Citation : 2015 Latest Caselaw 5130 Del
Judgement Date : 17 July, 2015
$~2
THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment delivered on: 17.07.2015
+ FAO(OS) 370/2015
NATIONAL HIGHWAYS AUTHORITY OF INDIA ... Appellant
versus
M/S SUNWAY CONSTRUCTION SDN BHD ... Respondent
Advocates who appeared in this case:
For the Appellant : Ms Ayushi Kiran
For the Respondent : Mr Amit George with Ms Rajsree Ajay
CORAM:-
HON'BLE MR JUSTICE BADAR DURREZ AHMED
HON'BLE MR JUSTICE SANJEEV SACHDEVA
JUDGMENT
BADAR DURREZ AHMED, J (ORAL) CM 12271/2015 Allowed subject to all just exceptions.
CM 12269/2015 We have heard the learned counsel for the parties. The delay is condoned.
The application stands allowed.
FAO(OS) 370/2015 & CM 12268/2015 & CM 12270/2015
1. This appeal is directed against the judgment and/ or order dated
13.03.2015 passed by a learned Single Judge of this Court in OMP 166/2015,
which was a petition under Section 34 of the Arbitration and Conciliation Act,
1996 (hereinafter referred to as 'the said Act') in respect of an Award dated
30.09.2014 passed by the Arbitral Tribunal. The said petition was filed by the
appellant herein being aggrieved by the said Award. The Arbitral proceedings
arose out of an agreement dated 11.08.2005 entered into between the appellant
and the respondent for rehabilitation and upgrading of Km 406.00 to km
449.150 of NH-76 to 4 lane configuration in the State of Rajasthan, Contract
Package - EW-II (RJ-9) (hereinafter referred to as 'the contract').
2. Essentially, the dispute centres around two amounts. First of all, there
is an amount of Rs 3,39,31,497/-. This amount had been withheld by the
petitioner on account of certain observations made by the Comptroller and
Auditor General of India in an enquiry which he undertook in January, 2010.
This is an undisputed amount certified for payment, but has not been paid to
the respondent because of the observations of the CAG. It essentially relates
to the excise duty liability. The learned counsel for the appellant submits that
as long as that liability stands and the vigilance enquiry is in progress, the said
amount cannot be paid. This aspect of the matter has been considered in
detail by the Arbitral Tribunal as also by the learned Single Judge. Both have
held that there is no provision in the contract which permits the appellant to
withhold payment of the said amount.
3. In response to this, the learned counsel for the appellant draws our
attention to Clause 26.1 of the General Conditions of Contract which provides
that the contractor shall keep the employer indemnified against all penalties
and liability of every kind against the breach of any statute and/or regulation.
4. In response to this submission, the learned counsel for the respondent
states that this is a condition of the contract and the respondent shall continue
to be bound by this provision even if the payment of the said amount of
Rs 3,39,31,497/- is made. He further submitted that Clause 26.1 was only an
indemnity clause and the respondent shall continue to be bound by the said
clause and shall keep the appellant indemnified against all penalties and
liability of every kind against any breach of any statute and/ or regulation. We
accept the view expressed by the learned counsel for the respondent.
5. Consequently, we feel that no interference is called for in the impugned
order or Award directing the appellant to make the payment of
Rs 3,39,31,497/-. This would, however, be subject to the indemnity given by
the respondent under Clause 26.1 which shall continue to hold good.
6. The second dispute is with regard to an amount of Rs 2,28,43,270.52.
Insofar as this amount is concerned, we note that in the Section 34 petition,
which was filed by the appellant, ground 'D' has referred to the same. In the
said ground, it was mentioned that the contractor had repeatedly and
persistently disputed the final payment certificate issued by the engineer. It
was also mentioned that all along the payment received by the contractor on
account of variation valued by the engineer was disputed and the provisional
payments were also received under protest. It was further stated that the
contractor had till date not given its acceptance of the rate analysis and rate
proposed by the engineer and on that account Rs 2,28,43,270.52 was kept on
hold by the appellant.
7. The learned counsel for the respondent submits that he accepts the rate
analysis and the rate proposed by the engineer in respect of the items which
form the subject matter of the present Award. It is also accepted by him that
in case there is an overlap with regard to the items covered by the present
Award and the subject matter of disputes which are pending between the
parties, then the statement made here shall be binding in those cases also to
the extent of the overlap.
8. Accordingly, we direct that the sum of Rs 2,28,43,270.52 shall be paid
by the appellant to the respondent and simultaneously the respondent shall
give a discharge certificate in respect of all claims which form the subject
matter of this Award.
The appeal stands disposed of in the above terms.
BADAR DURREZ AHMED, J
JULY 17, 2015 SANJEEV SACHDEVA, J
SR
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!