Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Rattan Singh Builders Pvt. Ltd. vs Punj Lloyd Ltd.
2015 Latest Caselaw 961 Del

Citation : 2015 Latest Caselaw 961 Del
Judgement Date : 3 February, 2015

Delhi High Court
Rattan Singh Builders Pvt. Ltd. vs Punj Lloyd Ltd. on 3 February, 2015
Author: S. Muralidhar
        IN THE HIGH COURT OF DELHI AT NEW DELHI

                          ARB.P. 541/2014

        RATTAN SINGH BUILDERS PVT. LTD.         ..... Petitioner
                     Through: Mr. Prabhjit Jauhar with
                              Ms. Anupama Kaul, Advocates.

                          versus

        PUNJ LLOYD LTD.                       ..... Respondent
                     Through: Mr. J.P. Sengh, Senior Advocate
                              with Mr. Divyam Agarwal and
                              Ms. Ritika Kohli, Advocates.

        CORAM: JUSTICE S. MURALIDHAR

                          ORDER

03.02.2015

1. This is a petition under Section 11 of the Arbitration and

Conciliation Act, 1996 ('Act') seeking the appointment of an

Arbitrator to adjudicate the disputes between the parties.

2. The Petitioner and the Respondent entered into an agreement dated

6th April 2010 whereby the Respondent appointed Petitioner as

contractor to execute the civil and plumbing works for construction of

the proposed land system facility at Malanpur, District Bhind

(Madhya Pradesh). The value of the work was Rs. 21,62,00,000

(Rupees Twenty One Crores, Sixty Two Lakhs only). The contract

was modified by a letter dated 6th April 2010 which formed part and

parcel of the agreement dated 6th April 2010.

3. The Petitioner states that it completed the work order and the

contract to the satisfaction of the Architect in terms of the contract

and handed over the site to him in November 2011. In September

2011, the final bill had been submitted by the Petitioner. The

certificate of payment was issued by the Architect in terms of which

the Petitioner was also entitled to Rs. 2,14,94,273 by the Architect.

4. According to the Petitioner, only part payment of Rs. 60 lakhs was

disbursed by the Respondent to the Petitioner in the month of January

2012. A legal notice dated 12th July 2012 was served upon the

Respondent under Section 434 of the Companies Act, 1956 ('CA').

5. On 29th January 2014, an order was passed by the Company Court

in Company Petition No. 211 of 2013 noting inter alia that between

the parties there remained some controversy with regard to a sum of

Rs. 25,81,500 that had been retained by the Respondent for curing

certain alleged defects. The parties were then referred to the Delhi

High Court Mediation and Conciliation Centre ('DHCMCC'). The

Court in the said order dated 29th January 2014 observed that in the

event the parties were unable to resolve their disputes through

mediation, the Petitioner would be secured by the Respondent by

depositing the aforementioned amount and the parties would be at

liberty to initiate such action as may be advised within a specified

period of two months thereafter.

6. Apparently the mediation proceedings were not successful. On 6th

March 2014, the Respondent wrote to the Petitioner stating that as per

its record as of 31st December 2013 a sum of Rs. 79,67,975 was

payable to the Petitioner, subject to reconciliation. In response

thereto, on 20th March 2014, the Petitioner informed the Respondent

that apart from the outstanding balance as on 31st December 2013 of

Rs. 80,46,702, in the books of the Petitioner, a further sum of Rs.

28,34,452 was to be received from the Respondent. This was

followed by a legal notice dated 1st July 2014 sent to the Respondent

invoking the arbitration clause. It was inter alia stated therein as

under:

"17. That however at the time of raising 12th final bill against certificate No. 12, my clients inadvertently claimed only a sum of Rs. 2,14,94,273 but did not claim the balance amount of Rs. 25,52,429 against previous balance upto 11th running account certificate as my client ought to have claimed a sum of Rs. 2,40,46,702 in their final bill. However later on the said lapse on the part of my client was duly admitted by addressee company vide their letter dated 6th March 2014 wherein they have admitted that an amount of Rs. 79,67,975 was due and

payable to my client as per their books and wanted my clients to give a confirmation of the said amount due and payable to my clients."

7. This was followed by another notice dated 14th August 2014 again

seeking the appointment of the Arbitrator.

8. Mr. J.P. Sengh, learned Senior counsel appearing for the

Respondent, referred to a decision of this Court in Sushil Kumar

Bhardwaj v. Union of India 2009 LawSuit (Del) 768 and submitted

that since the procedure outlined in the contract between the parties

was not followed by the Petitioner, the present petition under Section

11 of the Act cannot be entertained. It is submitted by Mr. Sengh that

it is only when the parties failed to resolve the disputes in terms of the

arbitration clause, could the Court be approached under Section 11 of

the Act. It is further submitted that it is not open to the Petitioner to

expand its claim beyond what was stated in the notice issued under

Section 434 of the CA. Relying upon the order dated 29th January

2014, passed in Company Petition No. 211 of 2013 he submitted that

the Petitioner could claim only Rs. 25,81,500.

9. Mr. Prabhjit Jauhar, learned counsel appearing for the Petitioner,

on the other hand submitted that with the parties having failed to

resolve their disputes through mediation, no purpose would be served

in again attempting that process at this stage. In support of the above

proposition he relied upon the decision of the designated Judge in

Datawind Limited v. Indian Institute of Technology Rajasthan

(decision dated 13th December 103 in Arbitration Petition No. 20 of

2013). He also relied upon the decision of the Supreme Court in

Arasmeta Captive Power Company Private Limited v. Lafarge India

Private Limited AIR 2014 SC 525 and submitted that the question

whether the Petitioner can claim anything beyond what was noted in

the order dated 29th January 2014 passed by the Company Court can

be examined by the learned Arbitrator. He pointed out that by a

subsequent order dated 2nd May 2014 in Company Petition No. 211 of

2013, it was noted that the Respondent had deposited a sum of

Rs. 25,81,500 in this Court and that amount was directed to be kept in

an interest bearing fixed deposit.

10. The above submissions have been considered. As regards the

objection of the Respondent with regard to non-compliance of the

procedure outlined in the arbitration clause between the parties, the

Court notes that pursuant to the order passed by the Company Court

on 29th January 2014, the parties did go before the DHCMCC.

Therefore, the requirement of the arbitration clause of the parties

having to attempt to resolve the disputes through mediation was

satisfied. That mediation was not successful is another matter

altogether.

11. This was followed by the deposit made by the Respondent of the

amount noted in the order dated 29th January 2014. While recording

that fact in the subsequent order dated 2nd May 2014 in Company

Petition No. 211 of 2013, the Court directed the parties to initiate

action within two months. Pursuant thereto on 1st July 2014, a legal

notice was issued by the Petitioner invoking the arbitration clause.

Therefore, that order was also complied with. In light of the law

explained by the Supreme Court in Datawind Limited (supra) the

Court finds that there is no bar to the appointment of an Arbitrator,

once it is clear that efforts were made, although unsuccessfully, to

amicably resolve the disputes in terms of the arbitration clause.

12. As regards the issue whether the Petitioner can be permitted to

claim an amount beyond what is stated in the initial notice under

Section 434 of the CA, the Court is of the view that this is an issue

that can be examined by the learned Arbitrator. This Court is not

called upon to examine that issue in light of the legal position

explained by the Supreme Court in Arasmeta Captive Power

Company Private Limited (supra).

13. Accordingly, the Court appoints Mr. Rakesh Kapoor, District &

Sessions Judge (retired), residing at 5-C, Court Road, Civil Lines,

Delhi-110054 (Telephone No. 23993200) as sole Arbitrator to

adjudicate the disputes between the parties including their claims and

counter-claims. The arbitration shall take place under the aegis of the

Delhi International Arbitration Centre ('DAC'). The fees of the

learned Arbitrator will be in terms of the Delhi High Court

Arbitration Centre (Arbitrators' Fees) Rules.

14. The petition is disposed of. A copy of this order be communicated

to the learned Arbitrator as well as Additional Coordinator, DAC

forthwith.

S. MURALIDHAR, J.

FEBRUARY 03, 2015 Rk

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter