claim credit for the VAT
imposed on some of the inputs - subject to the prescribed conditions being
met - while determining the liability to pay VAT on the output. GEJV's
claim for additional costs on increase in the cost of inputs on account of
increase in the rate of VAT must be understood in the aforesaid context.
24. As indicated earlier, GEJV had claimed 1% of the gross value of
work done as additional cost; this was on account of increase in the levy of
VAT on the aggregate value of the work done. The point in issue before
the Arbitral Tribunal - albeit raised at a belated stage - was whether any
part of this cost taken into account while indexing any input.
25. The applicability of the second sub-paragraph of sub clause 70.6 of
COPA has to be considered in the context of the claim made by GEJV.
Thus, if NHAI had shown that value of any input had increased on account
of increase in the rate of VAT and the same was accounted for in the
formula as prescribed under sub clause 70.3 and for which any credit was
available to GEJV to mitigate the cost on account of increase in VAT
levied on the gross value of work done, then, it may have been open for
NHAI to contend that by virtue of the second sub-para to sub clause 70.6
of COPA, no further adjustment on account of increase in cost resulting
from increase in the rate of VAT was payable. Admittedly, no such
evidence was produced by NHAI.
26. Clearly, there is no evidence on record that any part of increase in
cost on account of levy of VAT on "gross value of work done" was
recovered or was accounted for in the price adjustment of any input. The
finding of the AT in paragraph 4.3(iii) of the impugned award must be
understood in the aforesaid context. Thus, in my view, the AT's finding
that NHAI had not provided any evidence to show that increase in VAT
was taken into account in indexing of any inputs cannot be faulted.
27. It is also necessary to observe that the intent and purpose of sub-para
70.6 of COPA is to eliminate the effect of double benefit. The clear import
of sub-para is that if an increase in cost has been taken into account while
effecting the price adjustment, the same can, for obvious reasons, not be
reimbursed again to the contractor.
28. In the facts of the present case, there is no material to indicate that
the additional costs as claimed by GEJV on account of additional levy on
the value of the contract had been taken into account while giving the
benefit of price indexation of inputs to GEJV.
29. In National Highways Authority of India v. ITD Cementation
India Ltd.: 2015 (6) SCJ 313, the Supreme Court considered the challenge
to an arbitral award wherein the AT had examined the similar clauses (in
that case sub clause 70.8 of COPA was identically worded as sub clause
70.6 of COPA in the present case). The AT had held that price
adjustments as per sub clauses 70.2 to 70.7 of COPA (which are more or
less similar to sub clauses 70.1 to 70.5 of COPA in this case) did not assure
full compensation for rise or fall in the prices; but, in terms of sub clause
70.8 of COPA (in this case sub clause 70.6), the additional cost on account
of subsequent legislation was stipulated to be paid in full. The Supreme
Court declined to interfere with the aforesaid interpretation as it held that
the same was reasonable and did not fall within the scope of Section 34(2)
of the Act.
30. Additionally, it is admitted that IOC's letter dated 22.06.2015 which
is relied upon by the NHAI in these proceedings to assail the impugned
award, was never produced before the AT at the relevant stage and was
submitted only as an annexure to the written submissions filed by NHAI.
Admittedly, the statement of defence filed by NHAI contained no averment
to the effect that the claim made by GEJV should be rejected on the ground
that the part of the increased cost claimed had been taken into account
while indexing the value of input of fuel. In these circumstances, even if it
is accepted that the said letter is relevant - which, as discussed earlier, it is
not - it is difficult to fault the AT's decision to ignore the same.
31. It is settled law that when it comes to arbitration awards, the court's
approach is one of non-interference. The grounds on which an award can
be set aside are highly restricted. Even if an arbitrator has interpreted the
agreement erroneously, the same is an error within his jurisdiction and it
cannot be interfered with (See: McDermott International Inc v. Burn
Standard Co. Ltd. and Ors. : (2006) 11 SCC 181 )except in cases where
the decision is perverse or so irrational so as to render the award
unreasonable on the touchstone of the Wednesbury's principle; that is, that
no reasonable person could have possibly arrived at such a
conclusion.(See: Oil and Natural Gas Corporation Ltd v. Western Geco
International Ltd.: (2014) 9 SCC 263).
32. In view of the above, this Court is unable to accept that any
interference is warranted with the impugned award.
33. The petition is, accordingly, dismissed.
VIBHU BAKHRU, J SEPTEMBER 15, 2016 RK
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!