Citation : 2016 Latest Caselaw 5701 Del
Judgement Date : 31 August, 2016
$~1
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ ARB. A. (COMM.) 21/2016 & IA No.8600/2016
NATRIP IMPLEMENTATION SOCIETY ..... Appellant
Through: Mr Sanjay Jain, ASG with Mr Ravi
Varma, Ms Natasha Thakur and Mr
Suadat Ahmad Kirmani, Advocates.
Versus
IVRCL LIMITED ..... Respondent
Through: Dr Amit George, Advocate.
CORAM:
HON'BLE MR. JUSTICE VIBHU BAKHRU
ORDER
% 31.08.2016 VIBHU BAKHRU, J
1. The appellant (hereafter „NATRIP‟) has filed the present appeal under
Section 37(2) of the Arbitration and Conciliation Act, 1996 (hereafter 'the
Act') impugning the order dated 21.05.2016 passed by the Arbitral Tribunal
(hereafter 'the impugned order').
2. By the impugned order, the Arbitral Tribunal (hereafter „the
Tribunal‟) had rejected NATRIP's application dated 22.04.2016 whereby it
had prayed that the amounts claimed by it in its counter claim be secured by
way of sufficient security or by bank guarantee.
3. NATRIP had invited bids for construction of Automotive Test Tracks
at Natrax - Pithampur and GARC - Chennai (hereafter 'the project'). The
tracks at GARC - Chennai and Natrax -Pithampur were to be completed by
September 2011 and September 2012 respectively.
4. The respondent (hereafter „IVRCL‟) was successful in the bidding
process and was accordingly awarded the contract for execution of the
project. The negotiated value of the contract was `525,97,06,879/-.
Admittedly, the execution of the contract was delayed. According to
NATRIP, IVRCL had failed and neglected to perform the contract despite
several notices.
5. In the circumstances, NATRIP issued notices calling upon IVRCL
to remedy the breaches, failing which NATRIP would be entitled to
terminate the contract without prejudice to its other rights and remedies.
IVRCL also issued notices, inter alia, alleging that the delays were on
account of NATRIP. NATRIP alleges that IVRCL did not resume
construction activities and took no steps to remedy the defaults;
consequently, NATRIP issued a letter dated 14.08.2013 terminating the
contract. NATRIP further states that thereafter, it issued a tender for the
balance works under the contract at the risk and cost of IVRCL. IVRCL
has its own tale of woe and inter alia alleges that the delay in execution
of the project is on account of NATRIP and the termination of contract is
wrongful. IVRCL invoked the arbitration clause. Thereafter, the Tribunal
comprising of three members including a former judge of this Court was
constituted. IVRCL filed its claim before the Tribunal for an aggregate
sum of `2,13,79,04,238/- which was later amended to `415,27,61,238/-.
NATRIP also filed its counter claim for a sum of `79,23,511,669/- which
was subsequently increased to `871,05,74,323/-.
6. The Arbitral proceedings are currently at the stage of final hearing.
The arguments on behalf of IVRCL have been concluded and the
arguments on behalf of NATRIP would have commenced on 26.08.2016.
However, the hearings scheduled on 26.08.2016, 27.08.2016 and
29.08.2016 have been adjourned at the instance of the learned counsel for
NATRIP. At the stage of final hearing, NATRIP filed an application
dated 22.04.2016, inter alia, praying that IVRCL be directed to provide
security for the amount claimed by it.
7. In its application, NATRIP, inter alia, pleaded that certain contracts
entered into by IVRCL with other agencies had been terminated on
account of failure on the part of IVRCL to perform those contracts. It
was also pleaded that a flyover in Kolkata had collapsed on 31.03.2016
and this was due to "the non-performance due to financial stringency of
the IVRCL". It was further pleaded that the financial condition of IVRCL
was precarious and it was currently under SDR (Strategic Debt
Restructuring) under which all expenses of IVRCL were to be approved
by representatives of the lenders. It is also stated that three winding up
petitions against IVRCL had been admitted and citations had been
published. NATRIP claimed that in the given circumstances, it would not
only be extremely difficult but impossible for NATRIP to realise the
amount of counter claim from IVRCL in the event NATRIP succeeded
before the Tribunal.
8. The Tribunal rejected the application principally on the ground that
the Arbitral proceedings were at a final stage. The Tribunal observed that
the case was a highly contested one and both parties had made allegations
and counter allegations. The Tribunal held that at the stage of final
hearing, it was neither possible nor advisable to take a prima facie view
of the matter in favour of NATRIP as the Tribunal was of the view that
the same would amount to pre-judging the case and would be prejudicial
to the outcome of the decision on merit.
9. The Tribunal further held as under:-
"....Since we are not able to determine with certainty the existence of prima facie case in favour of the Respondent in the sense that the Respondent is likely to succeed in counter claims, we refrain from commenting on the alleged financial stringency of the Claimant, which are again denied and disputed questions of facts."
10. Aggrieved by the aforesaid decision, NATRIP has preferred the
present appeal.
11. Mr Sanjay Jain, learned ASG appearing for NATRIP contended that
the financial condition of IVRCL was precarious and that winding up
petitions against IVRCL have been admitted. He submitted that in the
circumstances, it was necessary for the Tribunal to have considered
NATRIP's application on merits. He submitted that NATRIP had established
that IVRCL was debt ridden and not in a position to meet its liabilities and
therefore, an order for securing the amount in dispute ought to have been
passed. He referred to the decision of a Coordinate Bench of this Court in
Gatx India Pvt Ld. v. Arshiya Rail Infrastructure Limited & Anr: 216
(2015) 216 DLT 20 and on the strength of the said decision contended that
the fact that IVRCL‟s financial condition was precarious would be sufficient
for directing IVRCL to provide a security for the counter claims preferred
by NATRIP. He submitted that it was not necessary for NATRIP to allege
that IVRCL was siphoning of its funds or alienating its assets, in order to
succeed in its prayer for securing its counter claims. He submitted that even
if the financial incapacity of IVRCL was caused for reasons beyond its
control, the award that would follow would be impossible to enforce; and,
therefore, it was necessary that NATRIP be secured immediately without
awaiting the publishing of the award.
12. Dr Amit George who appeared for IVRCL on advance notice,
countered the contentions advanced by Mr Jain. He submitted that almost all
counter claims made by NATRIP were in the nature of damages and
indisputably NATRIP would not be entitled to such claims if the Tribunal
found that the termination of the contract was wrongful or that the delay in
execution of the project was not caused by IVRCL. He further submitted
that NATRIP had filed the application for securing the counter claims only
with a view to pressurise IVRCL. He handed over the copy of the minutes of
the proceedings of the 36th hearing of the Tribunal held on 30.07.2016 which
indicated that the Tribunal had scheduled hearings on 26.08.2016,
27.08.2016 and 29.08.2016 as well as 19.09.2016, 20.09.2016 and
21.09.2016 for hearing the final arguments on behalf of NATRIP. However,
on the insistence of NATRIP's counsel, the dates fixed in August 2016 were
cancelled. He submitted that on one hand NATRIP was insisting for urgent
orders for securing its counter-claim and on the other hand was delaying the
conclusion of the proceedings before the Tribunal by seeking adjournments.
He also relied on the decision of the Supreme Court in Raman Tech. &
Process Engineering Co. and Anr. V. Solanki Traders: (2008) 2 SCC 302
in support of his contention that an order for providing security could not be
granted unless the party seeking such relief had established a good prima
facie case and further established that the other party was attempting to
dispose of properties with the intention of defeating the decree that may
follow.
13. I have heard the learned counsel for the parties.
14. At the outset, it is necessary to observe that apart from claiming that
the financial condition of IVRCL is precarious, NATRIP has not urged any
other reason for seeking an order for securing its counter claims. Thus, the
only controversy that needs to be addressed at this stage is whether an order
directing a party to secure the amount in dispute can be issued only for the
reason that the said party is in financial distress and consequently the award
that follows may be impossible to be enforced?
15. Before proceeding further, it would be necessary to refer to the
relevant extract of Section 9 of the Act, which reads as under:-
"9. Interim measures, etc. by Court.-- A party may, before or during arbitral proceedings or at any time after the making of the arbitral award but before it is enforced in accordance with Section 36, apply to a Court:--
(i) for the appointment of a guardian for a minor or a person of unsound mind for the purposes of arbitral proceedings; or
(ii) for an interim measure of protection in respect of any of the following matters, namely:--
(a) the preservation, interim custody or sale of any goods which are the subject-matter of the arbitration agreement;
(b) securing the amount in dispute in the arbitration;
(c) the detention, preservation or inspection of any property or thing which is the subject-matter of the dispute in arbitration, or as to which any question may arise therein and authorising for any of the aforesaid purposes any person to enter upon any land or building in the possession of any party, or authorising any samples to be taken or any observation to be made, or experiment to be tried, which may be necessary or expedient for the purpose of obtaining full information or evidence;
(d) interim injunction or the appointment of a receiver;
(e) such other interim measure of protection as may appear to the Court to be just and convenient, and the Court shall have the same power for making orders as it has for the purpose of, and in relation to, any proceedings before it."
16. As is apparent from the plain language of the opening words of
Section 9(1) of the Act, a party may apply to the court for any of the reliefs
as set out in clauses (i) and (ii) above. However, the power of the court to
grant relief is indicated in the last line of Section 9(1) of the Act; that is, the
court has the same power for making orders as it has for the purpose of, and
in relation to, any proceedings before it. In Firm Ashok Traders and Anr. v
Guurmukh Das Saluja and Ors.: 2004 (3) SCC 155, the Supreme Court
explained as hereunder :-
" The reliefs which the Court may allow to a party under clauses
(i) and (ii) of Section 9 flow from the power vesting in the Court exercisable by reference to "contemplated", "pending" or "completed" arbitral proceedings. The Court is conferred with the same power for making the specified orders as it has for the purpose of and in relation to any proceedings before it though the venue of the proceedings in relation to which the power under Section 9 is sought to be exercised is the Arbitral Tribunal."
17. It is also clear from the opening sentence of section 9(1)(ii) of the Act
that the measures that can be ordered are "interim measures of protection".
It, plainly, follows that the principles that would be applicable for grant of
orders under section 9(1)(ii) of the Act would be the principles that may be
applicable to grant of such orders as are applicable to proceedings before the
Court. An order for securing the amount claimed prior to an arbitral award is
essentially in the nature of attachment before judgement and thus, the
principles as applicable for grant of such orders in proceedings before the
Court - that is, as applicable under Order XXXVIII Rule 5 of the Code of
Civil Procedure, 1908 (hereafter „the CPC‟) - would be equally applicable
for grant of relief under Sections 9(1)(ii)(b) or 17(1)(ii)(b) of the Act (as
amended by Act 3 of 2016) prior to the publishing of the arbitral award. In
Rite Approach Group Ltd. v. Rosoboronexport: 111 (2004) DLT 816,
Global Company v. M/s National Fertilizers Ltd.: AIR 1998 Delhi 397 and
Gatx India Pvt Ld. (supra), this Court held that it would take guidance from
the principles given in Order XXXVIII Rule 5 of the CPC for grant of orders
under Section 9 of the Act.
18. It is also well settled that the granting of orders under section 9 of the
Act are discretionary in nature and equitable considerations would apply for
grant of such orders. Thus, orders as prayed under section 9(1) of the Act
would be granted only if it is necessary and equitable.
19. In Raman Tech. & Process (supra), the Supreme Court explained that
the object of order XXXVIII Rule 5 of the CPC was to prevent any
defendant from defeating the realisation of the decree that may be ultimately
passed in favour of the plaintiff by either disposing of or removing assets
from the jurisdiction of the Court. The relevant extract of the said decision
is extracted below:-
"4. The object of supplemental proceedings (applications for arrest or attachment before judgment, grant of temporary injunctions and appointment of receivers) is to prevent the ends of justice being defeated. The object of Order 38 Rule 5 CPC in particular, is to prevent any defendant from defeating the realization of the decree that may ultimately be passed in favour of the plaintiff, either by attempting to dispose of, or remove from the jurisdiction of the court, his movables. The Scheme of Order 38 and the use of the words "to obstruct or delay the execution of any decree that may be passed against him" in Rule 5 make it clear that before exercising the power under the said Rule, the court should be satisfied that there is a reasonable chance of a decree being passed in the suit against the defendant. This would mean that the court should be satisfied that the plaintiff has a prima facie case. If the averments in the plaint and the documents produced in support of it, do not satisfy the court about the existence of a prima facie case, the court will not go to the next stage of examining whether the interest of the plaintiff should be protected by exercising power under Order 38 Rule 5 CPC. It is well-settled that merely having a just or valid claim or a prima facie case, will not entitle the plaintiff to an order of attachment before judgment, unless he also establishes that the defendant is attempting to remove or dispose of his assets with the intention of defeating the decree that may be passed. Equally well settled is the position that even where the defendant is removing or disposing his assets, an attachment before judgment will not be issued, if the plaintiff is not able
to satisfy that he has a prima facie case.
5. The power under Order 38 Rule 5 CPC is a drastic and extraordinary power. Such power should not be exercised mechanically or merely for the asking. It should be used sparingly and strictly in accordance with the Rule. The purpose of Order 38 Rule 5 is not to convert an unsecured debt into a secured debt. Any attempt by a plaintiff to utilize the provisions of Order 38 Rule 5 as a leverage for coercing the defendant to settle the suit claim should be discouraged. Instances are not wanting where bloated and doubtful claims are realised by unscrupulous plaintiffs, by obtaining orders of attachment before judgment and forcing the defendants for- out-of court settlements, under threat of attachment."
20. In order for the court to exercise its powers under Order XXXVIII
Rule 5 of the CPC, it is necessary that twin conditions be satisfied. First, that
the plaintiff establishes a reasonably strong prima facie case for succeeding
in the suit; and second, that the court is prima facie satisfied that the
defendant is acting in a manner so as to defeat the realisation of the decree
that ultimately may be passed. The object of Sections 9(1)(ii)(b) and
17(1)(ii)(b) of the Act is similar to the object of order XXXVIII Rule 5 of
the CPC. The Arbitral Tribunal while exercising powers under Section
17(1)(ii)(b) of the Act or the Court while exercising power under Section
9(1)(ii)(b) of the Act must be satisfied that it is necessary to pass order to
secure the amount in dispute. Such orders cannot be passed mechanically.
Further, the object of the order would be to prevent the party against whom
the claim has been made from dispersing its assets or from acting in a
manner to so as to frustrate the award that may be passed.
21. In the present case, there is no allegation that IVRCL is dispersing its
assets or acting in a manner so as to frustrate the enforcement of the award
that may be passed. Thus, on the application of principles as embodied in
Order XXXVIII Rule 5 of the CPC, no order for securing NATRIP can be
passed.
22. Further, if the financial state of IVRCL, as pleaded by NATRIP is
accepted to be correct, it is apparent that IVRCL would also be unable to
provide the security as prayed for by NATRIP. NATRIP claims that three
winding up petitions have been admitted against IVRCL as IVRCL has been
unable to pay its debts. If the same is correct, then it is obvious that IVRCL
would be unable to provide security or bank guarantee for the sums claimed
by NATRIP. It follows from the above, that it is almost certain that IVRCL
would not be in a position to comply with an order to provide security for
the counter claims preferred by NATRIP. In the given facts, such an order
would debilitate IVRCL‟s ability to pursue its claims against NATRIP. An
interim protection for one party cannot be granted at the cost of imposing an
onerous condition on the other and thus, rendering the other party in a
hapless condition.
23. It is relevant to bear in mind that if IVRCL is liable to be wound up as
is urged by Mr. Jain, then NATRIP would have to stand as one amongst
other unsecured creditors of IVRCL for recovery of its dues; NATRIP
cannot by obtaining an order under section 17 of the Act seek to place itself
in a better position than the other creditors.
24. The contention that financial distress of a party can be a sole ground
for directing that party to secure a claim of unadjudicated damages as
claimed by the other party is, in my view, bereft of any merit.
25. The reliance placed by Mr Jain in the case of Gatx India Pvt Ld.
(supra) is misplaced. In that case, the petitioner had made a claim for lease
rent of rakes as well as for liquidated damages. Since in that case, the
quantum of lease rent was ascertained and the petitioner had established the
case for lease rent, the Court granted an order directing furnishing of
security for the lease rent. However, as far as liquidated damages were
concerned, the Court denied the same because the liability on account of the
liquidated damages had not been ascertained. The said decision cannot be
read as an authority to mean that financial distress of a party would be
sufficient to require the said party to furnish a security.
26. In the present case, the arbitral proceedings are at the stage of final
arguments and considering the stage of the proceedings, the Tribunal has
declined to exercise its powers to pass an interim order. Orders under
section 17 of the Act are discretionary and the Tribunal has exercised its
discretion to not consider passing interim orders at the stage of final hearing.
I find no infirmity with the aforesaid view.
27. In view of the above, the present appeal is dismissed. The pending
application also stands disposed of.
VIBHU BAKHRU, J AUGUST 31, 2016 RK
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!