Citation : 2015 Latest Caselaw 1580 Del
Judgement Date : 24 February, 2015
$~13
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment delivered on: 24.02.2015
+ W.P.(C) 6695/2014 & CM Appl. 15887/2014
M/S. APEX ENCON PROJECTS PVT. LTD. DELHI .... Petitioners
Versus
DIRECTOR GENERAL MARRIED ACCOMMODATION PROJECT
DELHI & ANR ..... Respondents
Advocates who appeared in this case:
For the Petitioner : Mr T.V.L.Narasimha Rao and Mr Anurag Jain, Advocates.
For the Respondents : Mr Jasmeet Singh CGSC with Mr Kritik, Advocate for UOI.
CORAM:-
HON'BLE MR JUSTICE BADAR DURREZ AHMED
HON'BLE MR JUSTICE SANJEEV SACHDEVA
JUDGMENT
BADAR DURREZ AHMED, J (ORAL)
1. An invitation for pre-qualification of contractors was taken out by
the Director General Married Accommodation Project (MAP), Ministry
of Defence, Government of India, by virtue of notice dated 29.05.2014.
It may be pointed out that several works were specified in the said
invitation. The present petition is concerned with the work listed at serial
No.6. The same is as under: -
PQ No : DGMAP/PH-II/NOTICE NO.1 OF 2014-15
Sl Name of Work Estimated Value of Average Solvency Period of No. cost of satisfactorily yearly (in Competition work (in completed Financial Crore) Crore) similar Turnover works (in Crore)
----- ------ ------ ------- ------ ------- ------
------ ------ ------ ------ ------ ------ ------
6 COMPLETION OF 155.00 One work of 46.50 46.50 25 Months
BALANCE 93 Crore or
WORKS FOR two works of
CONSTRUCTION 62.00 Crore
OF DWELLING each or three
UNITS works of
INCLUDING 46.50 Crore
ALLIED each
SERVICES FOR
OFFICERS, JCOs
& ORS AT
HYDERABAD
(AF), DUNDIGAL,
SECUNDERABAD,
BEGUMPET (AF),
BIDAR,
HAKIMPET (AF)
----- ------ ----- ------ ---- ---- -----
2. It may be pointed out that only the balance work, as indicated in
serial No.6, is the subject matter of the present petition. Earlier, the
contract for construction of the dwelling units had been awarded to the
petitioner. That contract was cancelled by the respondent under condition
Nos 46, 47 and 48 of the general conditions of contract. The petitioner's
bid has been rejected on the ground-- "03 MAP contracts cancelled
earlier". The 03 MAP Contracts mentioned above relate to the works at
Bhatinda, Jabalpur and Secunderabad. The present tender pertains to the
balance work at Secunderabad.
3. It is the case of the respondent that since the petitioner did not
successfully complete the work at Secunderabad, it is ineligible to
participate in the subject tender, which is for the balance work left
unfinished by the petitioner.
4. The learned counsel for the respondent drew our attention to the
first proviso to Clause 60 (Arbitration) of the general conditions of
contract of the earlier contract. The said proviso reads as under:-
"Provided that in the event of abandonment of the works or cancellation of the Contract under Condition Nos. 46,47 and 48 hereof, such reference shall not take place until alternative arrangements have been finalised by the Government to get the works completed by or through any other Contractor or Contractors or Agency or Agencies."
5. In reference to the above provision, the learned counsel for the
respondent submitted that it was absolutely clear that if the work was
abandoned or cancelled under any of the Condition Nos. 46, 47 and 48,
the arbitration was not to take place unless and until alternative
arrangements had been finalized to get the works completed by or
through any other contractor or contractors or agency or agencies. It was,
therefore, submitted that the petitioner as well as the respondent were
well aware that in case the contract remains unfinished, the respondent
has the right to get it completed by someone else, other than the
petitioner. In this background, it was submitted that the petitioner could
not participate in the tender for the balance work, because the
understanding under the original contract was that the work would be
completed through some other contractor.
6. The learned counsel for the petitioner, however, submitted that
there is no disqualification of the petitioner in the current notice inviting
the qualification bid. He submitted that in an earlier round, when the very
same balance work was tendered on 20.12.2013, there was a specific
Clause (Clause 2.7), which enabled the respondents to disqualify a party
from participating in the tender, if that party had a record of negative
performance, such as abandoning the work or not completing the contract
etc. The learned counsel for the petitioner submitted that a clause similar
to Clause 2.7 in the earlier round was not included in the subject tender
and, therefore, it meant that the petitioner did not suffer from any
disqualification.
7. We have considered the arguments advanced by the counsel for the
parties and we find that the initial contract, that was awarded for the
Secunderabad Project to the petitioner, was left incomplete by the
petitioner. We are not going into the merits of that matter because that
would be the subject matter of arbitration. We are making it clear that we
have not expressed any opinion, as to whether the petitioner was in the
wrong or the respondent was in the wrong. The fact of the matter is that
the earlier contract clearly stipulated that if the same was cancelled or
abandoned under any of the condition Nos. 46, 47 and 48, the respondent
would have the right to get the works completed through some other
contractor.
8. This according to us, excluded the petitioner from being considered
for completing the balance work. The present tender is with regard to the
balance work. Therefore, it was well within the rights of the respondent
to reject the bid of the present petitioner on account of the fact that it is
with regard to the Secunderabad Project, which had been cancelled and it
was only the balance work, which was the subject matter of the present
tender.
9. In these circumstances, the writ petition does not have any merit,
the same is dismissed and the interim order is vacated. There shall be no
order as to costs.
BADAR DURREZ AHMED, J
FEBRUARY 24, 2015 SANJEEV SACHDEVA, J
n
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!