Citation : 2015 Latest Caselaw 389 Del
Judgement Date : 15 January, 2015
IN THE HIGH COURT OF DELHI AT NEW DELHI
O.M.P. 322/2013
ENFIELD INFRASTRUCTURE LIMITED ..... Petitioner
Through: Ms. Kavita Jha and Ms. Shraddha,
Advocates.
versus
NTPC VIDYUT VYAPAR LTD. & ORS. ..... Respondents
Through: Mr. Bharat Sangal with
Ms. Anasuya Choudhury and Ms. Saggar
Malhotra, Advocates for Respondent No.1.
Mr. Anuj Aggarwal, Advocate for Respondent
No.4.
CORAM: JUSTICE S. MURALIDHAR
ORDER
15.01.2015
1. This petition under Section 9 of the Arbitration and Conciliation Act,
1996 ('Act') by Enfield Infrastructure Limited ('EIL') seeks interim
relief in respect of a bank guarantee for Rs.5,07,54,000 and two bank
guarantees for Rs.10,15,08,000 each against Respondent No.1 NTPC
Vidyut Vyapar Ltd. ('NVVL') furnished by EIL to NVVL.
2. EIL and NVVL entered into a power purchase agreement ('PPA') on
25th January 2012. Pursuant thereto the aforementioned three bank
guarantees were furnished by EIL to NVVL. In terms of the PPA, EIL
was required to commission the Solar PV Project of 10MW capacity at
village Mandali in Jodhpur district, Rajasthan. The Rajasthan
Renewable Energy Corporation Limited ('RRECL') was appointed as
the State nodal agency and was obligated to facilitate EIL in
constructing and commissioning the power plant. As per the PPA, EIL
was required to commission the project and inject power from the power
project to the delivery point within 13 months of signing the PPA. The
effective commissioning date was, therefore, 26th February 2013.
3. According to EIL, the land site assigned to it for the project was not
found suitable due to problems caused by the local villagers. The
alternative site identified by the Petitioner was not made available as
NVVL did not grant the requisite No Objection to the change of site.
The said No Objection was granted by NVVL on 24th July 2012.On 8th
October 2012 the necessary amendment to the PPA was carried out. EIL
states that it is only after the said amendment that it could initiate the
civil and other construction work at the site. According to EIL, RRECL
was to grant permission for constructing a project road to the project
site. This was granted by RRECL only on 29th January 2013. It is then
stated that in the same month, the local villagers encroached on the site
land and hindered the construction work.
4. As a result of delay in commissioning the project by the scheduled
commissioning date, EIL sent letters to NVVL on 28th January 2013 and
5th February 2013 seeking extension of time under clause 4.5 of the
PPA. According to EIL, the request for extension of time was due to
Force Majeure events. On 5th February 2013, NVVL wrote to EIL
rejecting its request for extension of time. It is stated that despite a
further letter sent by EIL to NVVL on 21st February 2013, NVVL
threatened to invoke the bank guarantees in question. It was in the above
circumstances that the Petitioner approached the Court to restrain
NVVL from invoking the bank guarantees.
5. On 3rd April 2013, the Court passed an order, the operative portion of
which reads as under:
"Learned Senior counsel for the petitioner has referred to earlier order dated 1st March, 2013 passed in O.M.P. No.205/2013. His submission is that since the respondent No.1 in its letter dated 5th February, 2013 did not agree to accept the justification given by the petitioner with regard to Force Majeure, it is an apprehension that the respondents may invoke the bank guarantees in question. After having considered the pleadings and material placed on record, till the next date of hearing, subject to keeping the bank guarantees in question alive, the status quo be maintained by the respondents in respect of the following Bank Guarantees:-
Issuing Bank Bank Guarantee details
State Bank of Bikaner 1037612BG0000440
and Jaipur dated 21st January,
2012, valid till 26th
May, 2013
Dena Bank 124712IGPER0002
dated 24th January,
2012, valid till 26th
May, 2013
Dena Bank 124712IGPER0001
dated 24th January,
2012, valid till 26th
May, 2013
6. The said interim orders have continued till date. At one stage the
parties explored the possibility of a settlement but that did not
materialize.
7. The Court is informed today that the Arbitral Tribunal ('AT') has
since been constituted and its first sitting took place on 8th August 2014.
8. It is submitted at the outset by Mrs. Kavita Jha, learned counsel for
the Petitioner, that the interim order passed by the Court on 3rd April
2013 should be continued till such time the AT decides an application
that may be filed by either party under Section 17 of the Act. She
submits that a question whether the stay on the invocation of the bank
guarantees in question should be continued can be decided by the AT.
9. On merits Ms. Jha submits that under clause 4.5 of the PPA, NVVL
was obliged to grant extension of time since the Force Majeure events
continued. She refers to the averments in para 22 of the petition which
lists out the Force Majeure events. She points out that in para 31 of the
petition it has been averred that "fraud of an egregious nature has been
played by Respondent No.1 on the Petitioner" and, therefore, there was
a prima facie case in favour of the Petitioner for continuing the interim
orders in its favour during the pendency of the arbitral proceedings.
10. Mr. Bharat Sangal, learned counsel for NVVL has opposed the
above submissions. He submits that there is no justification for staying
the invocation of the bank guarantees. He submitted that the law in this
regard has been consistently explained by the Supreme Court in several
decisions. He relied on the decisions in U.P. State Sugar Corporation v.
Sumac International Ltd. (1997) 1 SCC 568 and Vinitec Electronics
Private Ltd. v. HCL Infosystems Ltd. (2008) 1 SCC 544. Mr. Sangal
submitted that apart from a bald plea of fraud, there is nothing in the
petition to show that the Petitioner would be subjected to any
irretrievable injury or irretrievable injustice warranting continuance of
the interim order against the invocation of the bank guarantees. He
pointed out that none of the Force Majeure events cited by the Petitioner
were attributable to any act of NVVL and, therefore, there was no
justification in preventing NVVL from enforcing the bank guarantees.
11. The above submissions have been considered. The law concerning
interference by the Court with the enforcement of bank guarantees is
fairly well settled. In U.P. State Sugar Corporation (supra), the
Supreme Court explained in para 12 as under:
"12. The law relating to invocation of such bank guarantees is by now well settled. When in the course
of commercial dealings an unconditional bank guarantee is given or accepted, the beneficiary is entitled to realize such a bank guarantee in terms thereof irrespective of any pending disputes. The bank giving such a guarantee is bound to honour it as per its terms irrespective of any dispute raised by its customer. The very purpose of giving such a bank guarantee would otherwise be defeated. The Courts should, therefore, be slow in granting an injunction to restrain the realization of such a bank guarantee. The Courts have carved out only two exceptions. A fraud in connection with such a bank guarantee would vitiate the very foundation of such a bank guarantee. Hence if there is such a fraud of which the beneficiary seeks to take advantage, he can be restrained from doing so. The second exception relates to cases where allowing the encashment of an unconditional bank guarantee would result in irretrievable harm or injustice to one of the parties concerned. Since in most cases payment of money under such a bank guarantee would adversely affect the bank and its customer at whose instance the guarantee is given, the harm or injustice contemplated under this head must be of such an exceptional and irretrievable nature as would override the terms of the guarantee and the adverse effect of such an injunction on commercial dealings in the country. The two grounds are not necessarily connected, though both may co-exist in some cases. In the case of U.P. Co- operative Federation Ltd. v. Singh Consultants and Engineers (P.) Ltd. (1998) 1 SCC 174 which was the
case of a works contract where the performance guarantee given under the contract was sought to be invoked, this Court, after referring extensively to English and Indian cases on the subject, said that the guarantee must be honoured in accordance with its terms. The bank which gives the guarantee is not concerned in the least with the relations between the supplier and the customer; nor with the question whether the supplier has performed his contractual obligation or not, nor with the question whether the supplier is in default or not. The bank must pay according to the tenor of its guarantee on demand without proof or condition. There are only two exceptions to this rule. The first exception is a case when there is a clear fraud of which the bank has notice. The fraud must be of an egregious nature such as to vitiate the entire underlying transaction."
12. The Court further explained with reference to the decisions in
United State District Court in Itek Corporation v. First National Bank
of Boston 566 Fed Supp 1210 that an irretrievable injury has to be of
such a kind that realisation of the bank guarantee would "make it
impossible for the guarantor to reimburse himself if he ultimately
succeeds." Recently in Vinitec Electronics Private Ltd. (supra) the
above legal position was reiterated. It was explained that with the bank
guarantees being unconditional and irrevocable, the bank was bound to
honour it and pay the amounts "at once upon receipt of written demand
of the Respondent." The Court rejected the plea of fraud in that case as
being vague and indefinite and not satisfying the requirement of law.
Even the plea of irretrievable injustice was "again vague and not
supported by any evidence."
13. Turning to the present case the Court finds that the plea of fraud
raised in para 31, is indeed vague and unsubstantiated and does not
satisfy the requirement of law as explained by the Supreme Court in the
above decisions. In Svenska Handelsbanken v. Indian Charge Chrome
AIR 1994 SC 626 it was stressed by the Supreme Court as under:
"We have already held that the contracts between the lenders and the borrower are not vitiated by any fraud much less established fraud and there is no question of irretrievable injury, therefore, there was no reason for the High Court to set aside the order of the trial court. Against there is no case of any irretrievable injury either of the type as held in the case of Itek Corporation (supra) as there is no difficulty in the judgment of this country being executable in the courts in Sweden.
The High Court was not right in working on mere suspicion of fraud or merely going by the allegations in the plaint without prima facie case of fraud being spelt out from the material on record."
14. The second exception spelt out in the above decisions to the general
rule that Courts will normally not grant stay of an enforcement of bank
guarantee, requires the Petitioner to establish that the encashment of the
bank guarantee will cause irretrievable injustice or irretrievable injury.
Apart from setting out the Force Majeure events in terms of clause 4.5
of the PPA, which according to the NVVL has nothing to do with, there
is no averment in the petition that the Petitioner would be subject to
irretrievable injustice. The usual grounds of irreparable loss and injury
which cannot be compensated in terms of the money is pleaded. That
does not, however, satisfy the requirement of the Petitioner having to
establish the exceptional conditions repeatedly stressed by the Supreme
Court in the aforementioned decisions.
15. Consequently, the Court is not satisfied that the present case falls
within either of the exceptions pointed out by the Supreme Court in the
aforementioned decisions warranting the continuation of the stay on the
encashment of the bank guarantees.
16. Consequently, this Court is not satisfied that the Petitioner has made
out a prima facie case for continuing the stay on the encashment of any
of the bank guarantees. Accordingly, the interim order dated 3rd April
2013 is vacated. It is, however, clarified that the encashment of the bank
guarantees by Respondent No.1 will be subject to the outcome of the
arbitral proceedings.
17. The petition is dismissed with no order as to costs.
S. MURALIDHAR, J.
JANUARY 15, 2015 dn
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!