Citation : 2015 Latest Caselaw 4506 Del
Judgement Date : 29 June, 2015
*IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of decision: 29th June, 2015
+ W.P.(C) No.5982 /2015
INDUS COLLEGE OF ENGINEERING .... Petitioner
Through: Mr. S. Nanda Kumar with Mr.
Parivesh Singh, Mr. Ravi Kant, Mr.
Mayank Manish & Ms. Jyoti Sharma,
Advs.
Versus
All INDIA COUNCIL FOR
TECHNICAL EDUCATION ..... Respondent
Through: Mr. Anil Soni, Adv.
CORAM:-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
RAJIV SAHAI ENDLAW, J
1. The petition impugns the letter dated 30th April, 2015 of the
respondent, withdrawing the approval earlier accorded to the petitioner vide
letter dated 25th July, 2008 for establishing an institution for imparting
education in engineering and technology. The writ petition came up first
before the Vacation Bench on 12th June, 2015 when the counsel for the
respondent also entered appearance and the matter was posted for today for
hearing.
2. The counsel for the petitioner has been heard at length.
3. The petitioner, in the writ petition has pleaded:
(a) that the respondent, after being satisfied of the petitioner having
fulfilled the requisite conditions, vide letter dated 25th July,
2008 granted approval to the petitioner for running the
undergraduate engineering course with annual intake of 240
seats for the academic year 2008-09;
(b) that the petitioner was also accorded extension of approval by
the respondent from time to time for relevant academic year;
(c) that on 4th June, 2014 the respondent granted extension of
approval to the petitioner for running courses in engineering
and technology with intake of 498 students for the session
2014-15;
(d) that the respondent issued a show cause notice dated 15th
September, 2014 to the petitioner and to which a reply was
submitted by the petitioner and whereafter the petitioner was
directed to appear before the Standing Complaint Committee
Meeting scheduled on 11th November, 2014;
(e) that the petitioner, in the hearing on 11th November, 2014
"submitted relevant documents in order to cure the defects as
pointed out by the AICTE";
(f) that the respondent vide its letter dated 20 th November, 2014
directed the petitioner to obtain and submit approval from
"DPCT" (sic for DTCP i.e. Director, Town and Country
Planning) and NOC from Forest Department within three
months therefrom;
(g) that the petitioner applied for approval to DTCP;
(h) that the respondent vide letter dated 24th March, 2015 asked the
petitioner to appear before the Standing Complaint Committee
Meeting scheduled on 30th March, 2015;
(i) that the petitioner participated in the hearing on 30 th March,
2015 and "produced all the relevant documents in order to cure
the defect" and also informed that it had applied for approval
from DTCP and NOC from Forest Department;
(j) that "however, the said Committee without appreciating the
case of the petitioner and his submissions made the arbitrary
recommendation to withdraw the approval";
(k) that the representation dated 27th February, 2010 (sic for 27th
April, 2015) was submitted to the respondent;
(l) that the respondent vide its letter dated 24 th April, 2015 directed
the petitioner to appear before its Standing Appeal Committee
and to present its case;
(m) that the petitioner appeared before the Standing Appeal
Committee and again represented its case stating that the initial
Land Use Certificate submitted by the petitioner was not forged
certificate but merely a certificate issued by another authority
i.e. the Panchayat;
(n) that however the respondent arbitrarily issued the aforesaid
letter dated 30th April, 2015 of withdrawal of approval.
4. However a perusal of the documents annexed to the petition shows the
respondent to have withdrawn the approval earlier accorded to the petitioner
for the reason:
(i) that the petitioner at the time of seeking approval for the
establishment of an institution for imparting education in
engineering and technology had submitted the Land Use
Certificate dated 24th December, 2007 issued by the Rural
Development Officer (RDO), Coimbatore and the Land
Conversion Certificate from the Alandurai Panchayat;
(ii) that on verification of the authenticity of the Land Use
Certificate with RDO / Collector of Coimbatore, it was
informed by the District Revenue Office, Coimbatore vide letter
dated 8th March, 2010 that the Land Use Certificate was not
issued by the RDO, Coimbatore and hence the certificate was
not an authentic one;
(iii) that the petitioner in September, 2010 submitted another Land
Use Certificate dated 27th February, 2010 issued by RDO,
Coimbatore;
(iv) that the petitioner had submitted its building plans to DTCP for
approval; DTCP had asked the petitioner to submit certain
documents including the NOC from the Hill Area Conservation
Authority (HACA);
(v) that the DTCP issued notice dated 18th January, 2013 to the
petitioner stating that the buildings constructed by the petitioner
were unauthorized and directed the petitioner to restore the land
to its condition before the said construction took place and
otherwise threatening sealing of the premises;
(vi) that the petitioner approached the Court against the said notice
of the DTCP but the case was dismissed and the order of DTCP
was upheld;
(vii) that since the petitioner failed to submit the documents to the
DTCP for approval of the building, the DTCP served notice
dated 25th July, 2014 to the petitioner of sealing of the premises
with effect from 1st August, 2014;
(viii) that DTCP sealed the Principal‟s office and Administrative
Block of the building of the petitioner on 1st August, 2014;
(ix) that in view of the aforesaid events, the AICTE had issued the
show cause notice dated 15th September, 2014 to the petitioner
asking it to explain as to why the approval should not be
withdrawn;
(x) that the petitioner in its reply dated 30th September, 2014 to the
aforesaid notice stated that the copy of the Land Use Certificate
dated 24th December, 2007 was not available in its records and
that the Land Use Certificate dated 27th February, 2010
subsequently submitted by it was genuine and true and that it
had taken steps in accordance with law and the matter was sub
judice;
(xi) that the petitioner in the hearing before the Standing Complaint
Committee had sought three months time to obtain and submit
NOC from DTCP and Forest Department and which was
granted;
(xii) that however the petitioner was unable to submit the said
documents within the said period of three months;
(xiii) that the Standing Complaint Committee accordingly concluded
that the petitioner‟s institute was started with a criminal activity
and on the basis of a forged Land Use Certificate and that the
buildings constructed by the petitioner institute were
unauthorized and had been ordered to be demolished and
accordingly recommended withdrawal of the approval earlier
accorded to the petitioner;
(xiv) that the petitioner was granted an opportunity to present its case
before the Standing Appellate Committee on 24th April, 2015;
(xv) that however the Standing Appellate Committee also concluded
that the petitioner had obtained approval in the year 2008 on the
basis of forged Land Use Certificate;
(xvi) that as per Clause 4.27 of the All India Council for Technical
Education (Grant of Approvals for Technical Institutions)
Regulations, 2012, if the institution has misrepresented, the
approval has to be withdrawn;
(xvii) that accordingly the Standing Appellate Committee
recommended withdrawal of approval and approval was
accordingly withdrawn vide letter dated 30th April, 2015.
5. I have enquired from the counsel for the petitioner as to how the
findings contained in the impugned letter dated 30th April, 2015, of the
petitioner having obtained the approval in the year 2008 by submitting a
forged Land Use Certificate is erroneous and that if it is not erroneous, how
can the order of the respondent AICTE of withdrawal of approval on the said
ground can be found fault with.
6. No proper reply has been forthcoming. The counsel however without
stating any basis states that the petitioner has not indulged in any forgery.
7. I have further enquired from the counsel for the petitioner as to which
Court the petitioner had approached against notice dated 18th January, 2013
(supra) of the DTCP asking the petitioner to restore the land to the condition
before the construction and threatening sealing of the premises.
8. The counsel for the petitioner states that the petitioner had then
approached the High Court of Madras at Chennai.
9. As per the impugned letter dated 30th April, 2015, the aforesaid case
of the petitioner was dismissed and the order of the DTCP was upheld. I
have enquired from the counsel whether the said order of the High Court of
Madras has attained finality.
10. The counsel replies in the affirmative.
11. The petitioner has however not chosen to place a copy of the said
order of dismissal of its writ petition before this Court. On enquiry, the
counsel for the petitioner states that he is not in possession of any copy of
the said order.
12. In my opinion, with the dismissal of the writ petition preferred by the
petitioner impugning the notice dated 18th January, 2013 of the DTCP
holding the buildings raised by the petitioner to be unauthorized and
directing the petitioner to demolish the said buildings and to restore the land
to its original condition, the question whether the said buildings are
unauthorized or not is no longer res integra. It can safely be presumed that
the buildings must have been held to be unauthorized for the reason of
having been constructed on land not meant for the said purpose and the use
whereof had not been permitted to be changed. It can further safely be
presumed that the petitioner, before the High Court of Madras also would
have relied or ought to have relied on the change of Land Use Certificates on
the basis whereof the petitioner in the year 2008 obtained approval from the
respondent. The High Court of Madras has obviously not believed the said
change of Land Use Certificate. Alternatively, if the petitioner has hesitated
from relying upon change of Land Use Certificates before the High Court of
Madras, the only reason therefor could be of the same being not genuine.
13. The counsel for the petitioner however contends that the buildings still
exists and that the classes are being held therein for the students admitted in
the previous years.
14. However merely because the order of demolition though passed has
not been implemented till date would not make any difference. The same
does not dilute the factum of the petitioner having indulged in forgery while
obtaining approval in the year 2008 from the respondent. Under the
Regulations of the respondent AICTE, the said conduct of the petitioner
entitles the respondent to withdraw the approval.
15. Faced therewith the counsel for the petitioner contends that no proper
hearing was given by the Standing Appellate Committee to the petitioner.
He places reliance on:
(i) Order dated 29th May, 2015 in W.P.(C) No.284/2015 titled as
Nest Educational and Welfare Society Vs. All India Council
for Technical Education;
(ii) Order dated 18th May, 2015 in W.P.(C) No.4884/2015 titled as
ACN College of Pharmacy Vs. All India Council for
Technical Education;
(iii) Order dated 18th May, 2015 in W.P.(C) No.4707/2015 titled as
Institute of International Excellence Vs. All India Council for
Technical Education;
(iv) Order dated 19th May, 2015 in W.P.(C) No.4956/2015 titled as
Daya Charitable Trust Vs. All India Council for Technical
Education.
to contend that in all the said cases also the matter was remanded to the
Standing Appellate Committee for reconsideration.
16. I am afraid that is not the case pleaded by the petitioner nor is any
such ground made out. The reliance placed on the judgments / orders
aforesaid is thus entirely misconceived. Rather, I am constrained to observe
that the pleadings in the petition are not lucid and clear and do not reflect the
case as found to have been contained in the documents. All that can be
observed qua the said contention of the counsel for the petitioner is that
though the respondent AICTE in the letter dated 30th April, 2015, besides
citing the ground of such forgery for withdrawal of approval has also stated
that "there were other deficiencies in relation to approval of building plan
etc." but without specifying the said deficiencies; however the ground, of the
petitioner having indulged in forgery, itself is enough to uphold the order.
The said ground of forgery, the petitioner has not been able to controvert.
Though the petitioner in the hearing held before the Standing Complaints
Committee on 12th November, 2014 sought three months time to obtain the
requisite documents from DTCP but could not get the said documents. The
question of getting any such documents after the dismissal of the writ
petition aforesaid by the High Court of Madras even otherwise does not
arise.
17. The counsel for the petitioner at this stage states that the petitioner has
applied afresh for change of land use and which is pending.
18. The aforesaid pendency however cannot come to the rescue of the
petitioner and cannot entitle the petitioner to renewal / extension of the
approval, grant whereof is steeped in forgery.
19. I therefore do not find any ground to entertain this petition which is
dismissed.
No costs.
RAJIV SAHAI ENDLAW, J
JUNE 29, 2015 „gsr‟
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!