Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Soma Enterprises Limited vs National Thermal Power ...
2015 Latest Caselaw 3416 Del

Citation : 2015 Latest Caselaw 3416 Del
Judgement Date : 28 April, 2015

Delhi High Court
Soma Enterprises Limited vs National Thermal Power ... on 28 April, 2015
        IN THE HIGH COURT OF DELHI AT NEW DELHI

                                            Date of decision: April 28, 2015

+                          ARB. PET. 79/2015

SOMA ENTERPRISES LIMITED                                   ..... Petitioner

                     Through:       Mr.Sushant Kumar, Advocate

                           versus

NATIONAL THERMAL POWER CORPORATION ..... Respondent

                     Through:       Mr.Puneet Taneja, Advocate

CORAM:
HON'BLE MR. JUSTICE V.KAMESWAR RAO

V.KAMESWAR RAO, J. (Oral)

1. This petition has been filed by the petitioner under Section 11(6) of

the Arbitration and Conciliation Act, 1996 („Act‟ for short) for

appointment of an Arbitrator.

2. It is the case of the petitioner that the respondent while setting up

its super thermal power plant at Sipat, District Bilaspur in the State of

Chattisgarh had invited tenders for the work of Raw Water Reservoir and

lining package as per its bidding document No.CS-9518-319A-9.

3. The petitioner, who had also submitted its bid, was awarded the

contract vide letter dated December 8, 2004. A contract agreement dated

February 3, 2005 was executed between the petitioner and the

respondent. It is the case of the petitioner that the contract agreement

was completed on March 7, 2007 within the extended time duly agreed

upon by both the parties. It is also averred that the petitioner submitted a

final bill and made certain claims for additional payment. No payment

has been made till date. On failure to clear the final bill the petitioner

with no option left invoked the arbitration clause as contained in Clause

56 of the GCC vide its letter dated July 26, 2014, in response thereof, the

respondent vide its letter dated August 18, 2014 refused to appoint an

Arbitrator, inter alia, stating that the invocation of arbitration clause for

any dispute, was not acceptable to it. The petitioner vide letter dated

September 8, 2014, reiterated its stand that disputes have arisen and

sought appointment of Arbitrator under clause 56 GCC. A copy of the

letter was marked to General Manager, Sipat, Super Thermal Power

Project and to Chairman and Director, NTPC Ltd.

4. The present petition was filed on February 4, 2015.

5. On notice the respondent filed its reply. It is the stand of the

respondent that the petitioner has signed the final bill in May 2012

without raising any dispute.

6. The additional claims made have been denied. The respondent has

given reply on the merits of the dispute between the parties. For the

purpose of this application, it may not be necessary for this Court to go

into the same.

7. On the plea of the petitioner regarding appointment of the

Arbitrator, the respondent‟s case is that at no point of time did the

petitioner invoke arbitration in terms of clause 56 of GCC. This is so,

because at no point of time, the petitioner approached the General

Manager of the project for entering reference for adjudicating the

disputes and claims raised by it. This, as per the respondent is evident

from the letter dated July 26, 2014 which was a letter addressed to

Project Incharge who is the Executive Director of Sipat Super Thermal

Power Project and not the General Manager of the Project. Since the

letter was merely a communication to the Executive Director of the

Project, the same was replied by the concerned officer on behalf of the

respondent by virtue of letter dated August 18, 2014. According to the

respondent the word "General Manager" having been replaced by the

words "Project Incharge of the Project.", it was realised that it was not

the General Manager of the Sipat Super Thermal Power Project who was

to arbitrate the disputes as the Sole Arbitrator but the officer with

designation of the Executive Director of the SSTPP who was to Arbitrate

being the Project Incharge of the SSTPP.

8. The respondent would submit, it did not consider the letter dated

July 26, 2014 of the petitioner as a letter invoking Clause 56 of the GCC.

It was later the respondent realised about the amendment to Clause 56 of

the GCC and further appreciated that the letter dated July 26, 2014

addressed to the Project Incharge, SSTPP was an invocation of an

arbitration. The said facts were apprised to the Project Incharge, i.e., the

Executive Director of SSTPP, i.e., Mr.V.B. Fadnavis who immediately

thereupon entered reference on February 12, 2015 and issued order dated

February 19, 2015 thereby calling upon the parties to appear before him

in his capacity as the Sole Arbitrator.

9. It is also the stand of the respondent even assuming that the letter

dated August 18, 2014 of the respondent can be construed as a refusal by

the Executive Director to act as the Sole Arbitrator but the said refusal

was withdrawn by him before the petitioner had exhausted the procedure

as prescribed under Clause 56 of GCC which provides for an

appointment of Sole Arbitrator by the CMD of NTPC in case the Sole

Arbitrator refuses or does not enter the reference.

10. I may point out here, the petitioner received the letter dated

February 19, 2015 from Mr.V.B. Fadnavis on February 23, 2015. A

response to the said letter was given by the petitioner vide its letter dated

February 24, 2015 wherein the petitioner had informed the respondent

about the filing of the petition in this Court and calling upon the

respondent to withdraw the communication dated February 19, 2015.

11. Mr.Sushant Kumar, learned counsel for the petitioner would

submit that the petitioner having invoked clause 56 of the GCC vide

letter dated July 26, 2014 and the Project Incharge having not responded

to the invocation by entering into the reference and the subsequent letter

of the petitioner dated September 8, 2014, a copy of which was sent to

the Chairman and Managing Director of NTPC to take necessary action

and even his failure to appoint an Arbitrator in place of the Project

Incharge, the respondent has forfeited its right to appoint an Arbitrator

and accordingly the petition under Section 11(6) of the Act seeking an

appointment of an Arbitrator by this Court has been filed. In this regard,

he would rely upon the judgment of the Supreme Court in the case

reported as (2013) 4 SCC 35, Deep Trading Company Vs. Indian Oil

Corporation and Ors. to contend that if no appointment is made till the

contractor has made an application under Section 11(6) of the Act, the

employer forfeits its right to appoint, on similar lines in terms of the law

laid down by the Supreme Court in Datar Switchgears Vs. Tata Finance

Ltd., ( 2000) 8 SCC 158. He would also rely upon the judgment of this

Court in the case of R.S.Avtar Singh and Co. Vs. Indian Tourism

Development Corporation Ltd., AIR 2003 Delhi 249 to contend that the

order of appointment would be taken to have been made when the order

is communicated and received by the Arbitrator and concerned party.

12. On the other hand, Mr.Puneet Taneja, learned counsel appearing

for the respondent would reiterate the stand taken by the respondent in its

reply. According to him, clause 56 of GCC postulates the Project

Incharge i.e. Sipat Super Thermal Power Project to be the named

Arbitrator. On invocation of the arbitration by the other party, the Project

Incharge being an Arbitrator has only to enter the reference. He states

that there was a misreading of the provision and because of which, the

letter dated July 26, 2014 which was addressed to the Project Incharge,

and not the General Manager, was construed as a normal communication

and not a communication seeking invocation, accordingly the Executive

Director did not enter the reference. Having realised the effect of the

amendment, Mr.Fadnavis has accordingly entered the reference.

Alternatively, he would plead, if the Executive Director, the Project

Incharge failed to act as an Arbitrator, the petitioner should have

approached the Chairman and Managing Director of the respondent

corporation seeking the appointment of another person as an Arbitrator.

He would state, that the letter dated September 8, 2014 is not a

communication addressed to the Chairman and Managing Director,

NTPC Ltd., as was contended by the learned counsel for the petitioner.

He would state, that, the latter part of clause 56 of GCC having not been

invoked by the petitioner, and in the interregnum the Project Incharge

having entered the reference, the issuance of letter dated February 19,

2014 which is a communication by the Sole Arbitrator giving notice to

the parties to appear before him is justified. He would rely upon a

judgment of this Court in the case of M/s. Gangotri Enterprises Ltd.

Vs.M/s. NTPC, Arb.P. 270/2013, decided on January 21, 2014, wherein,

this Court had upheld the reference entered by the General Manager on

identical facts.

13. Having heard the learned counsel for the parties, the only issue

which arises for my consideration, is in the facts of this case, whether an

Arbitrator need to be appointed by this Court in exercise of power under

Section 11(6) of the Act or the reference entered upon by Mr.V.B.

Fadnavis need to be upheld. Before I answer the question, I reproduce

hereunder clause 56 of the GCC:

"56. Except where otherwise provided for in the contract all questions and disputes relating to the meaning of the specifications, designs, drawings and instructions herein before mentioned and as to the quality of workmanship or materials used on the work or as to any other question, claim, right, matter or thing whatsoever in any way arising out of or relating to the contract, designs, drawings, specifications, estimates, instructions, orders or these conditions of otherwise concerning the works, or 1the

execution or failure to execute the same whether arising during the progress of the work or after the completion of abandonment thereof shall be referred to the sole arbitration of the General Manager of NTPC Limited {Formerly National Thermal Power Corporation Ltd.}, and If the General Manager is unable or unwilling to act, to the sole arbitration of some other person appointed by the Chairman and Managing Director, NTPC Limited (Formerly National Thermal Power Corporation Ltd}, willing to act as such arbitrator. There will be no objection if the arbitrator so appointed is an employee of NTPC Limited (Formerly National Thermal Power Corporation Ltd) and that he had to deal with the matters to which the contract relates and that in the course of his duties as such he had expressed views on all or any of the matters in dispute or difference. The arbitrator to whom the matter is originally referred being transferred or vacating his office or being unable to act for any reason as aforesaid at the time of such transfer, vacation of office or inability to act, Chairman and Managing Director, NTPC Limited (Formerly National Thermal Power Corporation Ltd}, shall appoint another person to act as arbitrator in accordance with the terms of the contract. It is also a term of this contract that no person other than a person appointed by CMD, NTPC Ltd as aforesaid should act as arbitrator and if for any reason, that is not possible, the matter is not to be referred to arbitration at all."

14. A perusal of the clause 56 of GCC as originally enacted, would

reveal that the General Manager of NTPC Ltd. would act as a Sole

Arbitrator and in the eventuality, the General Manager is unable or

unwilling to act as the Sole Arbitrator, some other person appointed by

the Chairman and Managing Director, NTPC Ltd. will act as an

Arbitrator. The amendment effected to this provision as is clear from the

document at page 34 of the reply, the word "General Manager" has been

replaced by the words "Project Incharge of the Project Concern of

National Thermal Power Corporation Ltd." If clause 56 is read from the

perspective of the amendment, it is clear that the Project Incharge, which

in this case, is the Executive Director need to act as Arbitrator at the first

instance. It appears from the stand, which has been taken by the

respondent of a misreading of the provision with a belief that it is the

General Manager, who was to act as an Arbitrator, need to be accepted as

the petitioner has not controverted the stand of the respondent in the reply

by filing a rejoinder. Even otherwise, the letter dated September 8, 2014,

in no way, can be construed as a letter written to the Chairman and

Managing Director of the respondent corporation to appoint another

person on failure of the Project Incharge to act as an Arbitrator. This I

say so, the letter dated September 8, 2014 was addressed to the AGM

(Civil), Sipat, and not to the Chairman and Managing Director. That

apart, mere sending a copy of the letter to the Chairman and Managing

Director for taking necessary action, cannot be construed as a

communication, calling upon the Chairman and Managing Director to

appoint another person in lieu of the Project Incharge. No such express

request was made. Rather, I find, from the reading of letter dated

September 8, 2014 was a reiteration of the contents of the earlier letter

dated July 26, 2014 relating to invocation of the arbitration in terms of

clause 56 of GCC for settling the claims, which is clear from the request

made by the petitioner in the said letter, which I quote:

"We request you to take immediate steps as per the

provision of clause 56 of GCC".

I agree with the submission of the learned counsel for the respondent that

the petitioner had never invoked the later part of clause 56 of GCC

calling upon the Chairman and Managing Director to appoint another

person in lieu of the Project Incharge till the filing of the petition and in

fact till date. The Project Incharge having entered the reference and

having issued letter dated February 19, 2015, it cannot be said that there

was a failure to invoke clause 56 of GCC. The issuance of letter dated

February 19, 2015 is justified. I note, for benefit the following conclusion

of this Court in the case of M/s. Gangotri Enterprises Ltd. (supra):

"9. Having heard learned counsels for the parties and perused the arbitration clause, aforesaid, I am of the view that after the invocation of the arbitration agreement, if the petitioner was aggrieved on account of inaction of the GM to enter upon the reference within 30 days of the said invocation, it was for the petitioner to inform the CMD of the same and to seek appointment of an arbitrator. Once the arbitration agreement is invoked, it is not necessary for the named arbitrator to act within 30 days of the said invocation. He may act even thereafter and if he so acts, he would have jurisdiction. However, if he does not act within 30 days, and before he acts and enters upon reference, one of the parties either approaches the court or triggers the mechanism for appointment of an arbitrator as provided in the contract, the named arbitrator may lose his authority/mandate to act as an arbitrator and enter upon reference, as held by the Supreme Court in the case of Datar Switchgears Ltd. v. Tata Finance, (2000) 8 SCC 151.

10. In the present case, the petitioner never gave an opportunity to the CMD to appoint the arbitrator, if, according to the petitioner, the GM was unable, unwilling or failed to act. The CMD may not even have been aware of the invocation of the arbitration agreement by the petitioner, since the same was not addressed to him. He may, therefore, not even be

aware of the fact that the GM has either expressed his inability, or unwillingness, to act or that he has failed to act. Even otherwise, merely because the named arbitrator, namely, the GM did not act within 30 days, cannot lead to the conclusion that he has expressed his inability or unwillingness to act in the matter as an arbitrator.

11. Therefore, the filing of the present petition appears to be misconceived, since the petitioner has not invoked the arbitration agreement in its terms by approaching the CMD to appoint the arbitrator. Even before the CMD has been called upon to appoint an arbitrator, the GM has already entered upon reference on 18.07.2013. Therefore, in my view, the GM has the mandate to proceed with the arbitration in the present case. Accordingly, this petition does not survive and the same is dismissed as such".

15. In view of the aforesaid position, the reliance placed by the learned

counsel for the petitioner in the case of Deep Trading Co. (supra) is

untenable and would have no applicability. Insofar as R.S.Avtar Singh

Co. case (supra) is concerned, in view of peculiarity of clause 56 of the

GCC, which postulates a named Arbitrator, who has to enter the

reference pursuant to the invocation of arbitration by the other party, the

said judgment also has no applicability.

16. In view of my above discussion, I do not see any merit in the

present petition. The same is accordingly dismissed. The parties would

be at liberty to raise all their claims and counter claims and objections

before the learned Sole Arbitrator.

(V.KAMESWAR RAO) JUDGE APRIL 28, 2015 akb

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter