Citation : 2015 Latest Caselaw 3543 Del
Judgement Date : 1 May, 2015
*IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of decision: 1st May, 2015
+ LPA No.364/2014
MOHAN NAIR ..... Appellant
Through: Mr. Ramesh Kumar, Adv.
Versus
RAJIV GUPTA & ORS. ..... Respondents
Through: Mr. Sunil Magon, Adv. for R-1 to 3.
Mr. Vivek B. Saharya, Adv. for R-
4/NDMC.
Mr. Sanjeev Goyal and Mr. Abhjoy
Banerjee, Advs. for R-5 with S.I.
Bishambar Dayal.
CORAM :-
HON'BLE THE CHIEF JUSTICE
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
RAJIV SAHAI ENDLAW, J
1. This intra-court appeal impugns the order dated 14 th March, 2014 of
the learned Single Judge of this Court, of disposal of Cont. Cas (C)
No.148/2014 filed by the appellant with liberty to the appellant to seek his
civil remedies against the respondents.
2. Notice of the appeal was issued and replies have been filed on behalf
of respondents No.1&2, respondent No.3 and respondent No.4. We heard the
counsel for the appellant, the counsel for the respondents No.1 to 3 and the
counsel for the respondent no.4/NDMC. The respondent No.5 is the Sub
Inspector of Police of the concerned police station.
3. To understand the controversy, it is necessary to commence from the
beginning.
4. The appellant /his father was an old tenant at a rent of Rs.100/- per
month in property No.N-5/2, Connaught Circus, New Delhi under the
respondent No.2 The Motor and General Finance Limited of which the
respondent No.1 is the Director. The appellant, on 4th January, 2003 was
dispossessed from his tenancy premises in execution of an order of eviction
obtained by the respondent no.2 Company in a petition for eviction under the
Delhi Rent Control Act, 1958 filed against some other person. The appellant,
on 14th January, 2003, filed an application under Section 25 of the Rent Act
in the Court which had passed and executed the order of eviction and
whereunder the appellant had been dispossessed from his tenancy premises.
The said application was allowed vide order dated 7th July, 2011 of the Court
of the Rent Controller. It was held that the appellant was a tenant under the
respondent No.2 Company in respect of premises No. N-5/2, Connaught
Circus, New Delhi as shown in the site plan Ex.AW5/4 and as portion D2 in
the site plan Ex. OW1/1 and that the appellant had been wrongfully
dispossessed therefrom. Accordingly, the respondent No.2 Company was
directed to restore to the appellant possession of N-5/2, Connaught Circus,
New Delhi as shown in site plan AW5/2 and as portion D2 of site plan
Ex.OW1/1.
5. However it appears that the respondent No.2 Company after
wrongfully taking over possession of the premises aforesaid in the tenancy
of the appellant, had commenced demolishing the same. On an application
of the appellant, vide order dated 15th July, 2003 the respondent No.2
Company was directed to maintain status quo and not to carry out further
demolition. Upon the respondent No.2 Company again, in or above the year
2005 proceeding to demolish the said premises, the appellant filed an
application. The respondent No.2 Company however took a stand that the
premises had fallen on their own. The appellant accordingly, after the order
dated 7th February, 2011 of restoration of his possession, applied to the Rent
Controller for a direction to the respondent No.2 to re-construct the property.
The respondent No.2 objected contending that the property could be re-
constructed only as per the provisions of the NDMC byelaws and no
building could be reconstructed in derogation thereof and thus no order for
reconstruction could be passed against the respondent No.2 Company. The
Rent Controller, vide order dated 24th August, 2011 accepted the said plea of
the respondent No.2 Company and refused to direct the respondent No.2
Company to reconstruct the tenancy premises. However the Rent Control
Tribunal in an appeal filed by the appellant in this regard, vide order dated
5th July, 2012 directed the respondent No.2 Company to their original
condition as shown in the site plans aforesaid.
6. The aforesaid order of the Rent Controller and Rent Control Tribunal
have attained finality.
7. The respondent No.2 however failed to comply therewith and which
lead to the appellant filing Cont.Cas (C) No.754/2012 in this Court.
8. The respondent No.2 Company contested the said contempt case by
again contending that it had written several letters to the NDMC seeking
permission to reconstruct the premises in the tenancy of the appellant as
directed by the Rent Control Tribunal but no satisfactory response had been
received from NDMC. The respondent No.2 Company further offered to pay
cost of re-construction to the appellant to enable the appellant to himself
restore the premises to the original condition at his own risk and
responsibility and in terms of the order of the Rent Controller and further
offered that it will cooperate and sign all papers to enable the appellant to do
so. The said offer of the respondent No.2 Company was accepted by the
appellant who submitted that no permission was required from NDMC;
reliance in this regard was placed on the observations in the order dated 5th
July, 2012 supra of the Rent Control Tribunal. It was further the contention
of the counsel for the appellant as recorded in the order of that day that even
as per the building byelaws, construction which was either demolished or
which fell on its own could be restored and no permission therefor was
required.
9. The Cont.Cas(C) No.754/2012 was accordingly disposed of by
accepting and taking on record the statements of the counsels for the parties
and ordering the parties to remain bound by the same and a direction for
payment of the agreed sum of money by the respondent No.2 Company to
the appellant towards construction cost was passed.
10. However the appellant was not able to himself also reconstruct and
restore the property to its original condition, according to the appellant
owing to collusion between the officials of the respondent No.2 Company,
Police and the NDMC, who prevented the appellant from doing so. This led
to the filing of Cont.Cas (C) No.148/2014 wherefrom this appeal arises.
11. The learned Single Judge however vide the impugned order dismissed
the said contempt case in limine observing, i) that the respondent No.2
Company, at the time of disposal of Cont. Cas(C) No.754/2012 earlier filed
by the appellant had not given any undertaking to facilitate re-construction /
restoration of the premises by the appellant and in fact the appellant had
agreed to carry out the said works at his own risk and responsibility; ii) if
according to the appellant the respondents were deliberately obstructing
reconstruction / restoration activity being undertaken by him, then it was for
the appellant to invoke the civil remedies as may be available to him in law
but contempt proceedings would not be a substitute for the same.
Accordingly, the contempt case was disposed of with liberty to the appellant
to seek his civil remedies against the respondents.
12. Inspite of being conscious of an appeal / LPA being maintainable only
against an order punishing for contempt, we issued notice of this appeal
finding that, in the legalese, the orders / directions aforesaid of the Rent
Controller and the Rent Control Tribunal which had attained finality, have
remained unimplemented thereby making a mockery of the process of law
and the likely effect whereof would be erosion of faith and respect in the
orders / directions of the Court. Sure enough, the counsel for the
respondents No.1 to 3 also, on the very first date, took objection as to the
maintainability of the appeal. The said objection has been reiterated in the
reply filed to the appeal.
13. The appellant has also impleaded Sh. Arun Mitter, another Director of
the respondent No.2 company as respondent No.3. The respondent No.3 has
filed a separate reply but through the same advocate as the respondents No.1
and 2. The respondent No.4 Chief Architect, NDMC has also filed a reply /
status report to the effect that though the respondent No.2 company was
directed to submit a proposal for the proposed construction in the prescribed
proforma but had not done so and without permission of the NDMC the
construction in terms of the order of the Rent Control Tribunal could not be
carried out.
14. The learned Single Judge, in the impugned judgment has not given
any reasoning whatsoever for holding as to why the contempt case was not
maintainable and as to why the appellant instead take up remedies in law
except for recording that the respondent No.2 Company at the time of
disposal on 25th February, 2013 of the earlier Cont.Cas (C) No.754/2012
filed by the appellant had not given any undertaking.
15. However the power to invoke contempt jurisdiction of this Court is
not limited to cases of breach of undertaking only. Reliance by the counsel
for the appellant in this respect on Rama Narang Vs. Ramesh Narang
(2006) 11 SCC 114 is apposite. It was held that the words "willful
disobedience to any judgment decree, direction, order, writ or other process
of a Court" in Section 2(b) of the Contempt of Courts Act, 1971 denote wide
nature of the power of the Court and that in the case of consent order /
decrees, even where no undertaking was given to the Court, the question
would still arise whether the party in breach of such promise could be called
upon to answer proceeding in contempt for willful disobedience of the
consent order. While addressing the said question, it was held that all
decrees and orders including consent decrees or orders are executable but
merely because they are executable would not take away the Courts
jurisdiction to deal with the matter under the contempt jurisdiction, if the
Court is satisfied that the violation of the order or decree is such that it
would warrant punishment under Section 13 of the Act on the ground that
the contempt substantially interferes or tends substantially to interfere with
the due course of justice. It was further held that in such circumstances, it
would neither be in consonance with the statute, judicial authority, principle
or logic to draw any distinction between the willful violation of the terms of
a consent decree and willful violation of a decree which is passed on
adjudication. It was yet further held that ultimately, the matter is one of the
Court's discretion having regard to the facts of the case. Finding that the
violation in the facts of that case to be a violation of the Court‟s order, it was
held that the violation was contumacious.
16. We, for the reasons following are of the view that the present appeal is
maintainable and the findings returned by the learned Single Judge in the
impugned order are liable to be set aside and the respondents No.1 to 3 have
indeed committed contempt of Court and appropriate directions required to
be issued to enforce the orders of the Rent Controller and the Rent Control
Tribunal:
(A) The finding of the Rent Controller which has attained finality is
that the respondent No.2 company of which respondents No.1
and 3 are Directors, in execution of an order of eviction not
obtained against the appellant, wrongfully dispossessed the
appellant on 4th January, 2003 from the premises in his/in his
father‟s tenancy since the year 1953.
(B) Though the appellant, within a few days of his dispossession,
on 14th January, 2003 filed objections under Section 25 of the
Rent Act as aforesaid, but the respondents No.1 to 3 inspite of
knowledge of pendency of the said objections, on or about 6th
June, 2003 got the said premises demolished by complaining to
the NDMC of the same being unauthorized. The appellant had
to again approach the Court for a direction to the respondents
No.1 to 3 to maintain status quo.
(C) Inspite of the said order of status quo, further damage was
caused to the premises, though the explanation of the
respondents No.1 to 3 was that the premises have fallen on its
own.
(D) The objections filed by the appellant under Section 25 were
finally allowed as aforesaid on 7th July, 2011 with a direction to
the respondent No.2 Company to restore possession to the
appellant and direction for reconstruction/restoration of the
premises to the original condition was also issued on 24th
August, 2011.
(E) Though the respondents No.1 to 3 did not challenge the said
orders of the Rent Controller and Rent Control Tribunal but
also did not comply with the same taking the excuse of having
applied to the NDMC and NDMC having not permitted
reconstruction / restoration of the premises, inspite of the said
plea having not found favour with the Rent Control Tribunal
and thereby compelling the appellant to approach this Court in
Cont.Cas (C) No.754/2012.
(F) Faced therewith, the respondents No.1 to 3 offered to pay the
cost of reconstruction / restoration of the premises to the
appellant to enable the appellant to himself restore the premises
as directed by the Rent Control Tribunal and which offer was
accepted by the appellant.
(G) In this manner, the respondents No.1 to 3 avoided decision on
merits of Cont.Cas (C) No.754/2012.
(H) From a reading of the order dated 25th February, 2013 of this
Court in Cont.Cas(C) No.754/2012 it can by no means be said
that the appellant discharged the respondents No.1 to 3 from
their obligations under the orders of the Rent Controller and
Rent Control Tribunal or that the liability of the respondents
No.1 to 3 to comply with the orders / directions of the Rent
Controller and the Rent Control Tribunal came to an end. This
is quite evident from the statement of the counsel for the
respondents No.1 to 3 recorded in the said order to the effect
that the said respondents had no intention to flout the orders of
the Rent Controller and the Rent Control Tribunal and that
inspite of the respondents paying the agreed cost of
reconstruction / restoration to the appellant and the appellant
himself taking over the said work, the respondents would
remain liable to cooperate in the said works and would sign all
papers and documents which they may be required to sign in
this regard. Not only so, the said order dated 25 th February,
2013 also binds the respondents to the statement made by them
before the Court.
(I) The learned Single Judge is thus clearly in error in the
impugned order in proceeding on the premise that the directions
/ orders of the Rent Controller and the Rent Control Tribunal
averring contempt of which the earlier Cont.Cas(C)
No.754/2012 had been filed ceased to be enforceable or that a
fresh arrangement had come into being between the parties in
terms of the order dated 25th February, 2013 or that the
appellant was required to take civil remedies for enforcement of
the obligations of the respondents arising from the order dated
25th February, 2013.
(J) Not only so, once the right of the appellant to restoration of
possession of the premises in its tenancy by reconstruction
thereof in the same position as it existed prior to demolition
thereof has been established in a competent Court, to direct the
appellant for fresh adjudication is to make as aforesaid a
mockery of law and the process of the Courts and which this
Court can by no stretch of imagination allow to happen. If the
same were to be allowed, the same will send a message to the
public at large that the orders / directions of the Court need not
to be complied with.
(K) the net effect today is that the respondent No.2 Company,
inspite of accepting and allowing the orders aforesaid of the
Rent Controller and Rent Control Tribunal to attain finality, has
for the last nearly three years been successful in evading
implementation / enforcement thereof.
(L) The impugned order dated 14th March, 2014, holding that the
orders of the Rent Controller and Rent Control Tribunal are no
longer actionable/enforceable and the relationship of the parties
is now governed by the terms recorded in the order dated 25 th
February, 2013, in our view is not a order declining to initiate
proceedings for contempt or of dropping the proceedings for
contempt or an order acquitting or exonerating the contemnor
but a decision made on the merits of the dispute between the
parties;
(M) The Supreme Court in Midnapore Peoples' Coop. Bank Ltd.
Vs. Chunilal Nanda (2006) 5 SCC 399 has held that any
direction issued or decision made by the High Court on the
merits of a dispute between the parties, will not be in the
exercise of jurisdiction to punish for contempt and therefore not
appealable under section 19 of the Act unless such direction or
decision is incidental to or inextricably connected with the
order punishing for contempt, in which event the appeal under
section 19 of the Act can also encompass the incidental or
inextricably connected directions. It was further held that if the
High Court decides an issue or makes any direction relating to
the merits of the dispute between the parties in a contempt
proceedings, the aggrieved person is not without remedy; such
an order is open to challenge in an intra-court appeal.
(N) The counsel for the respondents No.1 to 3 has not even argued
that the obligations / liability of the respondents No.1 to 3 under
the orders aforesaid of the Rent Controller and the Rent
Controller Tribunal stand extinguished; rather, to be fair to the
counsel for the respondents No.1 to 3, he had stated that the
respondents No.1 to 3 have no objection to the appellant
reconstructing / restoring the premises to the same condition as
shown in the site plan referred to in the order of the Rent
Controller and would create no impediments thereto, if the
NDMC was not to object to the same.
(O) Thus the impugned order of the learned Single Judge treating
the relationship of the appellant and the respondent No.2
company to be governed by the terms and conditions contained
in the order dated 25th February, 2013 and the liability of the
respondent No.2 company to comply with the directions
contained in the orders aforesaid of the Rent Controller and
Rent Controller Tribunal to have stood extinguished, has but to
be set aside.
(P) We have considered whether after holding so, to remand the
matter to the learned Single Judge to proceed with the
contempt. However, the matter being very old and having
heard the counsel for the NDMC also and is the only objection
to the implementation / enforcement of the orders of the Rent
Controller and the Rent Controller Tribunal, we do not feel the
need therefor.
(Q) The counsel for the NDMC of course, with undue vehemence
contended that without plans for construction being submitted
and being sanctioned by the NDMC no re-construction /
restoration of the premises to the original condition can be
permitted.
(R) We are however of the opinion that the said argument is today
not available. We may highlight that the said contention, this
time by the counsel for the NDMC, is but an echo of the
contention raised by the counsel for the respondent No.2
company before the Rent Controller and which had found
favour with the Rent Controller who refused to direct the
respondent No.2 company to reconstruct the property.
However, the Rent Control Tribunal in appeal held that the
contention that permission from NDMC would be required or
the reconstruction would invite an action against the respondent
No.2 company was misconceived. It was held that once it was
found that the respondent No.2 company had illegally obtained
possession of the said portion in the tenancy of the father of the
appellant, the appellant was entitled to get it re-erected. It was
also noticed that it was not the case of the respondent No.2
company that the said portion was illegal. The said finding also
has attained finality and though NDMC was not a party to the
proceedings before the Rent Controller or the Rent Control
Tribunal, but is bound thereby. The attempt of the NDMC to
help the respondents no.1 to 3 is evident.
(S) We may in this regard also notice that the finding which has
attained finality is, of the father of the appellant being a tenant
with respect to the said premises since the year 1953. The
NDMC areas prior to the year 1994 when the NDMC Act was
enacted were governed by the Punjab Municipal Act, 1911.
Under the said Act, action for demolition of unauthorized
construction even if any could be taken only within six months
of the construction. It has been held by the Division bench of
this Court in NDMC Vs. H.K. Choudhary
MANU/DE/1985/2009 that the NDMC could not take any
action for demolition of any unauthorized construction carried
out prior to 27th May, 1984. Thus the question whether the
construction of the premises in the tenancy of the appellant / his
father was legal or illegal is now not relevant. Further, the
NDMC having wrongfully demolished the said construction on
the complaint of the respondent No.2 company of the same
being illegal, cannot now object to reconstruction / restoration
thereof.
(T) The principles of restitution would apply to such
reconstruction/restoration of premises to the original condition
and the procedure applicable to raising new construction would
not apply. The action of reconstruction/restoration to original
condition which has been directed, is nothing but undoing of
what has been found to be done illegally. Both, respondents
no.1 to 3 as well as NDMC are privy to such illegality and
cannot now object to such restitution on the grounds raised.
(U) We, in arriving at the aforesaid conclusion, have been guided
strongly by our view that to say that the orders of the Rent
Controller and Rent Control Tribunal are unimplementable and
unenforceable has the tendency of making the law and the
Court, a laughing stock. The perception of "the law" as Mr.
Bumble (in Oliver Twist) said "is a ass − a idiot" will be
cemented if the Courts themselves hold their own orders to be
unimplementable and unenforceable. It is the duty of every
Court to prevent its machinery from being made a sham,
thereby running down the Rule of Law and rendering itself an
objection of ridicule. The House of Lords, in Attorney General
Vs. Guardian Newspaper Ltd. [1987] 1. W.L.R. 1248 observed
that public interest requires that we have a legal system and
courts which command public respect and if the courts were to
make orders manifestly incapable of achieving their avowed
purpose, law would indeed be an ass. Justice Krishna Iyer in
Bushing Schmitz Private Ltd. Vs. P.T. Menghani (1977) 2
SCC 835 also held each Court to be clothed with the purpose to
prevent, its process from being rendered a parody and the rule
of law from becoming an objection of public ridicule and the
law, a laughing stock. We are of the opinion that to allow the
orders aforesaid of Rent Controller and Rent Control Tribunal
from remaining unimplemented on the grounds which were
considered while making the said order, would indeed make the
law a laughing stock and frustrate justice.
(V) The Division Bench of this Court in Prof. Ram Prakash Vs.
Bengali Sweet Centre ILR (2012) Delhi 808 has also held that
the Courts, if owing to shackles of technicalities, do not grant
the relief, if found to be due, would be doing disservice rather
than service and that the Courts, if do not come to the rescue of
a litigant entitled to relief, would not be rendering justice for
which the Courts have been set up. It was observed that justice
is a virtue which transcends all borders and neither the rules of
procedure nor technicalities of law can stand in its way.
Reliance was placed on M.S. Grewal Vs. Deep Chand Sood
(2001) 8 SCC 151 laying down that Court will lose their
efficacy if they cannot possibly respond to the needs of the
society.
(W) Here, we have a large corporate (respondent no.2) controlled by
one of the most influential residents of the city (respondent
no.3) pilled against a small tenant who has only the Courts to
rely upon. The respondents no.1 to 3 have succeeded in, first
illegally dispossessing the said tenant from the premises in its
tenancy and after the tenant, by litigating for nearly nine years
obtained an order of repossession/restoration, now for the last
nearly three years, from implementation thereof. The Supreme
Court in Krishnadevi Malchand Kamathia Vs. Bombay
Environmental Action Group (2011) 3 SCC 363 observed that
justice is only blind or blindfolded to the extent necessary to
hold its scales evenly; it is not and must never be allowed, to
become blind to the reality of the situation, lamentable though
that situation may be.
17. We accordingly allow this appeal by directing:
(i) that the appellant shall be entitled to forthwith
reconstruct / restore the premises in its tenancy as shown
in the site plans referred to in the orders aforesaid of the
Rent Controller and neither the NDMC nor the
respondents No.1 to 3 or anyone else on behalf of the
respondent No.2 company shall cause any disruption in
the said works;
(ii) if either of them cause any disruption, the appellant shall
be entitled to apply for appropriate measures in this
proceeding itself;
(iii) if the respondents comply with this order, the contempt
case against them shall stand discharged; however, if
they cause or allow to be caused any interference in the
reconstruction / restoration of the premises, this Court
will be constrained to proceed further with the contempt
case to its logical conclusions;
(iv) the respondent No.2 company is also burdened with costs
of Rs.20,000/- of this appeal payable to the appellant
within 15 days hereof.
RAJIV SAHAI ENDLAW, J
CHIEF JUSTICE MAY 1, 2015 „pp/gsr‟
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!