Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Jayaswals Neco Ltd. vs Union Of India And Anr.
2016 Latest Caselaw 5009 Del

Citation : 2016 Latest Caselaw 5009 Del
Judgement Date : 2 August, 2016

Delhi High Court
M/S Jayaswals Neco Ltd. vs Union Of India And Anr. on 2 August, 2016
              THE HIGH COURT OF DELHI AT NEW DELHI

%                                     Judgment delivered on: 02.08.2016

+       EX.P. 224/2010

M/S JAYASWALS NECO LTD.                               ..... Decree Holder
                                   versus
UNION OF INDIA AND ANR.                               ..... Judgment Debtors

Advocates who appeared in this case:
For the Decree Holder : Mr Shatadru Chakraborty and Ms Kartika
                         Chaudhary.
For the Judgment Debtors: Mr R. V. Sinha & Mr R. N. Singh.
CORAM:-
HON'BLE MR JUSTICE VIBHU BAKHRU

                               JUDGMENT

VIBHU BAKHRU, J

1. The present petition has been filed by the Decree Holder (hereafter

'JNL') to enforce an arbitration award dated 09.10.2002. According to the

Judgment Debtors (hereafter 'the railways'), an excess payment of `12,483/-

has been made which is required to be recovered from JNL. JNL disputes

this and claims that as on 11.02.2015, a sum of `2,53,481/- was outstanding

after adjustment of the amounts paid by the railways and this amount is

payable along with further interest at the rate of 18% p.a. till the date of

payment.

2. The central controversy relates to the manner in which payments

already made by the railways are to be adjusted; the railways claim that the

amounts paid by it are to be appropriated partly towards the award of claim

no.1 - which the railways terms as the principal amount- and partly towards

interest in terms of the calculation sheet forwarded to JNL at the time of

making the remittance. JNL, on the other hand, claims that the amounts paid

by the railways are to be first appropriated towards interest and the balance

towards the awarded amount.

3. The aforesaid controversy arises in the context of the following facts,

which are briefly narrated as under:

3.1 The parties entered into a contract bearing no.99/Track-

II/22/14/8/70248 dated 18.06.1999 (hereafter 'the Contract'), in terms of

which JNL agreed to supply and the railways agreed to purchase 7 lakh

pieces of SGCI inserts. The railways short closed the Contract and that

gave rise to disputes between the parties. The Contract contained an

arbitration clause and, accordingly, the disputes were referred to Arbitration.

The arbitration proceedings culminated into an Award dated 09.10.2002

(hereafter 'the Award') in favour of JNL; the operative parts of which is

quoted below:

"8.1 Claim no. 1

...Therefore, the Respondents shall pay to the Claimants the difference between the rate agreed between the parties in their agreement dated 18.6.1999 and the rate as actually paid for 98,219 nos. inserts.

Simple interest of 12% over and above the price differential between the amount due and the amount actually paid from 45 days after the above payment become due till the date of declaration of the award is considered to be reasonable and is, therefore, allowed.

xxxxx xxxxxx xxxxx xxxxx

11. Respondents are directed to arrange payment of this award as stated within a period of 90 days from the publication of this award, failing which interest @ 18% shall be payable by the Respondents to the Claimant till the payment of this arbitration award."

3.2 The railways impugned the Award before this Court in OMP

No.45/2003 which was dismissed by an order dated 14.12.2005. The

railways appealed against the aforesaid order before a Division Bench of

this Court (in FAO(OS) Nos.578, 579 of 2006) which was also rejected by

an order dated 06.08.2007. The railways carried the matter to the Supreme

Court by way of a Special Leave Petition (being SLP(C) No.13848-13849

of 2008) which was also dismissed by an order dated 04.02.2010.

3.3 Since the railways had not paid the amount as awarded, JNL filed the

instant petition under Section 36 of the Arbitration and Conciliation Act,

1996 (hereinafter the „Act‟) read with Order XXI Rule 10 of the Code of

Civil Procedure, 1908 (hereafter „the CPC‟) seeking recovery of a sum of

`1,12,01,529.32/- which included interest till 17.02.2010.

3.4 JNL's main claim in the arbitration - Claim no 1 - related to loss

arising out of abrupt short closure of the Contract. The Arbitrator awarded

the aforesaid claim in favour of JNL and held that expected supplies from

JNL till 09.03.2000 should have been to the order of 6,48,219 inserts against

4,90,000 inserts actually accepted; therefore, the Arbitrator held that JNL's

loss be computed as the difference between the rate agreed between the

parties as per the Contract and the rate actually paid for 98,219 inserts.

3.5 There were certain controversies regarding the above calculation of

loss; the railways asserted that JNL had, admittedly, supplied 5,85,000

inserts and not 4,90,000 inserts and, therefore, the loss as awarded was to be

computed only in respect of 63,219 and not 98,219 inserts as stated in the

Award. The railways further claimed that the loss was to be computed at

the rate of ` 3.22 per insert and not ` 6.80 per insert as indicated in the

Award.

3.6 This Court - by an order dated 17.07.2013 - accepted the railways‟

stand that the figure of 98,219 inserts as stated in the award was an obvious

error and the loss awarded was to be computed for 63,219 inserts and not

98,219 inserts. However, the contention that the difference in the price per

insert was ` 3.22 and not ` 6.80 was rejected.

3.7 In the meantime, the railways remitted a draft of ` 6,24,119/- to JNL

under the cover of remittance note dated 18.06.2010 along with a

calculation sheet. The said calculation sheet indicated that the railways

computed the loss awarded at `2,03,565/- (for 63,219 inserts at the rate of `

3.22 each) and had, accordingly, worked out that a sum of ` 6,19,086/-

would cover the entire awarded amount including interest upto 10.05.2010.

3.8 Immediately on receipt of the aforesaid remittance, JNL filed an

application dated 02.08.2010 under Order XXI Rule 11(2) r.w. Order XXI

Rule 2(1) of the CPC, inter alia, stating that it had accepted the said

remittance of `6,24,119/- as part payment without prejudice to its rights

and contentions and further prayed that this Court may record the said

receipt as part payment towards the amount due from the railways.

3.9 The said application was disposed of by an order dated 13.08.2010.

3.10 The railways paid a further sum of `8,71,791/- on 18.11.2013 and this

according to the railways fully satisfied the Award. JNL disputes the

aforesaid contention as according to it, a further sum of `2,11,753/- was

payable as on that date. In view of the difference in calculation of the

amount payable, this Court, by an order dated 20.11.2014 directed the

parties to appear before the Registrar General, who was directed to examine

their respective calculations and submit a report. In compliance with the

aforesaid order, the Registrar General heard extensive arguments on behalf

of the parties and submitted a report on 18.09.2015, inter alia, accepting the

stand of the railways that an excess payment of `12,483/- had been paid to

JNL.

4. A perusal of the said report indicates that the difference in the

calculation as submitted by JNL and the railways stems from the manner of

appropriation of the part payments made by the railways.

Submissions

5. Mr Sinha, the learned Senior Standing counsel appearing for the

railways submitted that remittance of a sum of `6,24,119/- was made to JNL

partly on account of principal and partly on account of interest. Since, JNL

had accepted the same without protest, it was not open for JNL to now

contend that it had appropriated the aforesaid sum only towards interest and

not in the manner as indicated in the calculation sheet enclosed along with

the remittance note. He further referred to the decision of a Constitution

Bench of the Supreme Court in Gurpreet Singh v.Union of India: (2006) 8

SCC 457 and on the strength of the said judgment contended that if a

Judgment Debtor while making a deposit indicates that the same is towards

a specified debt, it is not open for the Judgment Debtor to appropriate the

amount deposited towards any other head. He referred to Section 59 to 61 of

the Indian Contract Act, 1872 (hereafter „the Contract Act‟) and submitted

that the principles of appropriation embodied therein are also applicable to

part payments made towards a decree. He submitted that in the present

case, the railways had specifically indicated in the calculation sheet

submitted with the remittance note dated 18.06.2010 that out of the sum of `

6,24,119/-, `2,03,565/- was towards the principal amount. He contended

that, therefore, JNL could not appropriate the amounts paid by the railways

towards interest.

6. Mr. Sinha further contended that if the amounts paid by the railways

was appropriated in the manner as canvassed by JNL, it would amount to

the railways paying interest on interest.

7. Mr Chakraborty, the learned counsel for JNL countered Mr Sinha‟s

submission and submitted that the remittance note dated 18.06.2010 - under

the cover of which a sum of `6,24,119/- was remitted to JNL - did not

specify that any amount was to be appropriated towards principal. He

further submitted that immediately on receipt of the aforesaid remittance,

JNL had filed an application dated 02.08.2010 which clearly stated that the

amount had been accepted without prejudice to the rights and contentions of

JNL and, therefore, it could not be stated that JNL had lost its right to adjust

the aforesaid sum towards interest due on the decretal amount.

8. Mr Chakraborty further submitted that it is settled law that in absence

of an agreement between the parties and/or any specific direction from the

Court, the amount paid by the Judgment Debtor would have to be first

appropriated towards interest followed by adjustment towards the principal

amount.

9. He also relied on the decisions of the Supreme Court in Leela Hotels

Limited v. Housing and Urban Development Corporation Ltd.: (2012) 1

SCC 302, V. Kala Bharathi & Others v. Oriental Insurance Company

Limited, Branch Chitoor: (2014) 5 SCC 577 and Gurpreet Singh (supra).

He also referred to the decision of the Division Bench of this Court in Ircon

International Ltd. v. M. Moolji (Bombay): (2012) 188 DLT 52 (DB) in

support of his contentions.

Reasoning and Conclusion

10. In the present petition, JNL has quantified the amount recoverable

under the award as `1,12,01,529.32/-. The manner in which the aforesaid

sum is computed is stated in paragraph 4 of the petition and is quoted

below:-

              S.        Particulars                            Amount        (In

              No.                                              Rs.)

1. i) Cost of 60,000 Inserts (58219-98219) @ Rs.31.95 Rs.19,17,000.00

ii) Cost of 98219 inserts @ Rs.6.80 (Amended Contract price 31.95 - paid Rs.6,67,889.20 price 27.45) Total Payable to JNL Rs.25,84,889.20

2. Interest for 960 days @12% Award allows payment if interest @12% from

45 days after the due date of payment to be made. As per award, last supply date taken 09.03.2000. Due date of payment taken as 09.04.2000 45 days after the due date taken as 24.05.2000. Award allows this interest to be paid up to 90 days after the award. Award date is 09.10.2002. 90 days after the award is 09.01.2003. Therefore interest is for the Rs.8,15,833.52 period 24.05.2000 to 09.01.2003 which comes to 960 days.

3. Interest for 2617 days @18% Award allows payment of interest @18% after 90 days of award, if not paid within this time, till the date of payment. Hence, interest from 10.01.2003 to 17.02.2010. Rs.

78,00,806.00/-

                     Total             amount           with          interest
                     Rs.01,12,01,529.32

(Rs. One crore twelve lacs one thousand five hundred and twenty nine and paise thirty two only)

11. In so far as the sum of `19,17,000/- on account of the cost of 60,000

inserts is concerned, there is no dispute that the same has not been awarded

in the Award. Against the aforesaid claim, the railways remitted a sum of

`6,24,119/- on 18.06.2010 enclosing therewith a calculation sheet which

was captioned "Tentative calculation of Liabilities arising out of Arbitration

Award". The said calculation sheet is reproduced below:-

S Claim by claimant (2) Amount as per Amount as per No. claimant (3) award (4)

1. 1) Cost of 60,000 Inserts Not part of

(58219 - 98219 @ Rs. 31.95 Rs. 19,17,000.00 award. Hence, disallowed

ii) Cost of 98219 inserts @ Rs. 6.80 Rs. 6,67,889.20 Rs. 2,03,565 (Amended Contract price (63219 X 3.22) 31.95 -paid price 27.45 Ref. Annexure 'C' for details Total payable to JNL Rs.25,84,889.20 Rs.2,03,565

2. Interest for 960 days @12% Award allows payment If interest @12% from 45 days Rs.8,15,833.52 Rs. 58,091.32 after the due date of (on item 1 for 960 (on item 1 for payment to be made. As days) 868 days from per award, last supply 25.5.2000 to date taken 09.03.2000. 09.10.2002) Due date of payment taken as 09.04.2000 45 days after the due date ken as 24.05.2000. Total 1+2 Award allows this Rs.2,61,656.32/-

interest to be paid up to 90 days after this award.

                     Award date is 09.10.2002,                             To be verified
                     90 days after the award is                            by FA& CAO,
                     09.01.2003.                                           C. Rly
                     Therefore, interest is for
                     the period 24.05.2000 to
                     09.01.2003 which comes
                     to 960 days.
          3.       Interest for     2617   days
                   @18%. Award allows
                   payment of interest @18% Rs. 78,00,806.60               Rs, 3,57,429.70
                   after 90 days of award, if                              (on
                   not paid within this time,                              Rs.2,61,656.32/-
                   till the date of payment.                               for 2770 days @
                   Hence,       interest  from                             18% from
                   10.01.2003 to 10.03.2010.                               10.10.2002
                                                                                  till
                                                                           10.05.2010)

                                                                           To be verified
                                                                           by FA&CAO,
                                                                           C. Rly





                         Total                 Rs.1,12,01,529.3

                                              2                  Tentative
                                                                 Rs.6,19,086/-
                                                                 upto
                                                                 10.05.2010

Tentative per day Interest beyond 10.05.2010 is Rs.129.04/-

12. According to the railways, the amount awarded to JNL against claim

no.1- loss due to abrupt short closing of the contract - was `2,03,565/-; this

was calculated by taking the number of inserts as 63,219 inserts and by

taking the difference in the value as `3.22 (the amount awarded is calculated

by multiplying the number of inserts by the difference in the rate). JNL, on

the other hand, computed the amount awarded against claim no.1 as

`6,67,889.20/-; this was calculated by taking the number of inserts as

98,219 (as mentioned in the Award) and taking the difference in the

amended cost price and the price paid as `6.80.

13. The controversy as to the number of inserts short purchased and the

difference in rates was considered by this Court on 17.07.2013. This Court

accepted the contention advanced by the railways that the number of inserts

ought to be taken at 63,219 and not 98,219 as indicated in the Award. The

Court found that the same was an apparent error. However, this Court did

not accept the railway‟s contention that the difference in rate was `3.22 and

not `6.80 as stated in the Award.

14. In terms of the order passed on 17.07.2013, the amount awarded to

JNL against Claim no.1 was crystallised as `4,29,889/- (multiplying 63,219

inserts at the rate of `6.80). In the order dated 17.07.2013, the Court noted

that the railways had already paid a sum of `6,24,119/- against the decretal

amount and further directed that the remaining money be paid along with

interest on the unpaid balance within a period of four weeks from that date.

Although, JNL had initially claimed that interest at the rate of 12% p.a.

awarded on the aforesaid amount of loss would be payable for 960 days -

that is, from 24.05.2000 till 09.01.2003 - the same was erroneous as the

interest awarded was to be computed till the date of the award, that is, for a

period of 868 days from 24.05.2000 till 19.10.2002. There is no dispute

between the parties on this aspect.

15. Thus, admittedly, the amount awarded to JNL in terms of the award is

`5,52,567/- (`4,29,889 plus `1,22,677/- being interest @ 12% p.a. for 868

days). On the aforesaid basis, JNL submitted its calculation for the amount

due till 11.02.2015. The said calculation is reproduced below:-

    S.      Particulars                         Interest         Amount
   No.
                                               (In Rs.)         (in Rs.)

       1. Cost of 63,219 inserts @ ₹6.80                           4,29,889
          (differentia between rate agreed
          to be paid and the rate actually
          paid)
       2. Interest for 868 days @ 12%            1,22,677          5,52,567
          (begins to run 45 days from due
          date of payment i.e. from
          24.05.2000 till the date of award
          i.e. 09.10.2002)
       3. Interest for 2715 days @ 18%           7,39,834
          (begins to run 90 days after the
          date of award i.e. 10.01.2003 till
          17.06.2010 since in the present
          case, the part payment of ₹
          6,24,119/- was received on
          18.06.2010
                                               Total interest     ₹12,92,400
                                                ₹ 8,62,511
       4. Payment received from Judgment        ₹6,24,119
          Debtor on 18.06.2010
       5. Balance as on 18.06.2010              ₹ 2,38,392        ₹6,68,281
       6. Interest for 1247 days @ 18%          ₹ 4,10,966       ₹ 10,79,247
          (from 19.06.2010 till 17.11.2013
          since in the present case, part
          payment of ₹ 8,71,791/- was
          received on 18.11.
          2013)
       7.                                      Total interest    ₹ 10,79,247
                                               - ₹ 6,49,358
       8. Payment received from judgment        ₹8,71,791
           debtor on 18.11.2013
       9. Balance as on 18.11.2013                   0            ₹2,07,456
       10. Interest for 42 days @ 18% from        ₹ 4,297         ₹2,11,753
           19.11.2013 till 31.12.2013
       11. Interest for 365 days @18% from       ₹ 37,342         ₹ 2,49,095
           01.01.2014 till 31.12.2014
       12. Interest for 42 days @ 18% from        ₹ 4,386         ₹2,53,481




                  01.01.2015 till 11.02.2015



16. The railways also forwarded their calculation sheet (to Mr. Sinha)

according to which the entire decretal amount stood paid. The said

calculation is reproduced below:-

          S.              Admissible Claim              Amount
          No.
          1.      Cost of 63219 insert @ Rs.3.58        Rs. 2,26,324.02
                  (6.80-3.22+3.58); payment @
                  Rs.3.22 has already been done by
                  Central    Railway      for   total
                  Rs.6,24,119/- vide cheques dated
                  18.06.2010
          2.      Interest for 868 days @ 12%.          Rs. 64,586.06 (on S. No.1
                  Award allows payment of interest      for     868     days    from
                  @ 12% from 45 days after due          25.05.2000 to 09.10.2002
                  payment to be made. As date of        total (1)+(2) = 2,90,910.075
                  award is 09.10.2002 interest @
                  12% is payable from 24.05.2000
                  to 09.10.2002 i.e. 868 days
          3.      Interest for 4036 days @ 18%          Rs.5,79,014.66
                  Award allows payment @ 18%            Total          (1)+(2)+(3)=
                  after 90 days of award if not paid    Rs.8,69,924.74          say
                  within this time till date of         Rs.8,69,925/-
                  payment. Say it will be paid by
                  31.10.2013, hence interest from
                  10.10.2002 till 31.10.2002
          4.      Extra interest beyond 31.10.2013      Rs.1866/-
                  @ Rs.1435 per day for 13 days as      Total=Rs.8,69,925+1866=R
                  payment done on 13.11.2013            s.871791





17. An examination of the aforesaid calculation sheet submitted by the

railways indicate that they have proceeded on the assumption that the entire

payment of `6,24,119/- made on 18.06.2010 was liable to be appropriated as

per the calculation sheet forwarded along with the remittance note dated

18.06.2010; that is, `2,03,565/- against award of claim no. 1 and the balance

against interest (both pre and post award). Accordingly, the railways

computed the loss on differential amount payable on account of cost of

inserts at `2,26,324.02/- (`4,29,889/- less `2,03,565/- remitted on

18.06.2010) and further worked out the interest on the aforesaid amount.

18. According to JNL, the entire amount of `6,24,119/- was to be

adjusted against the interest (post award) outstanding as on that date i.e. on

18.06.2010.

19. Thus, the only issue to be addressed is whether the amount paid by the

railways was to be appropriated in the manner as indicated by them in their

calculation sheet annexed with their remittance note dated 18.06.2010.

20. It is ex facie apparent that the calculation submitted by the railways is

fundamentally flawed. In terms of the award, amount awarded to JNL is

`5,52,567/- (`4,29,889 plus interest @ 12% p.a. for 868 days - `1,22,677/-

). This is the decretal amount that the railways were liable to pay to JNL.

The assumption that it consisted of multiple debts, one on account of award

against claim no. 1 and another on account of interest is palpably erroneous.

The award in favour of JNL is a single indivisible award. And, the interest

awarded (at the rate of 12% p.a.) is subsumed under the Award. The

contention that it was open for the railways to dissect this amount and

decide as to how much of its remittance was to be appropriated against

claim no.1 and how much against interest is plainly erroneous.

21. The next aspect to consider is whether JNL was entitled to

appropriate the amount remitted on 18.06.2010 towards post award interest.

22. The law as to appropriation of payments towards decretal amount is

now well settled. In M/s Industrial Credit and Development Syndicate v.

Smithaben H. Patel and Ors: (1999) 3 SCC 80, the Supreme Court had

observed as under:-

"In view of what has been noticed hereinabove, we hold that the general rule of appropriation of payments towards a decretal amount is that such an amount is to be adjusted firstly strictly in accordance with the directions contained in the decree and in the absence of such direction, adjustments, be made firstly in payment of interest and costs and thereafter in payment of the principal amount. Such a principle is, however, subject to one exception, i.e. that the parties may agree to the adjustment of the payment

in any other manner despite the decree. As and when such an agreement is pleaded, the onus of proving is always upon the person pleading the agreement contrary to the general rule or the terms of the decree schedule. The provisions of Sections 59 to 61 of the Contract Act are applicable in cases where a debtor owes several distinct debts to one person and do not deal with cases in which the principal and interest are due on a single debt."

23. In view of the above, Mr Sinha's contention that JNL was obliged to

appropriate the remittance made towards the award first and then towards

post award interest is not merited. In order for the railways to succeed in the

aforesaid contention, they would have to establish that the parties had

agreed that the payments made by them would be appropriated in the

manner as indicated in the calculation sheet.

24. In the facts and circumstances of the case, it is difficult to accept that

the parties had arrived at any such agreement. The remittance note dated

18.06.2010 does not indicate as to under which head the remittance was

being made by the railways. The calculation sheet annexed with the

remittance only indicates that it is a tentative calculation of liabilities arising

out of the Arbitration Award. JNL had accepted the same and had

immediately applied to the Court indicating that it had received the

remittance of `6,24,119/- without prejudice to all its rights and contentions.

25. Mr Sinha's contention that Section 59 of the Contract Act is

applicable to part payments made towards a decree and, therefore, JNL

would be obliged to apply the payments made by the railways towards the

specified heads is also without merit. First and foremost, Section 59, 60 &

61 of the Contract Act has no application to post decretal payments. This

was unequivocally held by the Supreme Court in Industrial Credit and

Development Syndicate (supra) in the following words :-

".....We are of the opinion that Sections 59 and 60, Contract Act, would be applicable only in pre-decretal stage and not thereafter. Post-decretal payments have to be made either in terms of the decree or in accordance with the agreement arrived at between the parties though on the general principles as mentioned in Sections 59 and 60 of the Contract Act. As and when such an agreement either express or implied is relied upon, the burden of proving it would always be upon its propounder. The judgment debtors, in the instant case, are proved to have failed in discharging such an onus. There does not appear to be any obligation on the decree holder to intimate the judgment debtor that the amount paid to him had not been accepted in the manner specified by him in the letter accompanying the payment insisting upon such a course would result in unnecessary burden upon the financial institutions and conferment of unwanted unilateral discretion in favour of the defaulters. Acceptance of the plea that the amount paid first should be adjusted in the principal amount would not only be against the provision of law but against the public policy as well. To provide security, continuity and certainty in business transaction, the Legislature has been making specific provisions in that regard which may be found in various provisions of the Negotiable Instruments Act or Order 37, CPC and other statutory provisions."

26. Further, the Supreme Court held in Gurpreet Singh (supra) that

Sections 59 to 61 of the Contract Act "would not get attracted when there is

only one debt due. Nor have they any direct application in a case where the

debt due has merged in a decree and the applicable rule then would be what

is provided in the decree itself or the general rule applicable in execution of

money decrees."

27. In Meghraj & Ors. v. Mst. Bayabai & Ors.: (1969) 2 SCC 274, the

Supreme Court considered the effect of deposit made by a Judgment

Debtor-Mortgager towards the decretal debt in terms of Order XXI Rule 1

of the CPC and observed as under:-

"..... any payment made by the Debtor is in the first instance to be applied towards satisfaction of interest and thereafter to the principal. It was for the mortgagors to plead and prove an agreement that the amount which were deposited in Court by the Mortgagors were accepted by the Mortgagees subject to a condition imposed by the Mortgagors....."

28. The rationale behind the principle of permitting JNL to appropriate

the amounts received, first towards interest was explained by the Supreme

Court in Leela Hotels (supra) in the following words:-

"The philosophy behind the principle set out in Meka Venkatadri's case (supra) and as reiterated in Rai Bahadur Seth Nemichand's case (supra) and also in Smithaben's

case (supra) and then consistently followed by this Court, is that a debtor cannot be allowed to take advantage of his default to deny to the creditor the amount to which he would be entitled on account of such default, by way of elimination of the principal amount due itself, unless, of course, the provisions of Section 59 of the Indian Contract Act, 1872, were attracted or there was a separate agreement between the parties in that regard. That is not so in the instant case and, accordingly, the creditor cannot be denied its dues on a unilateral stipulation that the amount of Rs.89.78 crores was being deposited as against the principal sum due in terms of the Award. Since the said amount was accepted by the Appellant on protest, it would be entitled to appropriate the same against the interest which was due and payable till that date on the principal amount, as has been asserted by it."

29. Mr Sinha's contention that accepting the JNL's calculation would

amount to directing payment of interest on interest is also unsustainable.

The Arbitrator had awarded loss due to abrupt short closure of the contract

as well as simple interest at the rate of 12% over the price differential

between the amount due and actually paid from 45 days after the above

payments became due till the date of declaration of the Award. The railways

were directed to make the payment of the aforesaid sum (that is loss, plus

interest) within a period of 90 days, failing which the Arbitrator directed

that railways would be liable to pay interest at the rate of 18% till the date of

payment. The claims awarded by the Arbitrator namely loss on account of

abrupt short closure of contract and simple interest at the rate of 12%

indicated the amount awarded by the Arbitrator. The amount so awarded is

not amenable to being split into principal and interest.

30. In the aforesaid view, there was no question of considering further

payment of interest at the rate of 18% p.a. on the awarded sum as an interest

on interest. This view is also supported by the following observations made

by the Supreme Court in V. Kala Bharthi (supra):-

"The next finding of the High Court is with regard to interest on interest. In money suit, the amount consists of principal and interest till the suit is filed. But, in case of award passed under the Act, the question of inclusion of any interest on the decretal amount does not arise. Unfortunately, the High Court proceeded on the assumption that it amounts to interest on interest which is prohibited under Section 3(3)(c) of Interest Act, 1978 (for short, 'the Interest Act').This is not so, as in the facts and circumstances of the present case, the decree passed by the trial Court or the appellate Court does not contain the mode of appropriation and in the absence of any such direction, the decree-holder is entitled to appropriate the amount deposited by the judgment debtor first towards interest, then cost and thereafter towards principal."

31. In the aforesaid circumstances, the railways are directed to make

payment of `2,07,456/- and interest calculated at the rate of 18% on the said

amount from 18.11.2013 till the date of payment within a period of four

weeks from today.

32. List on 15.09.2016.

VIBHU BAKHRU, J AUGUST 02, 2016 MK/RK

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter