Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

International Panaacea Ltd. vs National Seeds Corporation Ltd.
2016 Latest Caselaw 5485 Del

Citation : 2016 Latest Caselaw 5485 Del
Judgement Date : 23 August, 2016

Delhi High Court
International Panaacea Ltd. vs National Seeds Corporation Ltd. on 23 August, 2016
*       IN THE HIGH COURT OF DELHI AT NEW DELHI

%                                   Order delivered on: 23rd August, 2016

+                     Arb. P. No.270/2016

        INTERNATIONAL PANAACEA LTD.               ..... Petitioner
                      Through   Mr.Sumesh Dhawan, Adv. with
                                Ms.Vatsala Kak, Adv.

                           versus

        NATIONAL SEEDS CORPORATION LTD.        ..... Respondent
                      Through  Mr.Sameer Kulshreshtha, Adv.

        CORAM:
        HON'BLE MR.JUSTICE MANMOHAN SINGH

MANMOHAN SINGH, J. (Oral)

1. The petitioner has filed the present petition under Section 11(5) of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the "Act") for appointment of a sole Arbitrator to adjudicate the disputes arisen between the parties.

2. The respondent entered into an Agreement dated 24th May, 2012 with the petitioner for Registered Co-supplier/Co-producer of quality agri-inputs, i.e. Bio-manure, Bio-fertilizers, Bio-pesticides and micro- nutrients for Bihar and Jharkhand Regions. The arrangement was continued up to 31st December, 2012. The respondent failed to make the payment due. On 26th December, 2015, the petitioner served a legal notice upon the respondent for appointment of a sole Arbitrator. On 7th March, 2016, the respondent replied to the said legal notice, stating that the respondent had no objection for appointment of a sole Arbitrator, however, as no disputes had arisen between the parties,

there was no reason for appointment of sole Arbitrator. The similar plea is also taken by the respondent in its reply in para 2-B thereof.

3. The contention of the learned counsel for the petitioner is that despite of notice, as per the arbitration clause, the respondent failed to appoint an Arbitrator before filing of the present petition.

4. As far as the disputes between the parties are concerned, the respondent is not disputing the same so as the arbitration clause. The only submission of the respondent is that since it is a back-to-back contract, therefore, the prayer should not be allowed.

5. Learned counsel for the petitioner has referred a decision of the Supreme Court rendered in the case of Zonal General Manager, IRCON International Limited v. Vinay Heavy Equipments (2015) 13 SCC 680 (para 9) which reads as under:-

"9. Insofar as the question of primary liability therein is concerned, the law on subcontracts and employer liability is amply clear. In the absence of covenant in the main contract to the contrary, the rules in relation to privity of contract will mean that the jural relationship between the employer and the main contractor on the one hand and between the sub-contractor and the main contractor on the other will be quite distinct and separate. No such clause to the contrary, existent in the main contract between Appellants and SIPCOT, has been highlighted before us by the Appellants, which would persuade us towards a deviation from the presumption of distinct and sole liability of the Appellant-Contractor as employer viz. a. viz. the Respondent-Sub Contractor. On the contrary, much of the exercise in determining the existence of a "back to back clause" in the contracts C1 and C2 appears to be misplaced. Such an accommodation or transference of liability needs to be pinpointed in the main contract, for it is SIPCOT's acceptance of liability of subcontractor claims which is of the essence; even a clause indicating "back to back" liability in agreements C1 and C2 would not serve to

novate the main contract and fasten payment liability on SIPCOT, prevented as it would be by privity, for it would be a matter of SIPCOT's acceptance of subcontractor liability in the main contract, and not a matter of novation by imposition upon SIPCOT by two parties in a separate bilateral contract. Nothing presented before us suggests that SIPCOT's contract with the Appellant provided for "back to back" subcontracts whereby SIPCOT would be directly answerable for the payment claims raised by contractors. That subletting was provided for by the main contract, and indeed occurred, has been found by the Arbitrator (in both Arbitrations) and affirmed by the Courts below. This however, is quite distinct from concluding that SIPCOT contractually (in the main agreement) assumed primary liability for the Subcontractor-Respondent's payment claims in respect of agreements made with the Appellant. The fact that the Respondent was represented and present in parleys and meetings between SIPCOT and the Appellant or that it was referred to in the correspondence exchanged between them does not lead to the conclusion that a Tripartite contract had come into effect by evolution."

6. Learned counsel for the petitioner also submits that since third party is not a party to the Agreement, therefore, in the present case, the dispute is only between the petitioner and the respondent. He further submits that a sole Arbitrator be appointed by this Court and liberty may also be granted to the respondent to raise all the pleas before the Arbitrator.

7. There is a force in the submission of the learned counsel for the petitioner. Accordingly, the prayer made in the petition is allowed. Justice Mukul Mudgal, retired Chief Justice of Punjab & Haryana High Court (Mobile No.9818000250) is appointed as sole Arbitrator to adjudicate the disputes arising out of the agreement between the parties as mentioned in the present petition. The parties are also allowed to file their respective claims and counter-claims before the

Arbitrator. Liberty is granted to the respondent to raise all the grounds as mentioned in the reply to the petition.

8. The Arbitrator shall ensure the compliance of the provisions of Arbitration and Conciliation (Amendment) Act, 2015 before commencing the arbitration. The fees of the learned Arbitrator shall be in terms of the schedule of the amended Act. The parties to appear before the Arbitrator on 8th September, 2016 at 4.00 p.m. for directions.

9. The petition is accordingly disposed of.

10. Copies of this order be given dasti to the learned counsel for the parties and a copy thereof be delivered to the learned Arbitrator forthwith.

(MANMOHAN SINGH) JUDGE AUGUST 23, 2016

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter