Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Dsc Ltd. vs Earthcon System (I) Pvt. Ltd.
2015 Latest Caselaw 4978 Del

Citation : 2015 Latest Caselaw 4978 Del
Judgement Date : 14 July, 2015

Delhi High Court
Dsc Ltd. vs Earthcon System (I) Pvt. Ltd. on 14 July, 2015
Author: Valmiki J. Mehta
*              IN THE HIGH COURT OF DELHI AT NEW DELHI

+                           OMP No. 374/2015
%                                                      14th July, 2015

DSC LTD.                                                      ..... Petitioner

                            Through:     Mr. Sushil Kr. Kabra, Adv.

                            versus

EARTHCON SYSTEM (I) PVT. LTD.                                 ..... Respondent

                            Through:

CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA

To be referred to the Reporter or not?


VALMIKI J. MEHTA, J (ORAL)

1.             This is a petition under Section 34 of the Arbitration and

Conciliation Act, 1996 (hereinafter referred to as 'the Act') challenging the

Award passed by the sole Arbitrator on 4.3.2015. By the impugned Award, the

Arbitrator has allowed the claim petition and granted amounts to the respondent

herein, claimant in the arbitration proceedings, for the value of the work done

as also interest thereon.


2,             The arbitrator framed the following issues:-


               "Issue no.1. Whether the Statement of Claim has been instituted
                            in accordance with law and whether Mr. Rajiv Goel
                            who has signed the claim petition is duly and

OMP 374/2015                                                                     Page 1 of 4
                              authorized to institute, sign and verify the Statement
                             of Claim on behalf of the claimant?
               Issue no.2.   Whether the claims made by the claimant in the
                             claim petition arise out of two separate and
                             independent work orders/Purchase orders relating to
                             the same projects issued by the respondent, if yes,
                             whether the present arbitration proceedings arising
                             out of claims which are based on two separate
                             independent work orders/Purchase orders are
                             maintainable?
               Issue no.3.   Whether the claimant is entitled to a sum of
                             Rs.30,67,306/- on account of the work executed and
                             supplies made by it under the work orders dated
                             14.07.2009 and 06.02.2010 and Purchase Order
                             dated 20.03.2010?
               Issue no.4.   Whether the claimant is entitled to interest @ 18%
                             p.a. w.e.f. the date on which the amount became due
                             till the realization of amount, inclusive of pendentlite
                             and future interest at the same rate?
               Issue no.5.   Whether the claimant is entitled to the damages of
                             Rs.5,00,000/- on account of harassment suffered by
                             it due to delayed payment of bills?
               Issue no.6.   Whether the claimant is entitled to a sum of
                             Rs.5,00,000/- towards litigation cost?"

3.             The Arbitrator then notes in the impugned Award that petitioner

herein, respondent in the arbitration proceedings, has not cross-examined the

witness of the claimant that no amount as claimed is payable. Arbitrator also

notes that petitioner herein in spite of being given several opportunities did not

lead evidence and ultimately the right of the petitioner herein to lead evidence

was closed. Hence the claimant in the arbitration proceedings, respondent

OMP 374/2015                                                                      Page 2 of 4
 herein, proved its case and consequently the Arbitrator allowed the claim with

respect to the work executed by the respondent herein under the Work Orders

dated 14.7.2009 and 6.2.2010 and the Purchase Order dated 20.3.2010. While

awarding Claim No.1 the Arbitrator has noted the exact measurement of work

which was done as per the petitioner herein, and for such measured work only

Arbitrator has allowed the Claim No.1. With respect to Claim No.1 Arbitrator

awarded an amount of Rs.25,81,566/- for the work done.              Arbitrator has

thereafter awarded interest at 9% per annum and which in the opinion of this

Court is a reasonable rate of interest.


4.             The grievances of the petitioner herein are two-fold. Firstly, it is

argued that so far as the Purchase Order dated 20.3.2010 is concerned, there

was no arbitration clause and hence the Arbitrator could not have passed an

Award with respect to disputes which were not covered under the Arbitration

Agreement.


5.             This contention urged on behalf of the petitioner is misconceived

because it is noted that disputes were referred to an Arbitrator pursuant to

Section 11 petition filed in this Court being Arb. Petition No. 60/2013 and the

Arbitrator has acted pursuant to the order of this Court dated 21.3.2013

referring the disputes to arbitration. This order dated 21.3.2013 has achieved

finality. Whatever disputes were specifically referred to arbitration have only
OMP 374/2015                                                                    Page 3 of 4
 been decided by the Arbitrator and therefore the decision under Section 11 of

the Act operates as res judicata against the petitioner, and petitioner cannot

contend that the Arbitrator was not competent to decide the disputes referred to

the Arbitrator and accordingly decided by the Arbitrator. This argument urged

on behalf of the petitioner therefore is hence rejected.


6.             The second grievance of the petitioner is that the rate of interest

which has been awarded has been awarded from a date which has no rationale

or basis being 30.11.2011. However I note that the Arbitrator has rightly taken

this date being the commencing date for payment of interest because part

payment was made by the petitioner to the respondent herein on 30.11.2011

meaning thereby as on 30.11.2011, work was done, and payment was due to the

respondent herein from 30.11.2011.


7.             In view of the above, I do not find that the Arbitrator has

committed any violation of law or violation of provisions of contract or that the

Award is perverse for this Court to interfere with under Section 34 of the Act.


8.             Dismissed.




JULY 14, 2015                                         VALMIKI J. MEHTA, J.

ib

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter