Citation : 2015 Latest Caselaw 8077 Del
Judgement Date : 20 October, 2015
*IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of decision: 20th October, 2015
+ W.P.(C) 10030/2015 & CM No.24548/2015 (for stay).
M/S SHAURYA COAL CARRIERS PVT. LTD...... Petitioner
Through: Mr. Anunaya Mehta, Adv.
Versus
UNION OF INDIA & ORS ..... Respondents
Through: Mr. Dev P. Bhardwaj, CGSC for R-
1&2/UOI with Col. Lamba.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
CM No.24549/2015 (for exemption)
1. Allowed, subject to just exceptions.
2. The application is disposed of.
W.P.(C) 10030/2015 & CM No.24548/2015 (for stay)
3. The petition (i) impugns the letter dated 5 th October, 2015 of the
respondent No.2 Directorate General of Resettlement (DGR), Ministry of
Defence to the respondent No.3 Mahanadi Coalfields Ltd. (MCL) requiring
the respondent No.3 MCL to confirm the termination of the contract with the
petitioner and to withhold all payments to the petitioner till clearance from
the respondent No.2 DGR; (ii) impugns the letter dated 24 th April, 2015 of
the respondent No.2 DGR to the petitioner to submit parawise comments to
the earlier letter dated 6th April, 2015 of respondent No.3 MCL to the
respondent No.2 DGR; (iii) seeks a direction to the respondents to "refund
all amounts withheld from the petitioner" including the amount of
approximately Rs.91 lakhs withheld earlier as also the amount of
approximately Rs.50 lakhs withheld in terms of the letter dated 5 th October,
2015; and, (iv) seeks to restrain the respondents from withholding any
amounts of the petitioner and from taking any coercive action against the
petitioner without first issuing a proper show cause notice to the petitioner.
4. Having prima facie not found the petition entertainable, the counsel
for the petitioner has been heard at length. He has argued:
(a) that the petitioner is an Ex-Serviceman (ESM) company;
(b) that the respondent No.2 DGR has been set up to rehabilitate
the ESM ;
(c) that the respondent No.2 DGR has signed a Memorandum of
Understanding (MoU) with the respondent No.3 MCL of sponsorship
of ESM companies for transportation of coal;
(d) that the petitioner company was so sponsored by the respondent
No.2 DGR;
(e) that the petitioner company, instead of signing a fresh
agreement with the respondent No.3 MCL, merely ratified the MoU
aforesaid which governs the relationship between the petitioner and
the respondent No.3 MCL;
(f) that Clause 20 of the said MoU deals with "Termination of
Contract" and inter alia provides that if an ESM company is not
adhering to the conditions of MoU and/or is found indulging in any
malpractice, MCL/Coal Subsidiary may initiate action for termination
of contract, withholding of payment of bills, forfeiture of security
deposit but, after issuing a show cause notice to the ESM company
under intimation to DGR and after affording opportunity to ESM
company to initiate corrective / remedial measure;
(g) that the respondent No.2 DGR has issued a show cause notice
to the petitioner and which the petitioner could not place before this
Court owing to the extreme urgency in which this petition has been
filed but there has been no compliance of Clause 20 of the MoU
aforesaid which governs the contract of transportation of coal under
which the petitioner has been performing;
(h) that the respondent No.2 DGR has on the contrary directed the
respondent No.3 MCL to terminate the contract of the petitioner in
non-compliance with Clause 20 of the MoU;
(i) that in response to the various show cause notices issued by the
respondent No.2 DGR, the petitioner has submitted its replies and has
fully satisfied the respondent No.2 DGR of being in compliance of all
the terms and conditions and has also remedied / ratified the violations
which had occurred inadvertently and owing to be misguided from the
actions of the respondent No.2 DGR.
5. I have at the outset enquired from the counsel for the petitioner, as to
how the writ remedy under Article 226 of the Constitution of India is
available to the petitioner, the dispute subject matter of petition being in the
realm of private contract and having no public law character and whether not
the appropriate remedy for the petitioner is a remedy under the civil law or
of arbitration, if agreed to.
6. The counsel for the petitioner, well prepared to answer the said query,
has at the outset stated that there is no arbitration clause in the agreement
between the parties and the only other remedy available to the petitioner
would be by way of a civil suit. Else on law, he has invited attention to ABL
International Ltd. Vs. Export Credit Guarantee Corporation of India Ltd.
(2004) 3 SCC 553, Whirlpool Corporation Vs. Registrar of Trade Marks
(1998) 8 SCC 1 and to the latest dicta in Joshi Technologies International
Inc. Vs. Union of India (2015) 7 SCC 728.
7. The Supreme Court in Joshi Technologies International Inc. supra
having dealt also with the other two judgments cited as well as a host of
other judgments and having inter alia observed that the summarisation of the
legal position in paras 27 & 28 of ABL International Ltd. has to be
understood in the context of discussion that preceded and noted in the said
judgment, I have heard the counsel for the petitioner further with respect to
Joshi Technologies International Inc. supra only and have enquired from
him, how the present petition can be said to be having any public law
character attached to it and whether not the present petition is inter alia for
enforcing a money claim per se arising out of contractual obligations and
which have been held to be normally not entertainable, except in the
exceptional circumstances.
8. The counsel for the petitioner has attached the public law character to
the present action by contending that the act of the respondents No.1 & 2
Union of India (UOI) and DGR of sponsoring ESM companies for coal
transportation is a rehabilitative and welfare measure for the ESM and thus
is not purely a matter of contract but has a public law element to it.
9. I have further enquired from the counsel, whether not all actions of
the State are in a way for welfare of the citizens or for some section/s of the
society or the other and that if that were to be the test, whether not it would
tantamount to writ remedy being available against the State, including in
matter of contract and which otherwise in the judgment supra has been held
to be not.
10. The counsel for the petitioner has then contended that the writ petition
should be entertained because the respondent No.2 DGR is asking the
respondent No.3 MCL to act in violation of the terms and conditions of the
MoU which was entered into by the respondent No.2 DGR itself with the
respondent No.3 MCL.
11. I am afraid, the matter would still be in the realm of the contract.
Moreover, all that the respondent No.2 DGR did vide the impugned letter
dated 5th October, 2015 was to ask the respondent No.3 MCL to confirm the
termination of the contract of the petitioner. If the respondent No.3 MCL
before affecting the said termination is required to follow a procedure, I am
sure the said procedure shall be followed, if not already followed and there
is nothing to suggest that it will not be.
12. Notice in this regard may however be taken of the letter dated 6 th
April, 2015 of the respondent No.3 MCL to the respondent No.2 DGR. The
respondent No.3 MCL in the said letter informed (i) that during verification
of documents of the Pay Loaders deployed by the petitioner, it was found
that the ownership of one of the Pay Loaders was not as per the norms of the
MoU; (ii) that the petitioner in response thereto had stated that the said Pay
Loader may not be allowed to operate; (iii) that on re-scrutiny of documents,
it was further found that another Pay Loader also did not fulfil the terms of
the MoU and therefore the deployment of that Pay Loader also was stopped;
(iv) that thus the work done by the aforesaid two Pay Loaders was not as per
the guidelines for deployment of fleet, in the MoU; therefore an amount of
Rs.91.29 lakhs had been withheld from the payment to the petitioner, based
on the calculation of difference of ESM loading rate to civilian rate of the
contemporaneous time; (v) that the issue of wrongful deployment of the Pay
Loaders by the petitioner and withholding of payment was examined by a
committee constituted at the headquarter which had also opined to recover
the amount for differential rate of loading for ESM and civilian contract; (vi)
that since a violation of Para 8 of the MoU had been committed by the ESM
company, the case file was being forwarded for further scrutiny and
recommendation.
13. The aforesaid is suggestive of, response of the petitioner having been
called for to each and every violation.
14. This Court in writ jurisdiction cannot entertain the dispute, whether
the petitioner was in breach or not and if not whether the contract has been
wrongfully terminated and if so to what relief the petitioner is entitled to.
Suffice it is to state that the contract by its nature was terminable and not
specifically enforceable.
15. The counsel for the respondents No.1&2 appearing on advance notice
has also contended that in fact the petitioner is in default of payment to its
manpower and which is also making a claim against the respondents and
which claim will have to be satisfied by the respondents.
16. The counsel for the petitioner, though not disputing, states that the
petitioner would clear the said payments when its own monies are released
by the respondents.
17. The counsel for the respondents No.1&2 has also handed over a
booklet titled "Guidelines on Formation and Running of Ex-Servicemen
Coal Transport Companies" published by the Self Employment Directorate
of DGR, Ministry of Defence in June / July, 2007 and which in its Appendix
D contains "Clauses to be Incorporated in the Memorandum and Articles of
Association" of ESM company and Clause 11 whereof requires an ESM
Coal Transport Company sponsored by DGR to submit various reports and
returns as directed by the DGR from time to time and provides that non-
submission of specified reports or incorrect facts and figures may result in
cancellation of sponsorship / non-renewal of contract; Clause 13 similarly
provides that violating or non-compliance of all the clauses may lead to
withholding of payments by coal subsidiary or cancellation of sponsorship
by the DGR. Needless to state, once the sponsorship of the petitioner is
withdrawn by the respondent No.2 DGR, the question of the respondent
No.3 MCL dealing with the petitioner does not arise.
18. The counsel for the respondents No.1&2 has from the departmental
file brought by Col. Lamba to the Court also shown a letter dated 6th August,
2015 of the respondent No.2 DGR to respondent No.3 MCL detailing as
many as 12 show cause notices issued to the petitioner, right from 13 th July,
2009 till 8th July, 2015 and the replies thereto of the petitioner and stating
that since the petitioner "has been constantly violating the provisions of the
MoU" and the Guidelines on Formation and Running of Coal Transportation
Company, 2007 vide which the petitioner company is governed, immediate
action under para 20(a) of MoU was recommended against the petitioner.
19. The aforesaid also takes care of the grievance of the petitioner of the
respondent No.2 DGR having directed the respondent No.3 MCL to act in
violation of the said guidelines.
20. The aforesaid file also contains the notice dated 21st July, 2015 issued
by the respondent No.2 DGR to the petitioner and its three Directors asking
them to visit the DGR on 4th August, 2015 for meeting, as their previous
replies to the show cause notices issued earlier had not been found
satisfactory.
21. I am therefore satisfied that it cannot also be said that there is any
violation of the principles of natural justice as is also pleaded in the petition.
22. No case for entertaining the writ petition is thus made out.
23. Dismissed.
24. I however clarify that the observations contained herein are merely for
the purpose of adjudicating the maintainability of the writ petition and in the
event of any civil proceedings being undertaking by the petitioner would
have no binding effect in adjudication thereof.
No costs.
RAJIV SAHAI ENDLAW, J.
OCTOBER 20, 2015 „bs‟..
(corrected and released on 21st November, 2015)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!