Citation : 2015 Latest Caselaw 6861 Del
Judgement Date : 11 September, 2015
*IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of decision: 11th September, 2015
+ W.P.(C) 8754/2015 & CM No.19330/2015 (for stay)
M/S ROHTAK WIRE AND HARDWARE STORE..... Petitioner
Through: Mr. S.D. Singh & Ms. Surabhi
Shukla, Advs.
Versus
THE SECRETARY, MINISTRY
OF DEFENCE & ORS ..... Respondents
Through: Mr. Rakesh Kumar & Mr. Shraddha Bhargava, Advs. for R-1 to 4.
CORAM:-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
CM No.19329/2015 (for exemption)
1. Allowed, subject to just exceptions.
2. The application is disposed of.
W.P.(C) 8754/2015
3. The petition impugns the decision dated 18th August, 2015 of the
respondents No.1 to 6 Union of India (UOI) through the Ministry of Defence
and its various officials (respondent No.7 is MSTC Ltd. which had done the
e-auction herein below mentioned) taken in pursuance to the order dated 5 th
August, 2015 of this Court in W.P.(C) No.7432/2015 earlier filed by the
petitioner. Axiomatically, a direction is also sought to the respondents No.1
to 6 UOI to permit the petitioner to take delivery of the goods.
4. It is the case of the petitioner that:
(i) It had participated in an e-auction held on 24th July, 2015 by the
respondent No.7 MSTC Ltd. of the goods of the ordinance
factory, Katni , Madhya Pradesh of the respondents No.1 to 6
UOI and its bid upon being found to be the highest was
accepted and the balance price, after adjusting the earnest
money deposited, was demanded from it and though it
deposited / tendered the balance price but the respondents No.1
to 6 UOI arbitrarily, illegally and without any reason did not
deliver the goods and cancelled the auction inspite of a binding
contract having come into existence between the petitioner on
the one hand and the respondents No.1 to 6 UOI on the other
hand.
(ii) The petition earlier filed by the petitioner in this regard came up
before this Court on 5th August, 2015, when the counsel for the
respondents No.1 to 6 UOI appearing on advance notice stated
that representations made by the petitioner will be considered
by the respondents No.1 to 6 UOI and decided within two
weeks thereof. Recording the said statement, the earlier
petition was disposed of directing the respondents No.1 to 6
UOI to decide the representation within two weeks.
(iii) In pursuance thereto, the representations of the petitioner have
been rejected vide impugned order dated 18th August, 2015.
5. It has inter alia been reasoned in the impugned order:
(a) That as per the auction process, on conclusion of the e-auction,
the highest bidder was to be notified by the system at the e-mail
address through which the bid was made through system
generated "Sale Intimation Letter".
(b) That the auction process also required an acceptance letter /
dismantling and disposal order to be issued by e-mail and post
confirmation copy within 7 days from closure of the bid.
(c) That while auctioning, the right to accept or reject the highest
offer without any reason was reserved.
(d) That owing to a technical error, a defect crept in in feeding the
reserve price and of which the respondent No.7 MSTC was
subsequently informed and auction was cancelled.
(e) That the auction was cancelled owing to the reserve price
having been fed as Rs.22/- only instead of Rs.22,50,000/-.
(f) That thus the bid of the petitioner of Rs.12,51,001/- could not
be accepted.
(g) That no acceptance letter / delivery order, only upon issuance of
which a binding contract was to come into being, was issued
and thus no binding contract has come into existence.
(h) That the earnest money deposit of the petitioner as also of the
other bidders was returned and the balance sale consideration
tendered by the petitioner also was not accepted.
6. Needless to state, the counsel for the petitioner finds error with the
aforesaid reasoning of the respondents No.1 to 6 UOI.
7. I have at the outset enquired from the counsel for the petitioner as to
how the petitioner is entitled to the relief in the nature of specific
performance of the contract, even if any had come into existence. It is
pointed out to the counsel for the petitioner that the contract, even if had
come into existence, was not and has not been pleaded to be such which can
be specifically enforced or is on the parameters laid down in the Specific
Relief Act, 1963 of contracts which are specifically enforceable. Attention
of the counsel for the petitioner has also been invited to the Sale of Goods
Act, 1930 whereunder also the remedy of the petitioner, even if claims to be
a purchaser who has been denied delivery of goods inspite of having
tendered the sale price, is of recovery of damages only, of course, after
mitigating the loss if any.
8. It has further been enquired, as to how the petitioner, even if entitled
to the relief claimed, is entitled to maintain a petition under Article 226 of
the Constitution of India therefor, the relationship of the petitioner with the
respondents being purely contractual.
9. The counsel for the petitioner only contends that since the seller in the
present case is respondents No.1 to 6 UOI and which ought to act reasonably
and since the respondents No.1 to 6 UOI in the present case has acted
unreasonably, this writ petition as well as relief of specific performance
would be maintainable.
10. In my opinion, the applicability of substantive law of specific
performance in Specific Relief Act and sale of goods, is not to be different
qua UOI from that qua a private seller. If the contract, under the substantive
law is not specifically enforceable, specific performance thereof cannot be
granted merely because the seller is UOI or the State. There are no
allegations of mala fide or ulterior motives for the action of the respondents,
in which case the Court may hold the State to its contract even if were to be
not specifically enforceable under the Specific Relief Act.
11. The counsel for the petitioner refers to para 170 of the Natural
Resources Allocation, In Re, Special Reference No.1 of 2012 (2012) 10
SCC 1, where, relying on Shrilekha Vidyarthi Vs. State of U.P. (1991) 1
SCC 212, it was reiterated that, i) the State actions in the contractual field
are meant for public good and public interest and are expected to be fair and
just; ii) that Article 14 of the Constitution of India governs the State actions
in contractual field also; iii) the state action must be informed of reasons and
must not be arbitrary; and, iv) where no plausible reason or principle is
indicated or where the impugned action is ex facie arbitrary, the onus is on
the State to justify the same.
12. However the aforesaid judgment does not deal with the question of
granting the relief of specific performance of a contract not otherwise
specifically enforceable under the Specific Relief Act, merely because the
respondent / defendant is a „State‟.
13. Faced therewith, the counsel for the petitioner states that he is not
pressing for the relief of delivery of goods but the unfairness of the action of
the respondents may be adjudicated in this writ petition.
14. Adjudication cannot be piecemeal i.e. on the aforesaid limited aspect,
in this writ petition and vis-a-vis the claim for damages, in an ordinary civil
proceeding. Such piecemeal adjudication has always been deprecated.
Reference in this regard may be made to Moolchand Khairati Ram Hospital
& Ayurvedic Research Institute Vs. Secretary (Labour), GNCTD
MANU/DE/1135/2001, Al-Qahtani Pipe Coating Terminal Vs. Minerals
Sales (P) Ltd. MANU/MH/1278/2008, Claridges Hotel Pvt. Ltd. Vs. M.M.
Bhagat & Co. 92 (2001) DLT 61 and also to D.P. Maheshwari Vs. Delhi
Administration (1983) 4 SCC 293.
15. Moreover, once the petitioner has given up the only relief claimed in
this petition, the petition in any case would not be maintainable on the
reasoning given by the Supreme Court in Arnit Das Vs. State of Bihar
(2001) 7 SCC 657 followed by this Court in Association for Development
Vs. Union of India 167 (2010) DLT 481 (DB), Gurugobind Singh
Indraprastha University Vs. Dr. Amit Rajput 2015 SCC Online Delhi 9130
and recently in order dated 9th September, 2015 in W.P.(C) No.6555/2013
titled Neelam Kapur Vs. Director of Education that the jurisdiction under
Article 226 is not to be exercised academically and only in relation to the
facts and claims of a particular case.
16. I may also mention that the action of the respondents No.1 to 6 UOI in
the present case, of cancelling the e-auction, even if inspite of a contract
having come into existence, cannot by any stretch of imagination be said to
be falling within the parameters laid down by the Supreme Court in
Shrilekha Vidyarthi supra. If indeed it is true that the reserve price, owing
to a technical glitch, was mentioned as Rs.22/- instead of Rs.22,50,000/, the
same in my view was reason enough for the respondents No.1 to 6 UOI to
take remedial action to ensure that there is no loss of public monies. None
can be permitted to take advantage of such technical mistakes.
17. Once it is found that the relief in the nature of specific performance of
a contract cannot be granted owing to the contract even if any being not
specifically enforceable, no purpose would be served in this Court
adjudicating the said aspect.
18. Though the counsel for the petitioner has taken me through the
documents to contend that a contract has indeed came into being but in the
light of the view taken aforesaid, no purpose would be served in rendering
any decision thereon.
19. The counsel for the petitioner then draws attention to the Minutes of
the Meeting held between the petitioner and the officials of the respondents
on 7th August, 2015 to show that though the petitioner had given a proposal
for price negotiation, being the highest bidder, and the respondents had also
agreed to the same but no such negotiations were in fact held and no
reference thereto is made in the speaking order also.
20. That, in my view would not change or affect the aforesaid view. I can
only prima facie observe that once the reserve price had been wrongly
mentioned, the same would vitiate the entire auction process and the
negotiations if any held by the respondents with the petitioner as the highest
bidder in an auction which was vitiated may itself become subject matter of
challenge by some other bidder, embroiling the respondents No.1 to 6 UOI
in endless litigation.
21. Not only so, the invocation of writ remedy in a purely contractual
matter is also not permissible as recently held by Supreme Court in Joshi
Technologies International Inc. Vs. Union of India MANU/SC/0616/2015.
22. I may also notice that it is the plea of the counsel for the respondents
No. 1 to 6 UOI appearing on advance notice that this Court does not have
territorial jurisdiction, the entire cause of action if any having arisen at
Katni.
23. The petition is therefore dismissed with liberty to the petitioner to
avail of the civil remedies in accordance with law.
No costs.
RAJIV SAHAI ENDLAW, J SEPTEMBER 11, 2015 'gsr‟..
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!