Amarjeet Singh And Ors vs Land Acquisition Collector ...
2016 Latest Caselaw 5821 Del

Citation : 2016 Latest Caselaw 5821 Del
Judgement Date : 5 September, 2016

Delhi High Court
Amarjeet Singh And Ors vs Land Acquisition Collector ... on 5 September, 2016
$~70
* IN THE HIGH COURT OF DELHI AT NEW DELHI
%                                      Judgment delivered on: 05.09.2016

+       W.P.(C) 3845/2014 & CM Nos.21892-93/2015
AMARJEET SINGH AND ORS                                       .... Petitioners
                              versus
LAND ACQUISITION COLLECTOR (SOUTH) AND ANR.
                                       ..... Respondents

Advocates who appeared in this case:
For the Petitioner      : Mr Anuroop P.S.
For the LAC/L&B         : Mr Yeeshu Jain.
For the DDA             : Mr Sanjeev Sabharwal.

CORAM:-
HON'BLE MR JUSTICE BADAR DURREZ AHMED
HON'BLE MR JUSTICE ASHUTOSH KUMAR

                                JUDGMENT

BADAR DURREZ AHMED, J (ORAL)

1. The DDA had filed a review application claiming that it was

not made a party to the earlier proceedings. That review application

was allowed on the sole ground that the DDA had not been made a

party and the counsel for the DDA was obviously not heard before the

judgment dated 08.12.2014 was delivered. That is how the matter has

come up before this Bench. We have heard the learned counsel for the

parties including the learned counsel for the DDA. The review

petition filed on behalf of the DDA is treated as its counter affidavit.

2. The petitioners seek the benefit of Section 24(2) of the Right to

Fair Compensation and Transparency in Land Acquisition,

Rehabilitation and Resettlement Act, 2013 (hereinafter referred to as

'the 2013 Act') which came into effect on 01.01.2014. A declaration

is sought to the effect that the acquisition proceeding initiated under

the Land Acquisition Act, 1894 (hereinafter referred to as 'the 1894

Act') in respect of which Award No. 18/1987-88 dated 05.06.1987

was made, inter alia, in respect of the petitioners' land comprised in

Khasra Nos. 2206/1046/2/1 (8-00), 2206/1046/2/2 (20-13), 2208/1046

(3-14), 2207/1046/2 (11-10), 2207/1046/2/2 (28-02) and

2207/1046/2/3 (24-16) measuring 96 bighas and 15 biswas in all in

village Tughlaqabad shall be deemed to have lapsed.

3. The respondents claim that possession in respect of 38 bighas

out of the said lands was taken on three separate dates, namely,

06.06.2013, 31.07.2013 and 31.12.2013. In respect of the balance

land, it is an admitted position that possession was not taken.

However, the petitioners maintain that physical possession of the

entire land is with them and it has not been taken over by the land

acquiring agency. Insofar as the issue of compensation is concerned, it

is an admitted position that it has not been paid.

4. It is evident that with regard to a substantial portion of the land,

physical possession of the same has admittedly not been taken by the

land acquiring agency. With regard to the balance land, there is a

dispute as to who is in physical possession. But we need not go into

this controversy inasmuch as the award was made more than five

years prior to the commencement of the 2013 Act and, admittedly,

compensation has not been paid. The necessary ingredients for the

application of Section 24(2) of the 2013 Act as interpreted by the

Supreme Court and this Court in the following cases stand satisfied:-

(1) Pune Municipal Corporation and Anr v. Harakchand Misirimal Solanki and Ors: (2014) 3 SCC 183;

(2) Union of India and Ors v. Shiv Raj and Ors: (2014) 6 SCC 564;

(3) Sree Balaji Nagar Residential Association v. State of Tamil Nadu and Ors: Civil Appeal No. 8700/2013 decided on 10.09.2014;

(4) Surender Singh v. Union of India & Others: WP(C) 2294/2014 decided on 12.09.2014 by this Court; and

(5) Girish Chhabra v. Lt. Governor of Delhi and Ors: WP(C) 2759/2014 decided on 12.09.2014 by this Court.

5. As a result, the petitioners are entitled to a declaration that the

said acquisition proceedings initiated under the 1894 Act in respect of

the subject land are deemed to have lapsed. It is so declared.

6. The writ petition is allowed to the aforesaid extent. There shall

be no order as to costs.




                                      BADAR DURREZ AHMED, J



SEPTEMBER 05, 2016                    ASHUTOSH KUMAR, J
ab





 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter