Citation : 2015 Latest Caselaw 4470 Del
Judgement Date : 29 June, 2015
* HIGH COURT OF DELHI AT NEW DELHI
+ W.P.(C) 5124/2014 & W.P.(C) 5127/2014
Decided on : 29th June, 2015
W.P.(C) 5124/2014
MADHU TRANSPORT COMPANY PVT LTD & ANR.
..... Petitioners
Through: Mr. Prateek Jalan,
Mr. Surendra Dube,
Mr. Ankit Yadav,
Ms. Sonia Dube,
Mr. Shatadru Chakraborty,
Ms. Kanchan Yadav &
Mr. Anurag Singh, Advocates.
versus
UNION OF INDIA & ORS. ..... Respondents
Through: Mr. Jagjit Singh,
Ms. Manita Verma,
Ms. Nisha &
Mr. Shivanshu Bajpai, Advs.
W.P.(C) 5127/2014
JAI BALAJI INDUSTRIES LIMITED & ANR. ..... Petitioners
Through: Mr. Prateek Jalan,
Mr. Surendra Dube,
Mr. Ankit Yadav,
Ms. Sonia Dube,
Mr. Shatadru Chakraborty,
WP(C) Nos.5124/2014 & 5127/2014 Page 1 of 34
Ms. Kanchan Yadav &
Mr. Anurag Singh, Advocates.
versus
UNION OF INDIA & ORS. ..... Respondents
Through: Mr. Jagjit Singh,
Ms. Manita Verma,
Ms. Nisha &
Mr. Shivanshu Bajpai, Advs.
CORAM:
HON'BLE MR. JUSTICE V.K. SHALI
V.K. SHALI, J.
1. In both these writ petitions, the challenge has been laid to orders
dated 13.06.2014 & 18.06.2014 respectively passed by Respondent
No.3, Member Traffic, Railway Board rejecting the request of the
petitioners terminating the contract entered into by them with the
respondents on the ground that there is no addition or alteration in the
agreement arrived at between the parties and consequently, there was no
occasion for giving rise to cause of action in favour of the petitioners to
terminate the agreements on various dates entered between the parties
under Wagon Investment Scheme ('WIS Scheme' for short) and also
seeking a direction to the respondents to purchase the wagons at the
agreed terms and conditions.
2. Though the orders in the two writ petitions which are assailed are
of different dates, but essentially they are on the same lines and the
agreements entered between the parties are also containing the same
terms and conditions and, therefore, for facility of reference, the facts of
WP(C) No.5124/2014 only are being referred to and the reasoning and
the conclusion which is arrived at on the basis of the said facts will be
equally applicable mutatis mutandis to the facts of WP(C)
No.5127/2014.
3. Coming back to the facts of WP(C) No.5124/2014 titled Madhu
Transport Company Pvt. Ltd & Anr. Vs. Union of India & Ors., it may
be pertinent here to mention that this is a third round of litigation
initiated by Madhu Transport Company Pvt. Ltd against UOI on the
basis of the agreement dated 18.07.2006 under the WIS Scheme.
4. In the first round of litigation, the petitioners filed WP(C)
No.123/2014 which was disposed of with the consent of the parties
directing respondent No.2 to consider the representation dated
11.09.2013 submitted by the petitioners for the purpose of arriving at a
settlement, if possible, so far as the termination of the agreement dated
18.07.2006 and the consequent purchase of wagons by the respondents
is concerned.
5. In the second round of litigation initiated by the petitioners
{WP(C) No.2446/2014} it was again prayed that the respondents be
directed to purchase the wagons at a price offered by them being the
depreciated value thereof under the Indian Railway Financial Code or on
any other mutually agreed price or rates offered to similarly placed WIS
Investors. The said writ petition was disposed of on 22.04.2014 with
directions to respondent Nos.1 & 2 to take a decision on the
representation of the petitioners by a reasoned order and communicate
the same to the petitioner within 10 days. The petitioners were also
permitted to make oral submissions before the concerned officer in this
regard.
6. As a consequence of this order passed by the Court on 22.04.2014
that the Member Traffic, Railway Board has passed the impugned order
dated 13.06.2014 rejecting the request of the petitioners for termination
of the agreement dated 18.07.2006 between the parties and further
observing that the Railways is not bound to purchase wagons of the
petitioners. It is this order dated 13.06.2014 passed by the respondents
that has been challenged in the present writ petition.
7. The Central Government had published Wagon Investment
Scheme (WIS) in the year 2005 with the objective to encourage public
private partnership in procurement of wagons to meet with the
anticipated incremental freight traffic in the coming years. The
petitioners in order to avail of the benefit of the said Scheme known as
WIS applied for four rakes and accordingly four agreements dated
18.07.2006 were executed between petitioners and Railways/R-2 & R-3
although there are seven respondents. The important terms and
conditions of the agreement which provided certain preferential rights to
the petitioners are contained in clauses 7.3, 7.10, 10.1 & 12 & 13 of the
said agreement.
8. It may be pertinent to reproduce the contents of the said clauses
for facility of reference.
7.3 CATEGORY II - BOX'N WAGONS1
Freight rebate of 10% shall be granted for 10 years and guaranteed supply of wagons at the
Contained in Clause 2.5, 2.6, 5.2 nd 5.4 of the agreement dated 18.07.2006.
rate of 6 rakes per month. In addition, a guaranteed supply of two bonus rakes will be made without freight concession. (For customers opting for EOL Scheme 2 further additional bonus rakes will be supplied without freight concession).
7.10 OWNERSHIP OF WAGONS2 Ownership of wagons procured under Wagon Investment Scheme (WIS) shall get transferred to Indian Railways after 10 years for BOXN rakes, 15 years for BCN rakes, 9 years for BTPN rakes, 15 years for BRNA rakes, 7 years for BOST and 7 years for BOBRN rakes.
10 FAILURE TO MAINTAN/CONSUME GUARANTEED SUPPLY OF WAGONS3
10.1 The guaranteed supply of wagons will be monitored on a monthly basis.
12. TERMINATION OF AGREEMENT In the event of termination of the arrangement by the Investor on account of liquidation/merger with other company or due to any alteration/deletion in the scheme, the ownership of wagons would remain with the Investor. However, the Investor shall have the option to sell the wagons to Indian Railways at a mutually agreed price.
Contained in clause 5.6 of the agreement.
Contained in clause 7.1 of agreement.
13. CHANGES IN THE SCHEME
Terms of the scheme (WIS) may be altered by mutual consent of both parties."
9. Thus, a perusal of the aforesaid clauses of the agreement would
show that following salient rights were provided in favour of the
petitioners.
a. The investor guaranteed 6 rakes per month with freight rebate and 2 additional rakes were also guaranteed EOL without freight rebate.
b. Ownership of the wagons would remain with the investor for 10 years and would thereafter be transferred to the Railways.
c. The guaranteed supply of wagons will be monitored on monthly basis.
d. In the event of termination of the agreement by the investor on account of merger/liquidation or due to any alteration/deletion in the scheme, the ownership of the wagons would remain with the investor who shall have the option to sell the wagons to the Indian Railways at a mutually agreed price.
e. That terms of the WIS may be altered with mutual consent only.
10. All the four agreements were identical in nature and were
providing for supply of six rakes to the petitioners. The system worked
well for some time, however, the petitioners allege that the respondents
started issuing circulars unilaterally and arbitrarily which in fact had
changed the terms and conditions of the agreement entered into between
the petitioners and the respondents. These terms and conditions were
following in nature.
a) The original WIS in terms of para 7.3 of the WIS provided for
eligibility of 8 rakes per month and monitoring on monthly basis while
as the respondents issued a circular dated 26.09.2008 by virtue of which
it modified monthly quota of guaranteed rakes to a fortnightly quota.
Thus, the period for which the respondents were to supervise the
availability of rakes made to the petitioners on monthly basis was
reduced to fortnightly basis. It was specifically made clear in the circular
that in case fortnightly indent was not placed in time, it would result in
forfeiture of the said quota and in no case it would be permitted to carry
forward to ensuing fortnight.
b). It is alleged that a further circular was issued on 03.02.2011 by
virtue of which instead of guaranteed four rakes per month, the
respondents arbitrarily and unilaterally reduced the quota or rather
converted the quota of monthly rakes to one rake after every five days
thereby the monitoring which was done on monthly basis firstly got
reduced to fortnightly basis and then to almost five days or so to say
weekly basis.
c). Vide a circular dated 27.07.2012, the respondents are alleged to
have unilaterally withdrawn the Terminal Incentive Cum Engine on
Load Scheme (TIELS) and consequently, the petitioners' monthly
entitlement was unilaterally reduced by two rakes.
d). It was alleged that earlier practice of permitting changes of
loading station to the petitioners by the respondents was stopped by
issuance of a circular dated 01.08.2013 which imposed various
restrictions in the event of loading and unloading station being changed.
11. It has been alleged by the petitioners that the respondents on
account of this unilateral and arbitrary action on their part changed the
terms and conditions of the WIS Scheme and consequently the
agreement which necessitated issuance of letter dated 11.09.2013 by the
petitioners terminating the agreement. It has also been alleged that
despite the agreement having been terminated, the Railway Authorities
neither handed over the wagons to the petitioners nor did they offer to
purchase the same in terms of WIS.
12. It has been stated that in terms of WIS Scheme, the investment in
the wagons has been made by the petitioners and the agreement
envisages that for all practical purposes, the petitioners will continue to
own the wagons and by retaining the wagons illegally, the respondents
have indulged in unlawful and illegal action. It has been alleged that
since there was no response to the communication sent by the petitioner
to the respondents, they were constrained to file WP(C) No.123/2014
which was disposed of by this court vide order dated 16.01.2014 with
the consent of the parties, directing the respondent No.2 to consider the
representation dated 11.09.2013 submitted by the petitioners for the
purpose of arriving at a settlement, if possible. The court further
directed the petitioners to appear before Director (Freight), Railway
Board for making oral submissions in support of the representation on
20.01.2014 at 4 P.M.
13. It has been alleged since the respondents did not take the decision
despite the aforesaid order of the court and the oral submissions having
been made by them on 20.01.2014, they were constrained to file another
WP(C) No.2446/2014 which was disposed of on 22.04.2014 directing
the respondent Nos.1 & 2 to pass a reasoned order and communicate to
the petitioners within a period of 10 days with liberty to the petitioners
to seek such remedy in accordance with law as may be permissible.
14. It has been alleged that it is in consequence of the disposal of
WP(C) No.2446/2014 vide order dated 22.04.2014 that the respondents
have passed the impugned order rejecting the request of the petitioners
to treat the agreement between the parties as having been terminated and
also refused to purchase the wagons at an agreed price. Hence, the
petitioners were constrained to file the present writ petition.
15. The respondents have filed their counter affidavit in response to
the show cause notice and have taken the plea that the writ petition is
not maintainable. It has been alleged by them that clause 15 of the
agreement between the parties contained an arbitration clause and,
therefore, the petitioners ought to have invoked the arbitration clause
rather than filing the present writ petition.
16. Secondly, it has been alleged by the respondents that the
termination letter purported to have been issued by the petitioners to the
respondents is totally illegal and uncalled for. It has been stated that a
close perusal of the Circulars dated 26.09.2006, 29.10.2007, 26.09.2008,
03.02.2011, 27.07.2012 and 01.08.2013 make it abundantly clear that
there had been no change in WIS Scheme and these circulars are
purported to have been issued by respondents in terms of clause 6.1 (c)
and clause 14 of the agreement between the parties and they are alleged
to be clarficatory in nature.
17. It has been alleged by the respondents there is no
liquidation/merger with other company or any alteration/deletion in WIS
which as per clause 12 of the agreement would give rise to an occasion
in favour of the petitioners to terminate the agreement.
18. It has also been contended by the respondents that in a similar
case titled Aviral Minerals Pvt.Ltd v.UOI which is sub judice before the
Apex Court, a committee was constituted to look into the whole issue. It
has been stated that the said committee concluded that para 12 of the
agreement is not attracted in the said case of similarly placed person as
the petitioners. It has been stated that the said case is still pending in the
Supreme Court and, therefore, this case may either be clubbed with the
said case or decision in the said case be awaited.
19. It has also been contended that the allegation made by the
petitioners that they entered into a loan-cum-hypothecation agreement
with M/s SREI Equipment Finance Private Limited with respect to the
wagons purported to be owned by them was without the consent of the
respondents and, therefore, the same cannot be binding on the
respondents. It has been contended that the writ petition of the
petitioners is totally misconceived and accordingly the same deserves to
be dismissed.
20. I have heard the learned counsel for the parties. I have also
thoughtfully considered the submissions made by the respective sides
and have also gone through the record.
21. The question which arises in the instant case is as to whether in
the first instance the writ petition is entertainable or not. In this regard,
it may be pertinent here to mention that the respondents have taken a
preliminary objection regarding maintainability of the writ petition on
the ground that there is an arbitration clause contained in the WIS
Scheme and, therefore, the writ petition would not be maintainable.
22. This contention of the respondents that the High Court would not
be competent to entertain the writ petition on account of arbitration
clause has been contested by the petitioners. It has been contended by
them that merely because there is an arbitration clause, it would not be a
ground for not entertaining the writ petition.
23. The learned counsel for the petitioners has placed reliance on
Union of India v. Tantia Construction Pvt.Ltd: (2011) 5 SCC 697, ABL
International v. Export Credit Guarantee Corporation of India Ltd.;
(2004) 3 SCC 553, Chandana Kedia Sole Proprietor, M/s. Adinath
Industries v. Union of India; 2010 II AD (Delhi) 757 and Kishan Freight
Forwarders v.Union of India; 181 (2011) DLT 547 to contend that
despite there being an arbitration clause and hence an alternative remedy
being available in case the action of the state authority is arbitrary,
illegal and violative of right of a party, it can be challenged under
Article 226 of the writ jurisdiction..
24. The clause 15 of the WIS Scheme reads as under:
15.0 Arbitration
15.1 In the event of question, dispute or difference between the parties hereto relating to any matter arising out of or quoted 'with this' agreement, such dispute or difference shall be referred for the award of three arbitrators. One arbitrator is to be nominated by the Investor, the other by the Railways and the third arbitrator to be
nominated by mutual agreement between the parties and, in the event of non agreement, the third arbitrator shall be appointed in accordance with the provisions of the Arbitration and Conciliation Act, 1996."
25. There is no dispute about the fact that there is an arbitration
clause between the parties as contained in WIS agreement dated
18.07.2006 and, therefore, there is an alternative remedy available to the
petitioners. It is also not in dispute that before filing of the present writ
petition, there were two rounds of litigations between the parties which
were summarily disposed of by this court directing the respondents to
take a informed decision and pass a reasoned order. It has not been
shown to the court by the respondents as to whether in these two earlier
writ petitions they had taken any such plea regarding existence an
arbitration clause in the agreement between the parties and therefore
seeking reference of disputes between the parties to arbitration. Even if
it is assumed that such a plea was taken by the respondents in the
counter affidavit, still, at least in the orders, it is clearly shown that this
plea of the respondents that there being an arbitration clause between the
parties and in view thereof writ petition was not entertainable, was not
accepted by the court and, therefore, prima facie, I feel that to relegate
the parties now to arbitration despite this court having entertained two
sets of writ petitions earlier between the parties with regard to the
grievance raised by the petitioners, would only be an exercise of tossing
around the ball and it would only delay the adjudication of the dispute
between the parties. Therefore, I do not accept this contention of the
learned counsel for the respondents.
26. In addition to this, merely because there is an arbitration clause
between the parties is no ground per se not to entertain the writ
jurisdiction. Each and every case where such a clause exists between the
parties they should be relegated to arbitration must be able to show and
convince the courts that this is the best course available under the
circumstances.
27. There have been cases where one of the parties has taken a plea
with regard to availability of arbitration clause, yet the court in the
interest of justice has entertained the writ petition and passed
appropriate orders. Reliance in this regard can be placed on the
judgments in Tantia Construction Pvt.Ltd's case (supra), ABL
International's case (supra), Chandana Kedia's case (supra) and iv)
Kishan Freight Forwarders's case (supra).
28. In Union of India and Ors. v. Tantia Construction Private
Limited; (2011) 5 SCC 697, the question which had arisen for
adjudication before the apex court was with regard to the contractual
obligation and specific relief on account of termination and discharge of
contract between UOI and Tantia Construction Private Limited. This
case also involved an agreement between the Railways and private
parties. One of the arguments which was taken up before the Apex
Court was that the agreement between the parties provided for
adjudication through arbitration in respect of all the disputes and
differences of any kind arising between the parties out of or in
connection with the contract whether during the progress of work or
after its completion and whether before or after the termination of the
contract, the same could be adjudicated by the arbitrator. Nullifying this
submission, the Apex Court observed in para 33 and 34 as under:
33. Apart from the above, even on the question of maintainability of the writ petition on account of the Arbitration Clause included in the agreement between the parties, it is now well- established that an alternative remedy is not an absolute bar to the invocation of the writ jurisdiction of the High Court or the Supreme Court and that without exhausting such
alternative remedy, a writ petition would not be maintainable. The various decisions cited by Mr. Chakraborty would clearly indicate that the constitutional powers vested in the High Court or the Supreme Court cannot be fettered by any alternative remedy available to the authorities. Injustice, whenever and wherever it takes place, has to be struck down as an anathema to the rule of law and the provisions of the Constitution.
34 We endorse the view of the High Court that notwithstanding the provisions relating to the Arbitration Clause contained in the agreement, the High Court was fully within its competence to entertain and dispose of the Writ Petition filed on behalf of the Respondent Company. We, therefore, see no reason to interfere with the views expressed by the High Court on the maintainability of the Writ Petition and also on its merits.
29. In ABL International Ltd.'s case (supra), one of the questions
which had arisen before the Apex Court was whether the contractual
obligations between a private party and State or its instrumentality can
be subject matter of a writ petition or not.
30. The Hon'ble Apex Court observed that the aforesaid question is
no more res integra and despite there being an alternative remedy by
way of an arbitration clause available to a party, still the court can in
exercise its powers under Article 226 of the Constitution of India,
examine the matter and give the aggrieved party requisite relief. It was
held in para 27 of the said judgment as under:
"27. From the above discussion of ours, following legal principles emerge as to the maintainability of a writ petition :-
(a) In an appropriate case, a writ petition as against a State or an instrumentality of a State arising out of a contractual obligation is maintainable.
(b) Merely because some disputed questions of facts arise for consideration, same cannot be a ground to refuse to entertain a writ petition in all cases as a matter of rule.
(c) A writ petition involving a consequential relief of monetary claim is also maintainable."
31. Reliance in this regard was placed on the observations of the
Apex Court in Gujarat State Financial Corporation v. Lotus Hotels (P)
Limited; (1983) 3 SCC 379 which in turn had placed reliance on an
earlier oft-quoted judgment in Ramana Dayaram Shetty v. International
Airport Authority of India; (1979) 3 SCC 489.
32. Similarly, a learned single Judge of this court in Kishan Freight
forwarders's case (supra) in a matter pertaining to Railways and its
contract where a somewhat similar question with regard to termination
and extension of lease contract was involved, it was held that the writ
petition was entertainable and maintainable notwithstanding the fact that
there was an arbitration clauses and while arriving at such a conclusion,
it had copiously referred to the judgment of the Apex Court in ABL
International Ltd.'s case (supra) and Sanjana M.Wig v. Hindustan
Petroleum Corporation Limited; 2005 (8) SCC 242 to conclude that
where there is a question of public duty being performed by the
respondents, a writ petition will be entertained.
33. Similarly, the learned single Judge in another judgment Chandana
Kedia Sole Proprietor, M/s. Adinath Industries v. Union of India; 2010
II AD (Delhi) 757 has also expressed the same view that merely because
there is an arbitration clause between the parties would not be a ground
for the court to conclude that existence of an alternative remedy by way
of an arbitration shall prevent the court from entertaining the writ
petition and it observed that in appropriate cases, the court may exercise
its discretionary jurisdiction in case there is a violation of any
fundamental right or the party in question has been dealt with unfairly
and it is a party which is placed at an disadvantageous position.
34. From the aforesaid discussion, it is clear that merely because there
is an arbitration clause between the parties would not be a ground to
oust the jurisdiction of this court and dismiss the writ petition on the
ground of alternative remedy being available.
35. So far as the present case is concerned, the earlier two rounds of
writ petitions have been entertained by the court without any credence to
the objection of arbitration clause would show that the existence of
arbitration clause between the parties is not a ground not to entertain the
petition. Therefore, it will not be just and proper to reject the present
petition on the ground of existence of arbitration clause between the
parties.
36. Moreover, in addition to this, the contention of the learned
counsel for the respondents that the cases involves disputes question of
fact as to the interpretation of the various clauses which are relied upon
by the petitioners is as a matter of fact mirage. It is only what the
respondents are contending that there is a disputed question of fact. As
a matter of fact, this question of interpretation as to whether the
conditions existed which warranted invocation of termination of contract
by the petitioners on account of the alleged unilateral and arbitrary
change of terms and conditions of the agreement or whether the
circulars which are purported to have been issued by the respondents are
more in the nature of interpretation of various clauses of the agreement
rather than raising a disputed question of fact. Further in ABL
International Ltd.'s case (supra), the apex Court has observed that
merely because the respondent or for that matter one of the party raises a
plea of the matter involving a disputed question of fact does not mean
that it involves one and therefore the court will not have the jurisdiction.
It is for the court to be convinced that the matter actually and really
involves disputed question of fact and therefore the court should not
invoke the writ jurisdiction. In my considered view, the submissions
raised by the petitioners do not raise any disputed question of fact. It
only raises a question as to whether the issuance of circular by the
respondents tantamounts to changing the nature of the WIS Scheme.
Therefore, the same can be gone into by this court under Article 226 of
the Constitution of India.
37. The second submission made by the learned counsel for the
respondents is to keep the present proceedings of the writ petitions in
abeyance or alternatively direct the petitioners to move the hon'ble
Supreme Court for clubbing of the present writ petition before the
Hon'ble Supreme Court to be heard along with SLP Nos.39097-
39099/2012.
38. It may be pertinent here to mention that the parties had
approached the Hon'ble Apex Court for the purpose of withdrawing the
writ petition to be heard along with the matter pending before the apex
court. The said request was disallowed and it was observed by the
Hon'ble Apex Court that the High Court may decide the writ petition at
an early date. Therefore, in the light of the direction passed by the
Hon'ble Supreme Court, this contention of the learned counsel for the
respondents to keep the proceedings of the present writ petition in
abeyance till the decision of the apex court does not have any merit.
39. The next question and which is the core of the matter is as to
whether the issuance of circulars from time to time by the respondents
whereby the period of monitoring the wagons has been changed from
month to fortnight and then to days and whether the forfeiture of the
right of the petitioners to get a preferential treatment for a specified
period on account of non booking is clarificatory in nature or is a
unilateral action on the part of the respondents to change the terms of
the agreement? Whether the restriction imposed on the petitioners from
doing loading and unloading at stations other than specified is similarly
tantamounting to clarifying the general terms and conditions of booking
or is it in violation of the agreement?
40. There is no dispute about the fact that the respondents have issued
circulars from time to time. One of the circulars which has been issued
by the respondents is with respect to modifying monthly quota of
guaranteed rakes to a fortnightly quota. It has been further observed in
the said circular that in case the rakes in question which are falling in a
particular slot of fortnight are not availed of by the petitioners in that
particular slot, then it will result in forfeiture of that facility for the
ensuing fortnight meaning thereby that if out of four or six rakes to be
availed of by the petitioners on preferential basis two each for the first
fortnight and second fortnight are not availed of, the first two rakes
cannot be carried forward to the second fortnight meaning thereby that
in the second fortnight, they will be permitted to avail of only
preferential quota of only two rakes and not four rakes as envisaged in
the agreement.
41. This arrangement has been further reduced from fortnight basis to
one rake each in five days meaning thereby five working days which
would constitute one week with Saturday and Sunday either being
prefixed or suffixed and since month is having four weeks, therefore,
every week a rake must be booked by the petitioners on preferential
basis in terms of the agreement failing which the default cannot be
carried forward for the following and the subsequent weeks. The
language used in these circulars is both negative as well as positive to
bring home the question of sanction by way of forfeiture of this
unavailed quota. Therefore, in my opinion, this fundamentally
tantamounts to changing the terms and conditions of the WIS Scheme
and is, therefore, in violation of clause 12 of the agreement.
42. These changes in the WIS Scheme could by no stretch of
imagination be said to be a clarificatory in nature as they go to the root
of the WIS Scheme itself. No doubt, the respondents have taken a stand
that there is no liquidation or merger in the case of the petitioners but the
petitioners are not claiming the termination of the agreement on the
basis of liquidation or merger. Their case is hinged on the fact that there
is an alteration in the terms and conditions of the WIS agreement itself
by the circulars issued by the respondents.
43. I have illustrated hereinabove that the change of rakes from
monthly monitoring to fortnight and then to days with a sanction of
forfeiture for the said benefit for the ensuring week or month is
fundamentally tantamounting to alteration of the terms and conditions of
the agreement between the parties and, therefore, it gives rise to an
occasion to the petitioners to avail of the termination of the WIS
agreement in terms of clause 12.
44. The said alteration to the WIS agreement could have been done
only in accordance with clause 15 which envisaged that the respondents
could by a mutual consent by taking the petitioners into confidence that
on account of certain exigencies of service or exigencies of public
interest, it was necessary to change the terms and conditions of the
agreement. Since this has not been done, therefore, admittedly, not only
the aforesaid circulars are in violation of clause 12 of the agreement
there being lack of consent on the part of parties especially the
petitioners which is in violation of clause 15 of the agreement and,
therefore, cannot be sustained.
45. The argument which has been set up by the respondents that
under clause 6.1 (c) and clause 14 the agreement stands saved because
clause 6.1 lays down that the guaranteed rakes of traffic shall be subject
to following :
a} Rationalization of scheme.
b} Preferential traffic schedule.
c} Conditions of booking of goods traffic.
d} Central Government State bans and restriction and
e) Force majeure such as natural calamities like breaches, floods, etc.
over which Railways has no control.
46. So far as clauses (b), (d) and (e) are concerned, they on the face of
it do not apply to the facts of the present case. So far as clause (c) is
concerned, it deals with a condition of booking of goods traffic and if
read in the light of clause (14) which lays down the applicability of rules
and procedures of Indian Railways and envisages that this agreement
will be subject to all the rules and regulations of Indian Railways in
force made in pursuance to the Railways Act, 1989 then this
modification of the terms and conditions or alteration in the agreement
cannot be considered as saved by these two clauses. The reason for this
is that clause 6.1 (c) deals with the general conditions applicable to the
customers/clients across the board and does not impinge upon specific
incentives granted to the petitioners under the agreement. These
conditions which are envisaged under clause 6.1.(c) would be conditions
like the timings for booking of the rakes, the days on which the booking
is to be done, the schedule for the purpose of loading and unloading of
goods. Therefore, meaning thereby that section 6.1(c) which deals with
the conditions of booking of goods traffic are of such a nature which are
general and which do not go to the root of the agreement itself, so as to
knock off one of the parties prejudicially as has been done in the instant
case.
47. Similar would be the logic which would be applicable to the
circulars/conditions which are envisaged under clause 14 of the
agreement to all the customers across the board. Therefore, the
aforesaid analysis of the terms and conditions of the agreement clearly,
in my considered opinion, tantamount to respondents altering the basic
structure of the agreement between the parties by modifying the
essential terms and conditions of the incentives which are granted to the
petitioners and same gives rise to a cause of action in favour of the
petitioners to terminate the agreement which, they have, in my
considered opinion, validly done.
48. One of the arguments advanced on behalf of the respondents was
that the apex court had constituted a committee to look into this very
aspect as to whether the issuance of circulars by the respondents resulted
in any change in the WIS Scheme or the agreement. The said committee
had given its report that it does not result in any change.
49. My attention has not been drawn to any such committee report
consequently I did not have the advantage of going through the
reasoning for returning such a finding. I do not agree with the views of
the expressed by the committee that the aforesaid issuance of circulars
do not tantamount to alteration of basic structure of the agreement
between the parties. The reason for holding so is that the circulars have
changed the very monitoring pattern of the rakes from monthly to daily
basis with a sanction of forfeiture of the said preferential rakes.
Therefore, I feel that the petitioners were well within their rights to
terminate the agreement.
50. Having held so, the only question which arises is with regard to
sanction which is imposed under the agreement. It has been envisaged
that the respondents on account of the valid termination of the
agreement by the petitioners would either return the wagons to the
petitioners because the property in the wagons is still vested with the
petitioners as the period of contract is still subsisting and the period of
10 years from the date of the agreement has not elapsed. The
respondents were under an obligation to have returned the wagon on
account of the termination of the agreement by the petitioners on
13.09.2013. Since it was not done, therefore, the petitioners were well
within their rights to ask the respondents to purchase the wagons or the
property in the said wagons at an agreed price which it had refused to
do.
51. One of the arguments raised by the respondents is that with
respect to issuance of these circulars, there has been no discrimination
between the petitioners and other persons who are using the facilities of
booking of rakes or wagons. In my considered opinion, this argument is
of no consequence for the reason that the case of the petitioners is not
based on the ground of discrimination.
52. One of the arguments which has been given by the respondents
while rejecting the representation dated 11.09.2013 is that for the last
two years Government of India and the State Governments have
imposed various restrictions to discourage iron-ore export and to stop
illegal mining activities. Consequently, the quantum of iron ore mined
and transported through Railways has substantially dwindled. This has
affected most of the WIS and non-WIS customers except the established
steel plants. Since the WIS agreement is subject to various Government
restrictions as per clause 6.1(d) and business loss arising out of change
in the Economic Policy of Government cannot be masked as loss out of
alleged changes in terms. It was contended that issuance of circulars did
not tantamount to altering the terms and conditions of the WIS Scheme.
This submission made by the respondents is fallacious. If ban has
been imposed by the Central or the Statement Governments on the
export of iron ore with a view to stop illegal mining activities and it has
resulted in quantum of iron ore being mined and transported through
Railways substantially, then there was absolutely no ground for
rescheduling the availability of rakes to the petitioner from monthly
basis to fortnightly and then 5-day basis with two rakes and one rake
each respectively. This is on account of the fact that the question of
rationalization of making available preferential rakes to the petitioners
would arise only when there is an increased volume of goods to be
transported and not when the volume has got reduced as is admitted by
the respondents themselves. Therefore, this reasoning which has been
given by the respondents does not fit in with the change in nature of the
WIS Scheme by the respondents as there is no nexus between the
reasoning given by the Member Traffic, Railway Board and the change
in the WIS agreement which affects the rights of the petitioners
prejudicially. Accordingly, this argument also has no merit.
53. For the reasons mentioned above, I feel that the order dated
13.06.2014 rejecting the representation of the petitioners terminating the
agreement dated 18.07.2006 is totally unsustainable in the eyes of law. I
feel that since there was a change/alteration in the terms and conditions
of the WIS Scheme and consequently in the agreement dated 18.07.2006
unilaterally and arbitrarily without the consent of the petitioners which
fundamentally changed the nature of WIS Scheme, so far as the
preferential right of the petitioners is concerned, the petitioners were
well within their right to terminate the agreement. The agreement
having been terminated, the respondents were under an obligation to
purchase the wagons from the petitioners at a fixed price in the event of
non returning the same to the petitioners as the property in wagons
continued to vest with the petitioners. I accordingly hold that the order
dated 13.06.2014 of the Member Traffic, Railway Board is
unsustainable in the eyes of law and the same is liable to be set aside
and a writ of mandamus is issued to the respondents to either return the
wagons to the petitioners within a period of one month from today or
alternatively to purchase the wagons at an agreed price. However, so far
as the question of purchase of wagons by the respondents is concerned,
the price has to be agreed between the parties and certainly what will be
the price of the wagons will be a disputed question. Since this is a
disputed question of fact as to what would be the price unless it is
mutually agreed, it deserves to be adjudicated, it will be not proper to
permit the parties to fix either of the price unilaterally so as to cause
further delay in the final disposal of the matter and in such a
contingency since there is an arbitration clause, I feel that this aspect of
the matter deserves to be settled through arbitration.
54 It may be further pertinent here to mention that since the present
order is disposing of two writ petitions, the reasoning and holding which
has been arrived at in WP(C) No.5124/2014 shall be equally applicable
mutatis mutandis to the WP(C) No.5127/2014 and accordingly the
impugned order dated 18.06.2014 of Member Traffic, Railway Board in
the said writ petition is also set aside and as for the directions passed
with respect to appointment of an arbitrator in WP(C) No.5124/2014,
the same would also be equally applicable to WP(C) No.5127/2014.
55. For the determination of the price of the wagons, I appoint
Mr.R.C.Chopra (Mobile: 9818097777), a retired Judge of this court, as
an arbitrator to adjudicate the dispute within a period of four months
from today. The learned arbitrator shall be governed by the rules and
regulations as well as the payment of fees by the terms and conditions
governing the arbitration by the Delhi International Arbitration Centre.
56. Accordingly the writ petitions stand allowed in the aforesaid
terms.
V.K. SHALI, J.
JUNE 29, 2015 dm
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!