Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Jagson International Ltd vs Oil & Natural Gas Corporation Ltd
2015 Latest Caselaw 4900 Del

Citation : 2015 Latest Caselaw 4900 Del
Judgement Date : 13 July, 2015

Delhi High Court
Jagson International Ltd vs Oil & Natural Gas Corporation Ltd on 13 July, 2015
Author: Badar Durrez Ahmed
$~12
*       IN THE HIGH COURT OF DELHI AT NEW DELHI
%                                      Judgment delivered on: 13.07.2015

+       W.P.(C) 6546/2015


JAGSON INTERNATIONAL LTD                                       ....    Petitioner

                                       versus


OIL & NATURAL GAS CORPORATION LTD                              ..... Respondent

Advocates who appeared in this case:
For the Petitioner  : Mr Ajit Sinha, Sr Advocate with Mr Sanjay
                      Grover and Mr Shivlal Singh
For the Respondent : Mr Tushar Mehta, ASG with Mr Biju P.
                      Raman, Mr Rajat Nair and Mr Sasi Prabhu


CORAM:-
HON'BLE MR JUSTICE BADAR DURREZ AHMED
HON'BLE MR JUSTICE SANJEEV SACHDEVA

                                       JUDGMENT

BADAR DURREZ AHMED, J (ORAL)

CM 11916-11917/2015 Allowed subject to all just exceptions.

WP(C) 6546/2015 & CM 11915/2015

1. The petitioner challenges Clause 4.1 of the Bid Evaluation Criteria of the

subject tender. The respondent (ONGC) had issued an invitation to bid on

24.04.2015 for charter hire of offshore rigs, as detailed in the said notice inviting

tender. The petitioner had earlier been issued a letter of award in respect of its

drilling unit. However, that drilling unit never became functional. There is a

letter on record (Annexure-K to the writ petition) dated 07.05.2014 cancelling the

earlier letter of award. It is specifically stated there in paragraphs 3.0, 4.0, and 5.0

as under:-

"3.0 You failed to mobilise the Drilling Unit in terms of the LOA and requested for extension of time on several occasions. ONGC extended the mobilisation period for the Drilling Unit with levy of liquidated damages, the latest extension being upto 07.05.2014.

4.0 Despite several extensions in mobilisation period for the Drilling Unit, you have not mobilised & deployed the Drilling Unit so as to commence the operations till date. Instead of mobilising the Drilling Unit, you have once again vide your letter dated 23.04.2014 requested for an extension of time till 31.10.2014 for mobilisation of the Drilling Unit.

5.0 Please note that ONGC will not be able to give you any more extension for mobilisation of the Drilling Unit. In case you fail to mobilise & deploy the Drilling Unit so as to commence the operations by 24:00 hours on 07.05.2014 in terms of Clause 3.0 of the LOA, the LOA / Contract shall stand terminated with immediate effect. You shall be liable for all the consequences of such termination/ breach of the terms and conditions of the LOA / Contract, including adjustment / recovery of inspection charges incurred by ONGC from amounts payable to you under any other contract with ONGC."

It is clear from the above, as has been pointed out by Mr Tushar Mehta, the

learned ASG appearing on behalf of the ONGC, that the petitioner could not

mobilise the drilling unit.

2. Clause 4.1 referred to above, which is the subject matter of challenge, reads

as under:-

"4.1 The bidders should offer drilling rig(s) suitable for drilling wells for the water depth and environmental criteria mentioned in the bid document. The bidders, should offer only Serviceable Drilling Units and idling period of the Drilling Unit should not be more than 3years on the date of submissions of bids i.e., the drilling rig should have carried out operations on at least one well during last 3 years on the date of opening of unpriced bids.

The bidders shall submit documentary evidence towards operation of the drilling unit alongwith unpriced bid. The complete details of the last operator, the last contract taken up and the period during which the drilling unit was last in operation shall be indicated.

The bidders shall also furnish certificate from any one of the third parly inspection agencies like LRDIS, Oil Field Audit Services Inc., DNVGL NDA or ABS alongwith the un-priced bid bringing out clearly the condition and status of the drilling unit and equipments on board the drilling unit. However, the above mentioned conditions are not applicable for bidders offering rigs under construction."

(Underlining added)

3. Actually, the challenge to Clause 4.1 is only with regard to the portion after

'i.e'. In other words, there is no challenge to the portion prior to the expression

'i.e'. The portion which has been added in the subject tender which was not there

earlier is only explanatory and clarificatory of the earlier condition that bidders

should offer only Serviceable Drilling Units and idling period of the Drilling Unit

should not be more than three years on the date of submissions of bids. It has

been clarified by the additional portion that the drilling rig should have carried out

operations on at least one well during last 3 years on the date of opening of

unpriced bids. In the present case, the drilling rig / unit of the petitioner was

supposed to be deployed pursuant to the letter of award given earlier by the

respondent. That, as we have seen from the letter dated 07.05.2014 could not be

deployed / mobilized by the petitioner despite repeated opportunities having been

given by the respondent. It is, therefore, clear that the petitioner's drilling unit

remained idle for more than three years prior to the date of submission of the bids.

Even if we do not look at the clarificatory portion of Clause 4.1, the petitioner

would have no case. This is particularly so because the cancellation / termination

letter dated 07.05.2014, placing the blame on the petitioner that it failed to

mobilize the drilling unit in terms of the LOA, has not been challenged by the

petitioner before any forum.

4. The learned counsel for the petitioner seeks to draw our attention to pages

77, 78 and 82 of the paper book to indicate that the drilling unit was ready and that

there was a default on the part of the respondents. Be that as it may, the final seal

to the matter was furnished by the termination letter dated 07.05.2014, to which

there is no challenge.

5. In view of the foregoing, there is no merit in the writ petition. The same is

dismissed.

Dasti.

                                           BADAR DURREZ AHMED, J



JULY 14, 2015                               SANJEEV SACHDEVA, J
SR





 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter