Citation : 2015 Latest Caselaw 2144 Del
Judgement Date : 12 March, 2015
* HIGH COURT OF DELHI AT NEW DELHI
+ R.S.A. No.164/2014
Decided on : 12th March, 2015
RAMNATH GARG ...... Appellant
Through: Mr. Sugriva Dubey, Advocate.
Versus
BSES YAMUNA POWER LTD. & ANR. ...... Respondents
Through: Mr. Deepak Kumar Vijay, Adv. for R-1.
Mr. Kshitij Sharda, Advocate for R-2.
CORAM:
HON'BLE MR. JUSTICE V.K. SHALI
V.K. SHALI, J. (ORAL)
1. This is an appeal filed by the appellant against the respondents on
account of rejection of his appeal by the learned Additional District Judge
vide order dated 19.4.2014 of disallowing the application of the appellant
under Section 5 of the Limitation Act.
2. Briefly stated the facts leading to filing of the present appeal are
that the appellant filed a suit bearing No.437/09 for permanent and
mandatory injunction against the Municipal Corporation of Delhi and
Delhi Electric Supply Undertaking (DESU) in the year 1995 in which
subsequently, BSES Yamuna Power Limited, a service provider
company, was impleaded in lieu thereof DESU.
3. The case which was setup by the appellant was that the appellant
had purchased property No.4/47, Sarvaria Market, Vishwas Nagar,
Shahdara, Delhi-110032 by way of a registered sale deed and his name
was mutated in the record of the MCD. He was also paying house tax to
the MCD. The appellant temporarily allowed respondent No.2, Roshan
Lal, to occupy the property No.4/47 at his request that he would vacate
the same as and when an alternative accommodation is available to him.
There was an old electricity connection sanctioned by the respondent's
predecessor-in-interest, that is, DESU, at property No.4/48. Since there
was no electricity granted for the use of property No.4/47, Vishwas
Nagar. It was revealed that the aforesaid connection granted in respect of
property No.4/48, Vishwas Nagar, was on the basis of industrial license
and the respondent was threatening to proceed against the appellant and
disconnect the electricity alleging him to be misusing the connection in
contravention to provisions of law. This resulted in filing of a suit for a
decree of permanent injunction seeking a restraint order against DESU
and subsequently against BSES and Roshan Lal that they should not
disconnect the electricity connection. The matter was contested by both
the respondents.
4. On the pleadings of the parties, following issues were framed :-
"(i) Whether plaintiff has concealed material facts from this court? OPD-2
(ii) Whether suit of plaintiff against defendant is barred u/O 2 R 2 CPC? OPD-1
(iii) Whether plaintiff is entitled to relief of permanent injunction as claimed? OPP
(iv) Whether plaintiff is entitled to relief of mandatory injunction as claimed? OPP
(v) Relief."
5. The learned trial court after recording of evidence dismissed the
suit of the plaintiff. It is not necessary for this court to go into the reasons
of dismissal of the suit.
6. The appellant filed an appeal bearing No.45/14 along with an
application seeking condonation of delay under Section 5 of the
Limitation Act. There was a delay of nearly seven months in filing the
appeal. The reasons which were given for condonation of delay were that
the judgment of the trial court was delivered on 17.1.2013. On
16.2.2013, the certified copy of the judgment was applied for and on
11.3.2013, the certified copy of the judgment was ready for delivery. On
19.3.2013, the certified copy of the judgment was collected; however, on
19.3.2013 itself, the file is alleged to have been misplaced by the clerk of
the counsel which could be traced only on 14.8.2013. On 18.8.2013, the
appeal was alleged to have been prepared. On 23.8.2013, the supporting
affidavits were got signed from the appellant and ultimately on 6.9.2013,
the appeal was filed. Thus, there was roughly a delay of seven months as
alleged by the appellant in filing the appeal which, in the averments made
by the appellant, were beyond the control of the appellant and according
to him, it constituted 'sufficient cause' for which he sought condonation
of delay.
7. The learned trial court heard the arguments and rejected the
application seeking condonation of delay by giving the reasons that the
law does not come to the rescue of the appellants, who are lethargic and
grossly negligent in filing the appeal. In this regard, the learned first
appellate court had taken note of the fact that although certified copy of
the judgment was ready on 11.3.2013 yet it was collected on 19.3.2013.
The name of the clerk, who had misplaced the file and then recovered on
14.8.2013, has not been given and the details as to how this had happened
has also not been explained. The appellate court has observed that
although the appeal was prepared on 18.8.2013 and the affidavit got
attested on 23.8.2013 yet, the appellant took almost two weeks in filing
the appeal which clearly showed that he was lethargic and negligent. The
learned first appellate court referred to the judgments of the Apex Court
in Esha Bhattacharjee vs. Managing Committee of Raghunathpur Nafar
Academy & Others; (2013) 12 JT 450 as well as the case titled
Shakuntala Devi Jain vs. Kuntal Kumar; AIR 1969 SC 575 in order to
justify its reasoning of rejecting the application.
8. I have heard the learned counsel for the appellant and have also
gone through the record. No fault can be found with the preposition of
law which has been referred to by the learned appellate judge as
enunciated in the two Supreme Court judgments that the court normally
does not come to the rescue of a negligent and lethargic litigant for the
purpose of condonation of delay in not filing the appeal timely but at the
same time the broader principle which the Supreme Court has laid down
is that the law of limitation right starting from Ramlal, Motilal and
Chhotelal vs. Rewa Coalfields Limited; 1962 AIR 361 till 2013 of Esha
Bhattarcharjee's case (supra) has considerably been liberalised by
observing that the appellant seeking condonation of delay need not
explain each day's delay and similarly he is not to be asked a question as
to why he did not file the appeal within the time prescribed.
9. In Collector, Land Acquisition, Anantnag and Anr. Vs. Mst. Katiji
and Ors.; AIR 1987 SC 1353, the Hon'ble Apex Court has held as
follows:-
"The legislature has conferred the power to condone delay by enacting Section 5 (any appeal or any application, other than an application under any of the provisions of Order XXI of the CPC, 1908, may be admitted after the prescribed period if the appellant or the applicant satisfies the court that he had sufficient cause for not preferring the appeal or making the application within such period) of the Indian Limitation Act of 1963 in order to enable the courts to do substantial justice to parties by disposing of matters on 'merits'. The expression "sufficient cause" employed by the legislature is adequately elastic to enable the courts to apply the law in a meaningful manner which subserves the ends of justice-that being the life-purpose for the existence of the institution of courts. It is common knowledge that this court has been making a justifiably liberal approach in matters instituted in this court. But the message does not appear to have percolated down to all the other courts in the hierarchy. And such a liberal approach is adopted on principle as it is realized that :-
1. Ordinarily a litigant does not stand to benefit by lodging an appeal late.
2. Refusing to condone delay can result in a meritorious matter being thrown out at the very threshold and
cause of justice being defeated. As against this, when delay is condoned the highest that can happen is that a cause would be decided on merits after hearing the parties.
3. "Every day's delay must be explained" does not mean that a pedantic approach should be made. Why not every hour's delay, every second's delay? The doctrine must be applied in a rational common sense pragmatic manner.
4. When substantial justice and technical considerations are pitted against each other, cause of substantial justice deserves to be preferred for the other side cannot claim to have vested right in injustice being done because of a non-deliberate delay.
5. There is no presumption that delay is occasioned deliberately, or on account of culpable negligence, or on account of mala fides. A litigant does not stand to benefit by resorting to delay. In fact he runs a serious risk.
6. It must be grasped that judiciary is respected not on account of its power to legalize injustice on technical grounds but because it is capable of removing injustice and is expected to do so."
10. The aforesaid findings provide the framework to be adopted while
dealing with the applications of condonation of delay. It is true that one
cannot ignore the findings rendered by the Hon'ble Apex Court in Esha
Bhattarcharjee's case (supra) but the same needs to be read in the light of
the observations made in Collector, Land Acquisition's case (supra).
Meaning thereby that both the judgments must be harmonised and merely
because Esha Bhattarcharjee's case (supra) is latter in point of time, does
not necessarily, what has been held by the Apex Court earlier, deserves to
be ignored altogether.
11. In view of the observations made in Ramlal's case (supra) was that
after the last day's delay, each day's delay was to be scrupulously
explained by a party before a condonation of delay application could be
allowed. But this principle was diluted so as to observe that the quantum
of delay is not important. What is important is the bona fide of a person,
who is seeking condonation of delay in pursuing his remedy. It has also
been observed that while considering the question of delay, the court
must also prima facie glance through the merits of the matter so as to see
as to whether the matter has any merit to be considered by the first
appellate court. Meaning thereby that merely because of the default of a
counsel, the person should not be made to suffer and it should not result
in gross injustice to the appellant. It is trite true observation that a
meritious case must not be expelled only on the grounds of inordinate
delay which can be reasonably explained.
12. Every litigant cannot be expected to be legally education and
having engaged the counsel of repute is justified in their contention that
the mistake committed by the counsel or his clerk cannot prejudice the
party.
13. In the background of the aforesaid broader principles of law, I find
that the learned first appellate court has fallen into an error in following
the dictum of Ramlal's case (supra) inasmuch as it has specifically
observed in the impugned order that each and every day delay has not
been explained by the appellant. Similarly, at another place, it has been
observed that the appellant was bound to explain as to why he did not
apply for certified copy well within time. I feel, these two observations
are not in tandem with the preposition of law laid down by the Supreme
Court. In the light of the findings rendered in Collector, Land
Acquisition's case (supra), it is not practically possible to expect a litigant
to explain the delay of every day and every hour. The expression "every
days' delay must be explained" has to be dealt with a positive approach.
If the applicant has given a possible and a plausible explanation then in
such circumstances, a bona fide litigant must not be given a litigant non-
grata status merely due to the deficit of a minute to minute account of the
events leading to the delay.
14. The person concerned is not supposed to explain as to why he did
not apply for certified copy of the judgment within the period of
limitation. The only thing to be seen is that in case, he applies for a
certified copy within the period of limitation then the period which is
taken by the office in preparation of the certified copy will be deducted
from the total number of days within which the appeal is filed. In case, a
party applies for a certified copy after the period of limitation, it does not
get him any extension of time for the purpose of filing an appeal.
Meaning thereby, there is no deduction of time spent by a party in
obtaining certified copy. In the instant case, the copy was belatedly
applied within the prescribed period of limitation and it was ready on
11.3.2013 but the copy has been collected on 19.3.2013. In such an
event, there is no inordinate delay in collecting the copy so as to attribute
any mala fide to the appellant. The appellant is not required to show as to
why he did not collect the copy on 11.3.2013 itself as no litigant is
expected to visit the counter for collection of copy on each and every date
after having applied for the same. Therefore, the benefit of six days delay
in collection of the copy is not such a huge delay which should come in
the way of the court in taking a view against him. In O.P. Kathpalia vs.
Lakhmir Singh; AIR 1984 SC 1744, a full Bench of the Hon'ble Supreme
Court held that if the refusal to condone the delay results in gross
miscarriage of justice, it would be a ground to condone the delay. In the
instant case, the first appellate court ought to have considered the fact that
the first appeal is always a matter of right so as to give an opportunity to
the first appellate court to oversee the correctness and finding of the trial
court.
15. Therefore, in my considered opinion, on account of the aforesaid
reasons, the first appellate court ought to have taken a liberal view and
condoned the delay of seven months in filing the appeal on account of the
reasons which were given that the file was misplaced. The learned court
ought to have seen the merits of the matter or at least de hors the view it
has taken with regard to non-condonation of delay, applied its mind to see
as to whether on merits, the learned trial court has not gone wrong and
pronounced some observations. In the absence of all this, I feel it will
cause greater injustice to the appellant in case his application is rejected
on the sole ground of limitation and thereby foreclosing of his right to
have review of the evidence and its appreciation by the first appellate
court.
16. For the aforesaid reasons, I am inclined to accept the plea of the
appellant that the averments made in the application are constituting
'sufficient cause' and the appellant was not expected to show each day's
delay in filing the appeal. Therefore, the appeal is allowed and the first
appellate court's order dated 19.4.2014 is set aside. The delay is
condoned and the matter is remanded back to the trial court for the
purpose of consideration of the same on merits. Let the parties appear
before the learned District Judge on 23rd April, 2015.
V.K. SHALI, J.
MARCH 12, 2015 'AA'
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!