Citation : 2015 Latest Caselaw 2254 Del
Judgement Date : 17 March, 2015
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CS(OS) 3804/2014 & IA No.24849/2014
Decided on : 17.03.2015
IN THE MATTER OF:
M/S RAM KRIPAL SINGH CONSTRUCTION PVT. LTD. Plaintiff
Through : Mr. Rajesh Kumar, Advocate
versus
DAV COLLEGE MANAGING COMMITTEE & ORS. ..... Defendants
Through :
CORAM
HON'BLE MS.JUSTICE HIMA KOHLI
HIMA KOHLI, J.(Oral)
1.
The plaintiff has instituted the present suit against the
defendants/DAV College Managing Committee praying inter alia for
recovery of a sum of `41,75,625/- towards damages along with interest.
2. The case has been placed before the court by the learned Joint
Registrar who had recorded in the order dated 10.12.2014 that the suit
appears to be barred by limitation.
3. As per the averments made in the plaint, the plaintiff is in the
business of undertaking construction work for government departments
and other bodies and had participated in a pre-qualification tender for
construction of a building at Pehowa, Kurukshetra, Haryana, in terms of
an advertisement dated 13.1.2010 issued by the defendant No.1,
inviting bids. Upon the tender process being finalized, the work was
awarded in favour of the plaintiff on 16.6.2010. On 5.8.2010, an
agreement was executed between the plaintiff and the defendants. As
per the conditions stipulated in said agreement, the work was to be
completed by the plaintiff by 15.3.2011. The plaintiff has averred that
though they had arranged the entire resources at the construction site
for executing the work, the defendants had failed to make the drawings
available to its officers. The plaintiff claims that having failed to take
necessary steps in furtherance to the contract, the defendants had
breached their obligations under the said contract.
4. As per the plaintiff, though the first phase of the work at the site
was to be completed in less than one year, reckoned from 5.8.2010, the
date when the agreement was executed, the defendant No.2 had failed
to respond to the repeated requests made by it for being provided the
drawings of the construction required to be undertaken at the site. The
plaintiff has averred in the plaint that it had written a letter dated
28.9.2010 to the defendant No.2 for supplying the drawings, followed by
a letter dated 19.2.2011, asking for release of the mobilization expenses
incurred by it, but the defendants had not responded and finally, the
plaintiff was compelled to institute the present suit, for claiming recovery
of a sum of `41,75,625/-, on account of mobilization and de-mobilization
of resources, idle labour, bank charges and earnest money etc.
deposited with the defendants, as detailed in para 17 of the plaint.
5. It has been stated in para 20 of the plaint that the plaintiff had
waited for one and a half years in anticipation of payments to be made
by the defendants in terms of the invoice raised by it on 19.2.2011, but
since the defendants remained impervious, it had to issue a legal notice
dated 5.1.2013. The defendants did reply to the aforesaid legal notice on
22.8.2013, but they had denied their liability to pay any amount to the
plaintiff.
6. The records reveal that the present suit was instituted by the
plaintiff on 13.11.2014 whereas it had raised an invoice on the
defendants for expenses allegedly incurred by it under the contract, on
19.2.2011. In other words, by the time the present suit was instituted,
the period of three years prescribed under the Limitation Act had already
expired. In fact, the prescribed period of limitation would have expired
on 19.2.2014, whereas the suit has been instituted nine months
thereafter.
7. Counsel for the plaintiff insists that the suit is not barred by
limitation and seeks to refer to the reply dated 22.08.2013 sent by the
defendants to the plaintiff's legal notice and states that they had
admitted therein that the agreement in question had never been acted
upon. He submits that the date of the said admission should be taken
into consideration for calculating the limitation for purposes of instituting
the present suit.
8. The Limitation Act, 1963 prescribes a limitation of three years for
instituting a suit for compensation on account of breach of a contract
under Article 55 of the Schedule attached thereto and the said period of
three years has to be reckoned from the date when the contract was
broken or where there are successive breaches, when the breach in
respect of which the suit is instituted, occurs or where the breach is
continuing, when it ceases.
9. As per the averments made by the plaintiff in the cause of action
para, the cause of action had arisen in its favour and against the
defendants for the first time on 16.6.2010, when the plaintiff had
qualified for the work; it again arose on 5.8.2010, when the agreement
was executed between the plaintiff and the defendant No.1. The next
relevant date has been mentioned as 11.8.2010, when the plaintiff
states that it had written a letter to the defendants demanding various
documents from it and again on 28.9.2010, when the plaintiff had
demanded the drawings of the site plan from the defendant No.3.
10. It has been further stated by the plaintiff that the cause of action
once again arose in its favour on 18.2.2011, when it had raised an
invoice for a sum of Rs.41,75,625/- on the defendants in respect of the
expenses incurred on account of mobilization/demobilization of the
resources. The next relevant date mentioned is of 17.09.2011, when the
plaintiff had demanded payments from the defendants under the
contract and then on 05.01.2013, when the plaintiff had served a legal
notice upon the defendants demanding amounts which the defendants
had refused to pay vide their reply dated 22.8.2013.
11. It is apparent from a perusal of the cause of action para of the
plaint that in its letter dated 19.2.2011, the plaintiff had mentioned
having raised a final invoice of `41,75,625/- allegedly incurred by it
under the contract and it had called upon the defendants to pay the said
amount within ten days. On application of Article 55 of the Schedule
under the Limitation Act, the cause of action had clearly arisen in favour
of the plaintiff on 19.2.2011, when the final amount due and payable by
the defendants was quantified by it and the period of three years for
instituting the suit shall have to be computed from the said date. When
calculated in such a manner, the period of three years available in the
statute for instituting a suit for compensation on account of breach of
contract would have expired on 19.2.2014, whereas the present suit
came to be instituted by the plaintiff after almost nine months, on
13.11.2014.
12. Section 9 of the Limitation Act further prescribes that where once
time has begun to run, it continuous running and no subsequent
disability or inability to institute a suit or make an application, stops it.
In the present case, the cause of action had indisputably arisen on
19.2.2011, the date when the plaintiff had raised an invoice for the
disputed amount on the defendants and the period of three years for
instituting a suit for recovery, if reckoned from the said date, would have
continued running till it would have expired in due course, on 19.2.2014.
Merely because the plaintiff has chosen not to initiate legal action for a
period of one year thereafter and served a legal notice on the
defendants on 5.1.2013, would not be a ground to extend the period of
limitation for purposes of invoking its civil remedies against the
defendants.
13. As for the contention of the learned counsel for the plaintiff that in
their reply dated 22.8.2013, the defendants had acknowledged their
liability to make payments to the plaintiff, it may be noted that the said
submission is contrary to the plaintiff's own averments in the cause of
action para and are not even borne out from a perusal of the reply sent
by the defendants to the plaintiff's legal notice. There is nothing at all
that has been stated by the defendants in their reply that can be
construed as an admission on their part of their liability to pay any
amounts to the plaintiff on the basis of the invoice raised by it under
cover of letter dated 19.2.2011. Resultantly, a fresh period of limitation
cannot begin to run on the basis of the defendants' reply to the plaintiff's
legal notice. The statutory period of three years have to be computed
from 19.2.2011 and the said period would have expired on 19.2.2014,
whereas the present suit was instituted by the plaintiff on 13.11.2014,
which is far beyond the permissible period of three years.
14. As a result, the present suit is held to be barred by limitation and
is accordingly dismissed, along with the pending application.
(HIMA KOHLI)
MARCH 17, 2015 JUDGE
mk/rkb/sk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!