Citation : 2015 Latest Caselaw 3416 Del
Judgement Date : 28 April, 2015
IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of decision: April 28, 2015
+ ARB. PET. 79/2015
SOMA ENTERPRISES LIMITED ..... Petitioner
Through: Mr.Sushant Kumar, Advocate
versus
NATIONAL THERMAL POWER CORPORATION ..... Respondent
Through: Mr.Puneet Taneja, Advocate
CORAM:
HON'BLE MR. JUSTICE V.KAMESWAR RAO
V.KAMESWAR RAO, J. (Oral)
1. This petition has been filed by the petitioner under Section 11(6) of
the Arbitration and Conciliation Act, 1996 („Act‟ for short) for
appointment of an Arbitrator.
2. It is the case of the petitioner that the respondent while setting up
its super thermal power plant at Sipat, District Bilaspur in the State of
Chattisgarh had invited tenders for the work of Raw Water Reservoir and
lining package as per its bidding document No.CS-9518-319A-9.
3. The petitioner, who had also submitted its bid, was awarded the
contract vide letter dated December 8, 2004. A contract agreement dated
February 3, 2005 was executed between the petitioner and the
respondent. It is the case of the petitioner that the contract agreement
was completed on March 7, 2007 within the extended time duly agreed
upon by both the parties. It is also averred that the petitioner submitted a
final bill and made certain claims for additional payment. No payment
has been made till date. On failure to clear the final bill the petitioner
with no option left invoked the arbitration clause as contained in Clause
56 of the GCC vide its letter dated July 26, 2014, in response thereof, the
respondent vide its letter dated August 18, 2014 refused to appoint an
Arbitrator, inter alia, stating that the invocation of arbitration clause for
any dispute, was not acceptable to it. The petitioner vide letter dated
September 8, 2014, reiterated its stand that disputes have arisen and
sought appointment of Arbitrator under clause 56 GCC. A copy of the
letter was marked to General Manager, Sipat, Super Thermal Power
Project and to Chairman and Director, NTPC Ltd.
4. The present petition was filed on February 4, 2015.
5. On notice the respondent filed its reply. It is the stand of the
respondent that the petitioner has signed the final bill in May 2012
without raising any dispute.
6. The additional claims made have been denied. The respondent has
given reply on the merits of the dispute between the parties. For the
purpose of this application, it may not be necessary for this Court to go
into the same.
7. On the plea of the petitioner regarding appointment of the
Arbitrator, the respondent‟s case is that at no point of time did the
petitioner invoke arbitration in terms of clause 56 of GCC. This is so,
because at no point of time, the petitioner approached the General
Manager of the project for entering reference for adjudicating the
disputes and claims raised by it. This, as per the respondent is evident
from the letter dated July 26, 2014 which was a letter addressed to
Project Incharge who is the Executive Director of Sipat Super Thermal
Power Project and not the General Manager of the Project. Since the
letter was merely a communication to the Executive Director of the
Project, the same was replied by the concerned officer on behalf of the
respondent by virtue of letter dated August 18, 2014. According to the
respondent the word "General Manager" having been replaced by the
words "Project Incharge of the Project.", it was realised that it was not
the General Manager of the Sipat Super Thermal Power Project who was
to arbitrate the disputes as the Sole Arbitrator but the officer with
designation of the Executive Director of the SSTPP who was to Arbitrate
being the Project Incharge of the SSTPP.
8. The respondent would submit, it did not consider the letter dated
July 26, 2014 of the petitioner as a letter invoking Clause 56 of the GCC.
It was later the respondent realised about the amendment to Clause 56 of
the GCC and further appreciated that the letter dated July 26, 2014
addressed to the Project Incharge, SSTPP was an invocation of an
arbitration. The said facts were apprised to the Project Incharge, i.e., the
Executive Director of SSTPP, i.e., Mr.V.B. Fadnavis who immediately
thereupon entered reference on February 12, 2015 and issued order dated
February 19, 2015 thereby calling upon the parties to appear before him
in his capacity as the Sole Arbitrator.
9. It is also the stand of the respondent even assuming that the letter
dated August 18, 2014 of the respondent can be construed as a refusal by
the Executive Director to act as the Sole Arbitrator but the said refusal
was withdrawn by him before the petitioner had exhausted the procedure
as prescribed under Clause 56 of GCC which provides for an
appointment of Sole Arbitrator by the CMD of NTPC in case the Sole
Arbitrator refuses or does not enter the reference.
10. I may point out here, the petitioner received the letter dated
February 19, 2015 from Mr.V.B. Fadnavis on February 23, 2015. A
response to the said letter was given by the petitioner vide its letter dated
February 24, 2015 wherein the petitioner had informed the respondent
about the filing of the petition in this Court and calling upon the
respondent to withdraw the communication dated February 19, 2015.
11. Mr.Sushant Kumar, learned counsel for the petitioner would
submit that the petitioner having invoked clause 56 of the GCC vide
letter dated July 26, 2014 and the Project Incharge having not responded
to the invocation by entering into the reference and the subsequent letter
of the petitioner dated September 8, 2014, a copy of which was sent to
the Chairman and Managing Director of NTPC to take necessary action
and even his failure to appoint an Arbitrator in place of the Project
Incharge, the respondent has forfeited its right to appoint an Arbitrator
and accordingly the petition under Section 11(6) of the Act seeking an
appointment of an Arbitrator by this Court has been filed. In this regard,
he would rely upon the judgment of the Supreme Court in the case
reported as (2013) 4 SCC 35, Deep Trading Company Vs. Indian Oil
Corporation and Ors. to contend that if no appointment is made till the
contractor has made an application under Section 11(6) of the Act, the
employer forfeits its right to appoint, on similar lines in terms of the law
laid down by the Supreme Court in Datar Switchgears Vs. Tata Finance
Ltd., ( 2000) 8 SCC 158. He would also rely upon the judgment of this
Court in the case of R.S.Avtar Singh and Co. Vs. Indian Tourism
Development Corporation Ltd., AIR 2003 Delhi 249 to contend that the
order of appointment would be taken to have been made when the order
is communicated and received by the Arbitrator and concerned party.
12. On the other hand, Mr.Puneet Taneja, learned counsel appearing
for the respondent would reiterate the stand taken by the respondent in its
reply. According to him, clause 56 of GCC postulates the Project
Incharge i.e. Sipat Super Thermal Power Project to be the named
Arbitrator. On invocation of the arbitration by the other party, the Project
Incharge being an Arbitrator has only to enter the reference. He states
that there was a misreading of the provision and because of which, the
letter dated July 26, 2014 which was addressed to the Project Incharge,
and not the General Manager, was construed as a normal communication
and not a communication seeking invocation, accordingly the Executive
Director did not enter the reference. Having realised the effect of the
amendment, Mr.Fadnavis has accordingly entered the reference.
Alternatively, he would plead, if the Executive Director, the Project
Incharge failed to act as an Arbitrator, the petitioner should have
approached the Chairman and Managing Director of the respondent
corporation seeking the appointment of another person as an Arbitrator.
He would state, that the letter dated September 8, 2014 is not a
communication addressed to the Chairman and Managing Director,
NTPC Ltd., as was contended by the learned counsel for the petitioner.
He would state, that, the latter part of clause 56 of GCC having not been
invoked by the petitioner, and in the interregnum the Project Incharge
having entered the reference, the issuance of letter dated February 19,
2014 which is a communication by the Sole Arbitrator giving notice to
the parties to appear before him is justified. He would rely upon a
judgment of this Court in the case of M/s. Gangotri Enterprises Ltd.
Vs.M/s. NTPC, Arb.P. 270/2013, decided on January 21, 2014, wherein,
this Court had upheld the reference entered by the General Manager on
identical facts.
13. Having heard the learned counsel for the parties, the only issue
which arises for my consideration, is in the facts of this case, whether an
Arbitrator need to be appointed by this Court in exercise of power under
Section 11(6) of the Act or the reference entered upon by Mr.V.B.
Fadnavis need to be upheld. Before I answer the question, I reproduce
hereunder clause 56 of the GCC:
"56. Except where otherwise provided for in the contract all questions and disputes relating to the meaning of the specifications, designs, drawings and instructions herein before mentioned and as to the quality of workmanship or materials used on the work or as to any other question, claim, right, matter or thing whatsoever in any way arising out of or relating to the contract, designs, drawings, specifications, estimates, instructions, orders or these conditions of otherwise concerning the works, or 1the
execution or failure to execute the same whether arising during the progress of the work or after the completion of abandonment thereof shall be referred to the sole arbitration of the General Manager of NTPC Limited {Formerly National Thermal Power Corporation Ltd.}, and If the General Manager is unable or unwilling to act, to the sole arbitration of some other person appointed by the Chairman and Managing Director, NTPC Limited (Formerly National Thermal Power Corporation Ltd}, willing to act as such arbitrator. There will be no objection if the arbitrator so appointed is an employee of NTPC Limited (Formerly National Thermal Power Corporation Ltd) and that he had to deal with the matters to which the contract relates and that in the course of his duties as such he had expressed views on all or any of the matters in dispute or difference. The arbitrator to whom the matter is originally referred being transferred or vacating his office or being unable to act for any reason as aforesaid at the time of such transfer, vacation of office or inability to act, Chairman and Managing Director, NTPC Limited (Formerly National Thermal Power Corporation Ltd}, shall appoint another person to act as arbitrator in accordance with the terms of the contract. It is also a term of this contract that no person other than a person appointed by CMD, NTPC Ltd as aforesaid should act as arbitrator and if for any reason, that is not possible, the matter is not to be referred to arbitration at all."
14. A perusal of the clause 56 of GCC as originally enacted, would
reveal that the General Manager of NTPC Ltd. would act as a Sole
Arbitrator and in the eventuality, the General Manager is unable or
unwilling to act as the Sole Arbitrator, some other person appointed by
the Chairman and Managing Director, NTPC Ltd. will act as an
Arbitrator. The amendment effected to this provision as is clear from the
document at page 34 of the reply, the word "General Manager" has been
replaced by the words "Project Incharge of the Project Concern of
National Thermal Power Corporation Ltd." If clause 56 is read from the
perspective of the amendment, it is clear that the Project Incharge, which
in this case, is the Executive Director need to act as Arbitrator at the first
instance. It appears from the stand, which has been taken by the
respondent of a misreading of the provision with a belief that it is the
General Manager, who was to act as an Arbitrator, need to be accepted as
the petitioner has not controverted the stand of the respondent in the reply
by filing a rejoinder. Even otherwise, the letter dated September 8, 2014,
in no way, can be construed as a letter written to the Chairman and
Managing Director of the respondent corporation to appoint another
person on failure of the Project Incharge to act as an Arbitrator. This I
say so, the letter dated September 8, 2014 was addressed to the AGM
(Civil), Sipat, and not to the Chairman and Managing Director. That
apart, mere sending a copy of the letter to the Chairman and Managing
Director for taking necessary action, cannot be construed as a
communication, calling upon the Chairman and Managing Director to
appoint another person in lieu of the Project Incharge. No such express
request was made. Rather, I find, from the reading of letter dated
September 8, 2014 was a reiteration of the contents of the earlier letter
dated July 26, 2014 relating to invocation of the arbitration in terms of
clause 56 of GCC for settling the claims, which is clear from the request
made by the petitioner in the said letter, which I quote:
"We request you to take immediate steps as per the
provision of clause 56 of GCC".
I agree with the submission of the learned counsel for the respondent that
the petitioner had never invoked the later part of clause 56 of GCC
calling upon the Chairman and Managing Director to appoint another
person in lieu of the Project Incharge till the filing of the petition and in
fact till date. The Project Incharge having entered the reference and
having issued letter dated February 19, 2015, it cannot be said that there
was a failure to invoke clause 56 of GCC. The issuance of letter dated
February 19, 2015 is justified. I note, for benefit the following conclusion
of this Court in the case of M/s. Gangotri Enterprises Ltd. (supra):
"9. Having heard learned counsels for the parties and perused the arbitration clause, aforesaid, I am of the view that after the invocation of the arbitration agreement, if the petitioner was aggrieved on account of inaction of the GM to enter upon the reference within 30 days of the said invocation, it was for the petitioner to inform the CMD of the same and to seek appointment of an arbitrator. Once the arbitration agreement is invoked, it is not necessary for the named arbitrator to act within 30 days of the said invocation. He may act even thereafter and if he so acts, he would have jurisdiction. However, if he does not act within 30 days, and before he acts and enters upon reference, one of the parties either approaches the court or triggers the mechanism for appointment of an arbitrator as provided in the contract, the named arbitrator may lose his authority/mandate to act as an arbitrator and enter upon reference, as held by the Supreme Court in the case of Datar Switchgears Ltd. v. Tata Finance, (2000) 8 SCC 151.
10. In the present case, the petitioner never gave an opportunity to the CMD to appoint the arbitrator, if, according to the petitioner, the GM was unable, unwilling or failed to act. The CMD may not even have been aware of the invocation of the arbitration agreement by the petitioner, since the same was not addressed to him. He may, therefore, not even be
aware of the fact that the GM has either expressed his inability, or unwillingness, to act or that he has failed to act. Even otherwise, merely because the named arbitrator, namely, the GM did not act within 30 days, cannot lead to the conclusion that he has expressed his inability or unwillingness to act in the matter as an arbitrator.
11. Therefore, the filing of the present petition appears to be misconceived, since the petitioner has not invoked the arbitration agreement in its terms by approaching the CMD to appoint the arbitrator. Even before the CMD has been called upon to appoint an arbitrator, the GM has already entered upon reference on 18.07.2013. Therefore, in my view, the GM has the mandate to proceed with the arbitration in the present case. Accordingly, this petition does not survive and the same is dismissed as such".
15. In view of the aforesaid position, the reliance placed by the learned
counsel for the petitioner in the case of Deep Trading Co. (supra) is
untenable and would have no applicability. Insofar as R.S.Avtar Singh
Co. case (supra) is concerned, in view of peculiarity of clause 56 of the
GCC, which postulates a named Arbitrator, who has to enter the
reference pursuant to the invocation of arbitration by the other party, the
said judgment also has no applicability.
16. In view of my above discussion, I do not see any merit in the
present petition. The same is accordingly dismissed. The parties would
be at liberty to raise all their claims and counter claims and objections
before the learned Sole Arbitrator.
(V.KAMESWAR RAO) JUDGE APRIL 28, 2015 akb
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!