Citation : 2015 Latest Caselaw 1105 Del
Judgement Date : 6 February, 2015
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ WP(C) No.3047/2014
Decided on : 6th February, 2015
GMR CHHATTISGARH ENERGY LIMITED ..... Appellant
Through: Mr. Gopal Jain, Senior Advocate with
Ms. Padma Priya, Advocate.
versus
UNION OF INDIA & ORS. ..... Respondent
Through: Mr. Sanjay Jain, ASG with Mr. Malaya Kumar Chand and Ms.Rajul Jain, Advs.
for R-1/UOI.
Mr.Anil Soni, CGSC and Mr.Naginder Benipal, Adv. for R-2/Central Electricity Authority.
CORAM:
HON'BLE MR. JUSTICE V.K. SHALI
1. This is a writ petition filed by the petitioner against the
respondents for quashing the communication dated 19.06.2013 issued
by the Ministry of Railways to Central Electricity Authority ('CEA'
for short) as being totally arbitrary and violative of Article 14 of the
Constitution of India. It has been further prayed that directions be issued to the Railway Board for permitting the movement of imported
coal from Vizag port to the petitioner's plant via Tilda Station of SEC
Railway.
2. Briefly stated the fact of the case leading to the filing of the
present writ petition are that the petitioner had proposed to set up coal
based thermal power plant of 1370 MW (2 x 685 MW) at Village
Raikheda, Tilda Block, Raipur, Chattisgarh. The feasibility report was
submitted to the South Eastern Central Railway (hereinafter referred
to in short as 'SECR') which was approved in principle. However,
the plant could not be made operational on account of the fact that the
domestic coal linkage was not provided. Since there was a prolonged
delay in obtaining the immediate domestic long term coal linkage, the
petitioner proposed to use the imported coal from South Africa till the
time of obtaining the domestic coal linkage. The petitioner
accordingly signed a Memorandum of Understanding with South
African coal mines for supplying the requisite coal to the plant site till
the domestic coal linkage was obtained. The imported coal was
proposed to be moved from Vizag port via Titlagarh-Raipur railway
station to the plant site which was at a distance of 13 km from the Tilda station for the purpose of running thermal power plant.
Necessary approval was sought from the Chief Operations Manager,
SECR vide letter dated 29.03.2011. On 04.07.2011 the Railway
Transport Clearance (hereinafter referred to in short as 'RTC') was
issued to the petitioner by the Ministry of Railways for movement of
imported coal from Vizag to the plant siding at Tilda wherefrom it
was perhaps to be carried by road to the plant. In the said
communication, it was specifically assured to the petitioner that the
aforesaid RTC was valid for the full life of the project if
commissioned or for five years in case project is not commissioned.
On 13.10.2011, SEC Railway approved the detailed project report of
the petitioner categorically mentioning that the imported coal can be
moved via Tilda Station. The only requirement was that only 4.2 MT
of coal volume was to be imported and it was to come via Vizag port.
Based on the aforesaid assurance and the RTC, the petitioner
approached the Railway Board for issuance of instructions to the
concerned railways authorities on 25.01.2013 for undertaking the
movement of imported coal from Vizag port to the plant site.
3. On 28.02.2013, the Ministry of Railways replied to the petitioner that the imported coal to power houses in the country, as
per the logistics plan issued by the Railway Board, the power plants
in Chattisgarh State have been linked to Western Ports and the power
houses wanting to move imported coal from the port outside the
logistics plan, the approval of the CEA was required.
4. It may be pertinent to mention here that this was for the first
time after the grant of RTC by the respondent No.1 that said
respondent made a reference to the logistics plan of Railways for the
movement of coal to the power plants in Chattisgarh.
5. On 14.03.2013, the petitioner without prejudice to its rights
approached to Central Electricity Authority for its recommendation to
permit the movement of imported coal from Vishakhapatnam port to
the plant site. It was mentioned in the said representation dated
14.03.2013 by the petitioner to the Central Electricity Authority that
the implications of changing the import of coal from Viszag port to
any of the western ports, like Mundra Port, Dahej and Dharamtar
would not only result in increase of cost of production of electricity
which was assessed at between 380-600 crores, but it will bring an
additional burden of increased ocean freight of approximately INR 46 crores apart from the increase of distance from the port of import to
plant.
6. The CEA examined the request of the petitioner and
recommended to the Railway Board on 27.05.2013 permitting the
petitioner to move the imported coal from Vizag port to their power
plant from Tilda station. Thus, this approval by the CEA to the
proposal of the petitioner, which was not in line with the so called
logistics plan of the respondent No.1/Ministry of Railways,
tantamounted to approval of their plea that the change of port for
importing the coal from east to west would result in substantial
increase in the electricity tariff. Despite the aforesaid approval
having been granted by the CEA as well as the RTC having been
granted for the full life time of the project, the respondent No.1 vide
communication dated 19.06.2013 rejected the request of the petitioner
to carry the coal from Vizag port to Tilda.
7. The petitioner made representations on 14.11.2013 and
23.12.2013. However, nothing was heard from the respondents. On
21.03.2014, the petitioner went to the extent of making a request to
the respondent No.1 seeking permission to allow at least one rake per day for the purpose of commissioning of the plant so that it does not
suffer any financial loss on account of the delayed commissioning of
project. Since nothing was heard or done by the respondent No.1
favourable to the petitioner, they were constrained to file the present
writ petition challenging the communication of the respondent dated
19.06.2013.
8. The respondent/Ministry of Railways filed their reply affidavit
wherein it was stated by them that the permission of RTC was granted
to the petitioner subject to the logistics plan although the factum of
the logistics plan was not mentioned in the approval in principle
granted by the respondent No.1. It was the case of the respondent
No.1 that the RTC was granted in anticipation of doubling of TIG-
RSD section and since this could not be done, therefore, the petitioner
could not be permitted to carry the coal from vizag port. It was also
averred that the port location had to be changed due to the logistics
plan and all other thermal power plants in and around the area where
the petitioner's plant was set up were also being similarly treated for
the purpose of import of coal from the western ports and no special
treatment could be accorded to the petitioner.
9. It has been stated that all these factors clearly show that the
RTC was issued only as first stage clearance and could not be treated
as clearance having been granted by the respondent No.1 after due
deliberation once and for all, so as to enable it to force the petitioner
to import the coal only from eastern port.
10. Similarly, the respondent No.1 took the plea that the petitioner
is yet to complete the project of its siding at Tilda. Annual reports
had not been submitted which was a precondition to grant of RTC. It
was also averred that the decision to shift the port of import from east
to west was in public interest as all other power plants in Chattisgarh
area have been permitted to import the coal form western ports. Thus,
the petitioner did not deserve to be accorded any special treatment.
11. The petitioner in its rejoinder refuted the averments made by
the respondents in the counter affidavit contending that the RTC was
only a first time clearance in principle and that was subject to the
logistics plan. As a matter of fact, it was stated by the petitioner that
the clearance which was granted was without any reservation and was
valid for the entire life of the project and it was on the basis of these
assurances having been granted by the respondents that the petitioner invested huge amount of money for setting up not only the thermal
plant, but in erecting the siding at Tilda also.
12. It was averred by the petitioner that the petitioner's case could
not be equated with that of the cases of the other power plants on
account of the fact that in the case of the petitioner, a definite promise
was made on the basis of which it had altered its position and
therefore its case was distinguishable as compared to the cases where
the RTC was yet to be issued. So far as the applicability of the
logistics plan is concerned, it has been averred that the logistics plan
is referred to for the first time only after the permission in principle
had been granted and, therefore, after having granted the RTC without
any reservation, it was not open to the respondents to retrace their
steps so as to deny the benefit of the same to the petitioner.
13. It was also averred by the petitioner that the shifting of port of
import of coal from east to west is not subserving any public interest
inasmuch as not only the cost of power generation gets increased, but
the production of the thermal electricity becomes costelier and it was
no argument on the part of the respondent No.1 that the petitioner
remains unaffected by the said increase inasmuch as it could transfer the said additional burden to the end consumer. On the basis of the
aforesaid facts, the petitioner prayed for quashing of the letter dated
19.06.2013.
14. During the course of arguments, it transpired that the letter
dated 19.06.2013 of which quashing has been sought was actually
addressed to the CEA which in principle had given an approval for
import of the coal from Vizag port despite being at variance with the
logistics plan. Therefore, CEA was also impleaded as party. The
CEA in its reply has supported the case of the petitioner although they
did not file any formal reply, but in principle supported the stand of
the petitioner.
15. It may also be pertinent to mention that during the pendency of
the writ petition, the Ministry of Railways filed an additional affidavit
of one Sh. H.S.Bajwa, Director Traffic Transportation, Railway
Board praying to supplement the stand taken by them on the basis of
the logistics plan.
16. The oral submissions with regard to the RTC being a first time
clearance in principle which was ultimately to be subject to logistics plan of the Railways was sought to be enforced. Further the question
of short of capacity movement on the Vizag-Tilda Line was also
raised to wriggle out from their earlier stand. The aforesaid affidavit
was filed by the respondent No.1 without seeking permission of the
court and, therefore, was objected to by the learned senior counsel for
the petitioner.
17. The learned senior counsel for the petitioner had despite
objection in principle to the admissibility of the said additional
affidavit, had filed reply to the same and contended that the policy
governing the RTC was not new but was formulated on 09.12.2004
and it was contended that by granting permission or rather RTC, the
respondents were now trying to wriggle out of the same by giving
reasons which not only are not germane to the position and are also
extraneous and, therefore, cannot be taken into consideration.
18. On the basis of the aforesaid pleadings, the contention of
Mr.Gopal Jain, the learned senior counsel for the petitioner, has been
two-fold.
a) The first and foremost submission has been that the respondents
having chosen to give RTC to the petitioner on the basis of which the petitioner has invested not only considerable amount of money, but
has also erected railway siding, are now bound by the doctrine of
promissory estoppel and the respondents cannot after having
permitted the petitioner to change his position retrace their steps
unilaterally by deviating from the terms and conditions of the RTC.
In this regard, supplemental argument of the learned senior counsel
for the petitioner has been that the RTC was to remain valid and
subsisting for the entire life of the project and this was specifically
mentioned in the letter dated 04.07.2011 by virtue of which the RTC
was granted. It has been contended by the learned senior counsel that
at the time when the clearance was granted, admittedly, the logistics
plan was in position and therefore the respondents had granted the
RTC to the petitioner with their eyes open and in the teeth of the
existence of the logistics plan which now cannot be altered or
deviated from. It was also contended by him that even at the stage
when the petitioner was required to transport coal from Vizag to the
Tilda, the respondent did not talk about these impediments for the
transportation but rather referred the petitioner to the CEA for the
purpose of approval as a pre-condition for transporting the coal from Vizag to Tilda. It is contended that even this requirement was
complied with by the petitioner inasmuch as not only the approval
was granted by the CEA but they had also taken note of the fact that
the shifting of the port from east to west as envisaged in the logistics
plan would result in considerable enhancement of valuation of the
project. It has been contended by him that the contention of the
learned ASG that the petitioner can offload the extra burden to the
customer is not in public interest and therefore this cannot be
permitted to be done.
b) The learned senior counsel for the petitioner has also placed
reliance on the judgments of the Supreme Court in i) SVA Steel Re-
rolling Mills Ltd. Vs.State of Kerala & Ors. in Civil Appeal
Nos.10103-10106 of 2010 decided on 06.02.2014; ii) State of Bihar
& Ors. v. Kalyanpur Cement Ltd.; (2010 3 SCC 274 and iii)
Mohinder Singh Gill v. Chief Election Commissioner; (1978) 1 SCC
405.
19. So far as the respondents are concerned, the learned ASG has
tried to put stress essentially on the aspect of logistics plan and
contended that at the time of when the RTC was granted, the said clearance was granted only in principle for the purpose of setting up
of siding at Tilda and it had to be read as subject to the logistics plan
and the plan envisaged doubling of the railway track from Vizag to
Tilda which could not be done for various reasons. Therefore the
movement of the goods including import of coal from Vizag port to
the Tilda could not be carried out smoothly and in an orderly manner
and the port of import had to be diverted to west coast. It has also
been contended that the petitioner is not being discriminated on that
score because all other thermal power plants set up in and around the
plant of the petitioner were being permitted to import coal only from
the west coast only and, therefore, the petitioner cannot raise the plea
of arbitrariness and discrimination under Article 14 of the
Constitution of India. It was also contended that so far as the
enhancement of the cost of generation of power is concerned, that was
not an impediment because it is ultimately to be borne by the
customer and therefore, this argument of the petitioner does not have
any merit.
20. It has also been contended that the decisions which have been
taken by the respondents are in the public interest and they have not been taken with a view to penalize the petitioner.
21. I have considered the submissions made by the learned senior
counsel for the petitioner as well as of the learned ASG and have also
gone through the record.
22. Before dealing with the submissions urged by the learned
senior counsel for the petitioner, it may be pertinent to refer to the
doctrine of estoppel.
'Estoppel' is a rule of equity to prevent a person from taking advantage of a condition or situation when, with knowledge of the facts, he has so conducted himself as to lead the other party to believe that he would not do as he did. It is thus an appeal to conscience of court and ordinarily involves some element of wrongdoing on the part of the person sought to be estopped which would render it inequitable to permit him to take advantage of his prior conduct.
The doctrine of promissory or equitable estoppels is well established in Administrative Law and in Constitutional Law. It represents a principle evolved by equity to avoid injustice. Explaining the principle, Wade (Administrative Law {9th Edition}) states: "The basic principle of estoppels is that a person who by some statement or representation of fact causes another to act to his detriment in reliance on the truth of it is not allowed to deny it later, even though it is wrong. Justice here prevails over truth."
"Estoppel is a rule of equity flowing out of fairness striking on behavious deficient in good faith. It operates as a check on spurious conduct by preventing the inducer from taking advantage and assailing forfeiture already accomplished. It is invoked and applied to aid the law in administration of justice. But for it great many injustices may have been perpetrated. (Indira Bai v. Nand Kishore;
(1990) 4 SCC 668, 670"
23. A perusal of the aforesaid doctrine would show that the
doctrine of promissory estoppel is a doctrine which has been invoked
by the Courts in a number of cases where a party on the basis of a
representation of the other side has changed his position and incurred
liabilities. The said doctrine is invariably permitted to be invoked
when a party in case is not protected by the said doctrine would
seriously be prejudiced and subjected to great injustice.
24. In the present case also, there is dispute about the fact that the
petitioner had got approved his proposal for setting up of a thermal
plant of 1370 MW (2 x 685 MW) at Village Raikheda, District
Raipur, Chhattisgarh near Tilda Station. According to the petitioner,
it had invested almost Rs.8,000 crores in not only setting up the plant,
but also a siding at Tilda-Bilaspur Section for the purpose of
offloading the imported coal for which it had entered into a Memorandum of Settlement for supply of coal for running the power
plant successfully and generating electricity. This coal was sought to
be imported by the petitioner from Vizag port which was the nearest
port to the project site. The necessity for importing the coal arose on
account of the fact there was a shortage of domestic coal linkage for
running the thermal plant. Accordingly, keeping all these parameters
in view, the petitioner had applied with the respondent No.1/Ministry
of Railways seeking RTC for carrying the coal from Vizag port to the
Tilda i.e. up to their siding and thereafter to be transported by road at
a distance of 12-13 kms at which the project site was situated. This
permission was granted by the respondent No.1 vide letter dated
04.07.2011 subject only to the condition that the project ought to have
been commissioned or if it was not commissioned, then it had to be
done necessarily within a period of five years from the date of grant
of permission.
25. It is not the case of the petitioner or that of even the
respondents that at the time when the permission was granted the
plant was functioning. The plant was yet to be commissioned,
therefore, it had a period of five years within which the plant had to be commissioned. It may also be pertinent here to mention that the
aforesaid permission which was granted by the respondent No.1 was
without any reservation or reference to the fact that it was subject to
the logistics plan or any other condition which will empower it to
review the decision.
26. On the contrary, the respondents had specifically assured the
petitioner that the aforesaid RTC was granted to them for the life of
the project itself. That being the position, the respondent No.1 could
not be permitted to contend now that this permission which was
granted to the petitioner on 04.07.2011 was subject to the condition of
logistics plan and the logistics plan envisaged two things : i) the
permission which was granted to the petitioner was only to be treated
as a permission in principle and was subject to the condition that the
respondent No.1 was anticipating to double the railway line from
Vizag to Tilda which would have resulted in increased movement of
the goods from point of start to the point of termination. Such a
condition does not find mention in the letter of approval granted by
the respondent No.1 in favour of the petitioner.
27. Similarly, at the time when the permission was granted by the respondent No.1 to the petitioner, the logistics plan was already in
existence but there was not even an iota of mention with respect to the
same the letter dated 04.07.2011 granting RTC to the petitioner that
the said RTC is to be treated as subject to the logistics plan.
Therefore, the respondents cannot plead now that the logistics plan
being a part of the RTC to wriggle out of their commitment of
permitting the petitioner to transport the imported coal from Vizag
port (rail head) to Tilda (their siding) and from Tilda Station to the
project site. If this stand of the respondent No.1 is upheld then not
only it will be against the doctrine of promissory estoppel but it will
not attach any seriousness or finality to the decision of the
respondents. Such a casual approach of the respondents will have
disastrous effect on the project and its founder.
28. It is no argument on the part of the respondent No.1 that they
had convened a meeting of all the stake holders namely the CEA or
NTPC or the concerned railway authorities and arrived at a
conclusion that all the imported coal which is to be utilized by the
existing or prospective thermal plants set up in the Chattisgarh region
should be supplied through western port.
29. The contention of the learned ASG was that there was no
discrimination between the petitioner and the other plant holders is
totally bereft of any logic. The reason for this is that so far as the
petitioner is concerned, its case is based on the doctrine of promissory
estoppel. In the case of the petitioner, RTC has already been issued
while as in the case of others, there is no RTC having been issued by
the respondent No.1. Therefore, the petitioner's case cannot be
equated with that of other plant holders who are yet to be granted
RTC on the same lines on which the RTC has been granted to the
petitioner. Therefore, the plea of non-discrimination does not hold
any water. On the contrary, the actions of the respondents clearly
show an arbitrariness in changing their decision.
30. On the contrary, the respondent No.1 when approached by the
petitioner seeking permission to transport the imported coal from
Vizag port to their siding at Tilda, they were asked to obtain the
approval of the CEA. The CEA is a specialized body which is having
expertise of going into the question of resources and the raw material
and advise the Ministry of Railways after examining the proposal of
the parties as to whether the proposal given by a particular plant holder is feasible or not. Even at this stage, when respondent No.1
was approached by the petitioner for the purpose of grant of
permission to carry their imported coal from Vizag to Tilda, the
respondent No.1 did not find it fit to raise the question of logistics
plan.
31. The petitioner approached the CEA, gave the requisite
information and also brought to the notice of the CEA that in case
their port of import is shifted from east to west then, not only the
distance between Vizag port and the ports to which they are likely to
be shifted on the west coast of the country would be almost doubled,
but it would also entail additional expenditure to the tune of Rs.380-
600 crores apart from the increase in the freight charges to the tune of
Rs.86 crores. The CEA after receipt of the proposal had also
approved the transportation of the imported coal from Vizag port to
the Tilda and accordingly granted the necessary approval.
32. Once the CEA had recommended the case of the petitioner for
import of coal form Vizag port to Tilda that should have been the end
of the matter and the respondents ought not to have raised any query
or rejected the proposal. But the respondents still took the stand that they are to go according to the logistics plan.
33. Thus action of the respondent No.1 is arbitrary, bereft of any
logic or reasoning and seems to be actuated by ulterior motives that
despite the petitioner having been referred to CEA for the purpose of
obtaining the approval and the letter in this regard having been
obtained, yet the respondent No.1 was trying to wriggle out of the
same by taking flimsy pretexts. One of the flimsy pretexts which was
taken for the purpose of wriggling out of the assurance given by them
was that the additional burden which the petitioner bears will
eventually have to be borne by the consumer and therefore, no serious
prejudice would be caused to the petitioner even if the imported coal
is permitted to be routed through the western port.
34. This argument of the respondent No.1 that the ultimate burden
is to be borne by the customer is not only highly unreasonable but
also illogical. This is on account of the fact that any action of a
Government body must be initiated keeping in mind the larger public
interest. The respondent No.1 has taken the plea that their action of
shifting the port of import from east to west was actuated by
subserving the public interest. But I find that instead of serving the public interest, the very action of the respondent No.1 is anti public
inasmuch as it will result not only in enhancement of cost of
production of electricity, but will also result in causing great deal of
inconvenience and loss of resources to the petitioner. This cannot be
permitted to be done at the whims and fancies of the respondent No1.
35. One of the arguments which has been raised by the respondent
No.1 is that the permission which was granted to the petitioner and
which was valid for a period of five years was subject to the condition
that they were to submit the annual reports. It has been alleged by
them that the petitioner did not submit its annual reports. This aspect
has been contested by the petitioner by contending that this is
factually incorrect. They had submitted the reports on 01.07.2012,
25.06.2013 & 24.07.2014. The details in this regard have not only
been averred in the rejoinder affidavit but also copies of the same
have been placed on record as Annexure P-1 to P-6. This contention
of the respondent No.1 that the non submission of annual report also
was a ground to be taken into consideration for non granting them the
benefit of the letter dated 04.07.2011 is untenable in law.
36. Last but not the least, the respondent No.1 has taken a plea that they have taken a plea that they have filed an additional affidavit and
in the additional affidavit they have tried to supplement the denial of
import of coal from Vizag port by giving additional reasons which
have been amplified in the said additional affidavit. The additional
reasons given by the respondent No.1 in the additional affidavit
cannot be taken cognizance of on account of two reasons.
37. Firstly, this additional affidavit has been filed by the petitioner
without obtaining the permission of the court or without any direction
from the court. The pleadings in a writ petition essentially consist of
averments made in the petition by way of an affidavit, the counter
affidavit/reply affidavit filed by the respondent and the rejoinder
thereto filed by the petitioner. In the instant case, all these processes
were completed yet the respondent No.1 of their own without any
rhyme or reason and without obtaining any permission of the court,
chose to file the additional affidavit. In the additional affidavit, they
have tried to give the reasons as to why the port of import has been
shifted from east to west and as to how it does not impact the
decisions taken by them which was communicated to the petitioner
vide letter dated 04.07.2011. The court does not find it necessary to go into the finer details of the averments made in the additional
affidavit for the simple reason that this was not done on the direction
of the court. Even if it is taken into consideration, what is essentially
to be seen is the decision taken by the respondent No.1 vide letter
dated 19.06.2013 sent by them to the CEA which does not give the
reasons as to why they have shifted the port of import of coal from
east to west. The reasons for the same cannot be supplied by way of
an affidavit. It ought to be evident in the letter itself.
38. The learned senior counsel for the petitioner has relied upon the
judgment of Mohinder Singh Gill V. Chief Election Commissiner;
(1978) 1 SCC 405 and has contended that the action of a party has to
be adjudged on the basis of the reasons provided in the order itself
and not by the supplementary reasons in the shape of an affidavit.
This judgment squarely fits in with the facts of the present case. In the
instant case, the impugned order dated 19.06.2013 by virtue of which
the port of import has been shifted from east to west and
communicated to the CEA, does not have any basis whatsoever as it
does not give any reasons why this has been done. Therefore, in my
view, the judgment in Mohinder Singh Gill's case, the letter dated 19.06.2013 cannot be relied upon as a reasoned order passed by the
respondent No.1.
39. In totality of circumstances, I feel that the action of the
respondent No.1 in issuing the letter dated 19.06.2013 to the CEA
shifting the port of import from Vizag to western port is totally
arbitrary, discriminatory, illegal and without any basis whatsoever
and accordingly the said letter is quashed and a writ of mandamus is
issued to the respondent No.1 to permit the petitioner to import coal
from Vizag port up to Tilda station as envisaged in the letter dated
04.07.2011. Further, the respondents are bound by the doctrine of
promissory estoppel. Accordingly, the writ is allowed in terms of the
prayer.
V.K. SHALI, J FEBRUARY 06, 2015/dm
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!