Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Nordic Intertrade As (Norway) vs Steel Authority Of India Ltd
2015 Latest Caselaw 3170 Del

Citation : 2015 Latest Caselaw 3170 Del
Judgement Date : 21 April, 2015

Delhi High Court
Nordic Intertrade As (Norway) vs Steel Authority Of India Ltd on 21 April, 2015
Author: V. Kameswar Rao
*       IN THE HIGH COURT OF DELHI AT NEW DELHI
                                                 Date of decision: April 21, 2015

+                         I.A. 11739/2012 in OMP 573/2012

NORDIC INTERTRADE AS (NORWAY)                                 ..... Petitioner

                                    Through:   Mr. Darpan Wadhwa, Mr.
                                               Sumeet Lall & Mr. Shwetabh
                                               Sinha, Advs.

                                    versus

STEEL AUTHORITY OF INDIA LTD                                ..... Respondent

                                    Through:   Mr. Arvind Nigam, Sr. Adv.
                                               & Mr. Ashish Kumar, Adv.
CORAM:
HON'BLE MR. JUSTICE V.KAMESWAR RAO
V.KAMESWAR RAO, J. (Oral)

I.A. 11739/2012 in OMP 573/2012

1. By this order I shall decide IA 11739/2012 filed in OMP

573/2012, by which the petitioner seeks condonation of 21 days‟ delay in

filing the petition under Section 34 of the Arbitration & Conciliation Act

(„Act‟ in short) challenging the Award dated January 23, 2012.

2. It is the case of the petitioner in the application that the impugned

arbitral award dated January 23, 2012 was received by erstwhile

Advocates of the petitioner from Indian Council of Arbitration („ICA‟ in

short ) on February 07, 2012. The petitioner company is based in

Norway. Its Indian agent M/s Sawhney Steel was looking after the

arbitration proceedings. The lawyers for the petitioner who are based in

Mumbai had sent the award to M/s. Sawhney Steel in Delhi.

M/s.Sawhney Steel forwarded the same to the petitioner in Norway. It

was the stand of the petitioner that it took some time for the lawyers in

Mumbai to send it to M/s.Sawhney Steel in Delhi and for M/s.Sawhney

Steel to send the same to its principal, i.e., the petitioner at Norway.

3. On receipt of the award in Norway, the petitioner examined it and

took advice from its lawyers on further course of action, which

consumed substantial time. Pursuant thereto all the documents were

entrusted to the present Advocate of the petitioner who after going

through the documents and the impugned award has prepared and filed

the petition. The petitioner has also averred that from the date of receipt

of the award i.e. February 07, 2012, the present petition ought to have

been filed within 3 months i.e. May 07, 2012, but was filed on May 28,

2012. According to the petitioner, the delay of 21 days had occurred for

the reasons stated above inasmuch as it took some time to receive proper

legal advice on the issues which involve complex questions of law as

well as important principles of shipping and maritime law and there is a

sufficient cause for condoning the delay which was unintentional and

bona-fide.

4. The respondent in its reply to this application would state that the

application does not have any specific details or reasons and the

petitioner had presumed that seeking condonation of delay is a matter of

right. The respondent would submit that the petitioner needs to satisfy

this Court that delay of each and every day was justified and for

sufficient reasons. The respondent disputed about the existence of

sufficient and cogent reasons seeking condonation of delay.

5. In the rejoinder the petitioner has reiterated its stand as taken in

the application seeking condonation of delay.

6. Subsequently on May 10, 2013, the petitioner had filed an

additional affidavit. In this affidavit, the stand of the petitioner

additionally is that the impugned arbitral award dated January 23, 2012

was received by the petitioner from ICA in Norway only on March 28,

2012 under the cover of ICA‟s letter dated February 01, 2012. The

petitioner has also stated that it has premised its application seeking

Condonation of delay by calculating the limitation from the date when

the erstwhile Advocates of the petitioner had received the arbitral award

i.e. on February 07, 2012 instead by the petitioner itself.

7. The petitioner filed a further additional affidavit on October 09,

2014, wherein the petitioner in para No.2 again concedes that it had

inadvertently stated in the additional affidavit filed on May 10, 2013 that

the petitioner had received the impugned arbitral award dated January

23, 2012 from ICA on March 20, 2012 (not March 28, 2012). According

to the petitioner, the mistake had occurred as the petitioner did not

realise that the stamp of acknowledgment for receiving the impugned

arbitral award on the letter dated February 01, 2012 of the ICA actually

was an acknowledgment given by the erstwhile Advocates for the

petitioner. It was also averred that the said confusion arose due to the

fact that the said letter was marked to the petitioner at its Norway

address. The last affidavit also states the impugned arbitral award sent by

ICA through registered post was received by the petitioner in Norway in

the last week of February, 2012. The petitioner concedes that it does not

have the receipt of receiving the impugned arbitral award in its

possession as in Norway the practice is to sign the register in the post

office for the receipt of the registered letter. The petitioner has also

stated that it does not have the envelope in which the impugned award

was received as old envelopes are not retained for long. It may be noted

that these were the primary reasons for the petitioner to plead ignorance

on the exact date of receipt of the arbitral award in the last week of

February, 2012. The petitioner had also written to the ICA requesting it

to provide the receipts confirming the date when the award was sent by

post to the petitioner in Norway and the date when the award was

received by the petitioner in Norway. According to the petitioner, the

ICA vide its letter dated September 25, 2014 confirmed that the said

award was sent to the petitioner in Norway and to the petitioner‟s

erstwhile Advocates in Mumbai through registered A.D post on February

01, 2012 and which was actually dispatched on February 02, 2012.

According to the petitioner, even the attempts made by its Advocates for

confirmation of the date when the award was received by the petitioner

in Norway has proved futile as the post office does not have any

information available with respect to the article dispatched on February

02, 2012. The petitioner‟s case is that if it had received the award on the

first day of the last week of February, 2012, i.e., February 22, 2012 then

the delay in filing the petition would merely be of six days and if

assuming the petitioner had received the award on the last day of last

week of February, 2012 then the petition is filed within 3 months i.e.

within limitation. It is its case in the affidavit that the limitation for

challenging the impugned arbitral award ought to be calculated from the

date when the petitioner received the copy of award from ICA and not

from February 07, 2012 when the erstwhile Advocates for the petitioner

received the award.

8. Mr.Darpan Wadhwa, learned cousnel for the petitioner has taken

me through the application and different affidavits filed by the petitioner

to urge that there was an inadvertent mistake on the part of the petitioner

not to mention in the application itself the receipt of the arbitral award by

its client in Norway. He also concedes that the premise on which the

application was filed that the arbitral award was received by the

erstwhile Advocates of the petitioner in Mumbai and sent to the

petitioner‟s agent in Delhi who had sent the award to the petitioner in

Norway is vague and without material dates. He also states that the stand

of the petitioner in the additional affidavit filed on May 10, 2013 that the

petitioner had received the impugned arbitral award dated January 23,

2012 on March 28, 2012 was also an inadvertent mistake. According to

him, it is not the case of the respondent that the delay in filing the

petition was beyond 3 months and thirty days. In other words, according

to him the delay, if any, being beyond 3 months but within additional 30

days as required under Section 34(3) of the Act, the reasons specified in

the application i.e. that after the receipt of the award the petitioner took

legal advice, and it was advised to challenge the impugned arbitral award

and thereafter the lawyers going through the record of the case and

preparing the petition which resulted in loss of time is a sufficient cause

for this Court to condone the delay. He would also state that in terms of

the settled position of law the limitation would start from the date when

the party has received a signed copy of the arbitral award from the

Arbitrator/Arbitral Tribunal, which according to him would be the last

week of February, 2012. He states, even then the delay would be 6 days,

from the Ist day of the last week of February 2012. Alternative he would

plead, even assuming the limitation start running from the date when the

erstwhile Advocates of the petitioner had received the impugned arbitral

award then also the delay would be of 21 days. It is his submission that

the word „sufficient cause‟ should be given liberal interpretation to

ensure that substantial justice is done, otherwise the petitioner would be

denied of a remedy against the impugned arbitral award. He would state

that the petitioner has a prima facie case in the main petition and would

rely upon the following judgments in support of his contentions:-

(a) State of Himachal Pradesh & Anr.. vs. Himachal Techno Engineers & Anr. (2010) 12 SCC 210

(b) State of Goa vs. Western Builders (2006) 6 SCC

(c) Union of India vs. Tecco Trichy Engineers & Contractors (2005) 4 SCC 239

(d) Benarsi Krishna Committee & Ors. vs. Karmyogi Shelters Private Limited (2012) 9 SCC 496

(e) Ram Nath Sao & Ors. vs. Gobardhan Sao & Ors. (2002) 3 SCC 195

(f) N.Balakrishnan vs. M. Krishnamurthy (1998) 7 SCC

(g) Delhi Development Authority vs. M/s Amita Nand Agarwal (OMP No.115/2007) decided on 25.02.2008

(h) Mrs. Gurdeep Kaur vs. Mrs. C.K. Bedi & Anr.

        (2008) 2 ARB 537 (Delhi)
        (i)    MCD vs. G.D Builders 119 (2005) DLT 658

9. On the other hand, Mr.Arvind Nigam, learned Senior Counsel for

the respondent has taken me through the application, rejoinder and the

additional affidavits filed by the petitioner in support of its prayer

seeking condonation of delay. According to him, the application itself is

premised on a false ground that the arbitral award was received by the

erstwhile Advocates of the petitioner. In other words, it was his case that

nowhere in the application did the petitioner mentioned that petitioner

had also received a copy of the impugned arbitral award. That apart he

would state that even the date of sending the arbitral award to the

petitioner‟s agent in Delhi has not been given nor the application refers

to the date on which the petitioner‟s agent in Delhi had sent the copy to

the petitioner in Norway. He would also state that a new fact has been

averred by the petitioner in the first additional affidavit filed on May 10,

2013 that the impugned arbitral award was received by the petitioner on

March 28, 2013. According to him, this is factually incorrect inasmuch

as the document evidencing the receipt of the arbitral award was in fact

is the receipt of the impugned arbitral award by the Advocates of the

petitioner in Mumbai. He has compared for the benefit of this Court the

stamps which are identical. He would also state that the petitioner has

admitted the false statement made by it in the affidavit dated May 10,

2013. According to him, even in the second additional affidavit filed on

October 09, 2014 the petitioner had stated that the arbitral award was

received in the last week of February, 2012. He would state, no date has

been given which would be material to consider the prayer for

Condonation of delay in filing the petition under Section 34 of the Act.

He would sum up by stating that a party which has not approached the

Court with clean hands is not entitled to any relief. He would rely upon

the following two judgments in support of his case:

(a) Municipal Corporation of Delhi vs. Madhu Kishan Gupta & Anr., OMP No. 576/2006, decided by this Court on December 12, 2007

(b) Basawaraj & Anr. vs. Special Land Acquisition Officer (2013) 14SCC 81

10. Having considered the submissions made by learned counsel for

the parties, it is the case of the petitioner that the petition has been filed

beyond the period of three months but within additional thirty days and

sufficient cause having been shown, this Court need to condone the

delay. It is to be considered whether sufficient cause has been shown for

the Court to condone the delay or as contended by the learned Senior

Counsel for the respondent that the petitioner having taken a false stand

which reflects that the petitioner had not approached this Court with

clean hands, the prayer for condonation of delay need to be rejected.

11. Before I deal with the merits of the contentions advanced before

me, I consider the judgments referred to by the learned counsel for the

parties.

12. In State of Himachal Pradesh and Anr. Vs. Himachal Techno

Engineers, a dispute arose between the parties with regard to the

construction of a water purification plant. A question was raised with

regard to date of commencement of limitation under Section 34 of the

Arbitration and Conciliation Act, 1996, whether the period of three

months can be counted as 90 days. The court held that:

Sub-section (3) uses the words 'three months' while prescribing the period of limitation and the proviso uses the words 'thirty days' while referring to the outside limit of condonable delay. The legislature had the choice of describing the periods of time in the same units, that is to describe the periods as 'three months' and 'one month' respectively or by describing the periods as 'ninety days' and 'thirty days' respectively. It did not do so. Therefore, the legislature did not intend that the period of three months used in Sub-section (3) to be equated to 90 days, nor intended that the period of thirty days to be taken as one month.

13. Further, with regard to the issue of when the period of

limitation is to commence, the court followed the ratio as laid down

in the Tecco Trichy Case (infra) holding that the period only

commences once a copy of the arbitral award has been received by a

party to the arbitration agreement.

14. In State of Goa v Western Builders (supra), the Supreme Court

discussed the issue of the applicability of the Limitation Act to a Section

34 petition in a matter where a dispute between the parties was originally

decided against the State of Goa. The State delayed filing its Section 34

petition challenging the award. On the applicability of the Limitation

Act, the Court held:

"general proposition is by virtue of Section 43 of the Act of 1996 The Limitation Act 1963 applies to the Act of 1996 but by virtue of Sub-section (2) of Section 29 of the Limitation Act, if any other period has been prescribed under the special enactment for moving the application or otherwise then that period of limitation will govern the proceedings under that Act, and not the provisions of the Limitation Act. In the present case under the Act of 1996 for setting aside the award on any of the grounds mentioned in Sub-section (2) of Section 34 the period of limitation has been prescribed and that will govern. Likewise, the period of condonation of delay i.e. 30 days in the proviso to Section 34(2) will govern.

15. In Union of India v Tecco Trichy Engineers & Contractors

(supra), a dispute arose in a contract with regard to gauge conversion of

railway tracks from Madras Beach to Trichchirappalli-Villupuram

Section. The question of condonation of delay in filing Section 34(3)

proceedings arose before the Supreme Court; specifically the question of

the date wherefrom the limitation under Section 34(3) would be

counted? Looking into the issue, the Supreme Court held that:

"The delivery of an arbitral award under sub-Section (5) of Section 31 is not a matter of mere formality. It is a matter of substance. It is only after the stage under Section 31 has passed that the stage of termination of arbitral proceedings

within the meaning of Section 32 of the Act arises. The delivery of arbitral award to the party, to be effective, has to be "received" by the party. This delivery by the arbitral tribunal and receipt by the party of the award sets in motion several periods of limitation such as an application for correction and interpretation of an award within 30 days under Section 33(1), an application for making an additional award under Section 33(4) and an application for setting aside an award under Section 34(3) and so on. As this delivery of the copy of award has the effect of conferring certain rights on the party as also bringing to an end the right to exercise those rights on expiry of the prescribed period of limitation which would be calculated from that date, the delivery of the copy of award by the tribunal and the receipt thereof by each party constitutes an important stage in the arbitral proceedings".

16. In Benarsi Krishna Committee & Ors. (supra), the Supreme Court

was dealing with a matter relating to the conversion of a cinema

compound into a commercial complex. Dispute arose in the matter, which

was referred to arbitration. A question was raised before the Supreme

Court with regard to Section 34(3) and what constituted valid service

under the section. It was held that service had to be validly made on a

„party‟ and the Court inter alia held, the expression "party" as defined in

Section 2(1)(h) of the 1996 Act, clearly indicates a person who is a party

to an arbitration agreement. The said definition is not qualified in any way

so as to include the agent of the party to such agreement. In such

circumstances, proper compliance with Section 31(5) would mean

delivery of a signed copy of the arbitral award on the party himself and

not on his advocate, which gives the party concerned right to proceed

under Section 34(3) of the aforesaid Act".

17. In Ram Nath Sao (supra), it was a case of partition suit involving

approximately 116 acres of land, in which an issue arose, whether

substitution of legal heirs of deceased defendants had been done within

the limitation period. In this case, it has been held by the Supreme Court

that „sufficient cause‟ is to be liberally construed. On the issue of

limitation, it held that the condonation of delay is a matter of discretion of

the court. For the delay, it also held that the rule in court should be

acceptance of the explanation furnished by a party for delay and not the

other way around.

18. In N. Balakrishnan (supra), the Supreme Court while dealing with

Section 5 of the Limitation Act, in addition to condonation of delay being

at the discretion of the court, held that the Rules of limitation are not

meant to destroy the rights of parties. They are meant to see that parties do

not resort to dilatory tactics, but seek their remedy promptly.

19. In Delhi Development Authority v M/s Amita Nand Aggarwal

(supra), the petition under Section 34 was filed 20 days after the

permissible period of 3 months had passed. However, certain objections

were raised by the Registry, which were finally cleared only after the

additional 30 days period had passed. Delay was condoned under Section

34(3) by this Court. In this case, it was seen that the government agency

involved, DDA, had a long internal procedure before the matter was filed.

A 20 days delay beyond the initial 3 months was permitted. The time

taken to clear objections before the Registry was not counted for the

purposes of limitation.

20. In Gurdeep Kaur (supra), the dispute between the parties hinged

on a plot of land measuring 1005 sq. yards in Greater Kailash, New Delhi,

purchased by the respondent, a British citizen after obtaining permission

from the Reserve Bank of India. While challenging the decision of the

arbitral tribunal under Section 34, there was a delay in filing the petition

before the Court. Delay was condoned by this Court as the party had

received a copy of the award late as she was abroad. The counsel for the

party had received the copy, but limitation for purposes of Section 34 was

held to start from the date of receipt of the award by the party herself, and

the fact that she was abroad and thus unable to receive the award was

accepted by this Court.

21. In Municipal Corporation of Delhi v GD Builders (supra), this

Court has examined when a delay under Section 34 is to be condoned.

While looking at the facts of the case, it was determined that filing was

done within the 30 days period over and above the 3 months that have

been prescribed in Section 34(3). The Court while examining judicial

precedent for determining what constitutes „sufficient cause‟ held as

under:

" In Shakuntala Devi Jain v. Kuntal Kumari and Ors. [1969]1SCR1006 , their Lordships held that unless an application was found to be bereft of bona fides or the delay was caused by inaction or negligence of the party, the prayer for condonation should not be declined. In New India Insurance Co. Ltd. v.Smt. Shanti Misra: [1976]2SCR266 , their Lordships held that the discretion vested in the court under Section 5 cannot be defined or crystallized so as to convert a discretionary power into a rigid rule of law and that the expression 'sufficient cause' should receive a liberal construction. Reference may also be made to State of Kerala v. E.K. Kuriyipe and Ors. where the court held that the existence or otherwise of a sufficient cause to justify condensation of delay was a question of fact to be decided in the facts and circumstances of each case. This was followed by the decision of the Supreme Court in O.P. Kathpalia v. Lakhmir Singh and Ors. AIR1984SC1744 where the court held that of refusal to condone the delay would cause grave miscarriage of justice, the same should be condoned.

The Court condoned the delay occurred due to departmental/official

process on account of functioning of local body.

22. Whereas in the case of Madhu Kishan Gupta (supra) this Court

was considering an application filed seeking condonation of delay of 14

days in filing the petition under Section 34 of the Act by the Municipal

Corporation of Delhi. The ground taken by the petitioner MCD for the

delay was on account of "necessary procedural steps". This Court was

of the view that no cogent reasons or facts have been disclosed, on the

basis of which it can be inferred that the delay is on account of sufficient

reasons. The Court further held in the absence of facts highlighting

alleged procedural steps, the condonation sought was not for bona fide

and sufficient reasons/cause.

23. In Basawaraj & Anr. (supra), the Supreme Court was considering

a case, where the land of the appellants was acquired in pursuance of

notification dated 23.4.1994. The award under Section 11 was made on

23.10.1997. The appellant preferred reference under Section 18(1) of the

Act for enhancement of compensation and the reference Court vide

award dated 28.2.2002 enhanced the compensation. Aggrieved, the

appellant filed appeals under Section 54 of the Act before the High Court

on 16.8.2007 with applications for condonation of delay. The same stood

rejected by the High Court as it did not find sufficient cause to condone

the delay. The Supreme Court held that the discretion to condone delay

has to be exercised judiciously based on facts and circumstances of each

case. Sufficient cause cannot be liberally interpreted if negligence in

action or lack of bona fides is attributed to the party. Whether or not

sufficient cause has been furnished can be decided on the facts of the

case and no straight jacket formula is possible (Reference is made to

Madan Lal v. Shyam Lal, 2002 (1) SCC 535). The Court also held that

the sufficient cause means that the party should not have acted in a

negligent manner or there was want of bona fide on the part in view of

the facts and circumstances of a case or it cannot be alleged that party

has not acted diligently or remained inactive.

24. On a reading of the afore-said position of law, as relied upon by

the parties, the following position emerges:-

(1) The delivery of an arbitral award is not a matter of mere

formality. It is a matter of substance. The period of limitation

under Section 34(3) commences once a copy of the arbitral award

has been received by a party to the arbitration agreement and not

by the Advocate.

(2) Where there is a challenge to the arbitral award, the period

prescribed under the Act, which being a special enactment for

moving the application or otherwise, then that period of limitation

will govern the proceedings under the Act.

(3) The sufficient cause is to be liberally construed and

condonation of delay is a matter of discretion of the Court and

acceptance of explanation given should be the rule and refusal the

exception.

(4) The rules of limitation are not meant to destroy the rights of

the parties but to ensure that the parties do not resort to dilatory

tactics but seek their remedy promptly.

(5) A delay of 20 days because of long internal procedure

beyond 3 months was condoned.

(6) Delay was condoned on the ground that the petitioners had

received a copy of the award after she had come from abroad.

(7) In an application seeking condonation of delay cogent

reasons/facts need to be divulged to form a view of sufficient

cause.

(8) The plea of condonation of delay has to be with regard to

the facts of each case. Even though the Court has discretion, it has

to be exercised judiciously. Sufficient cause cannot be liberally

interpreted if negligence in action or lack of bona fides is

attributed to the party.

25. The application of the petitioner was premised on a factual aspect,

that the impugned arbitral award was received by the lawyers of the

petitioner in Mumbai on February 07, 2012. The onward transmission of

the arbitral award through the petitioner‟s agent in Delhi and then to

Norway to the petitioner and further consideration of the arbitral award

by the petitioner and its taking a legal advice of a new counsel and the

preparation of the petition resulted in the delay. The relevant dates have

not been given. In the first additional affidavit, the petitioner had referred

to 28th March, 2012 as the date on which the arbitral award was received

by the petitioner in Norway possibly to justify the petition was within

limitation. In fact the petitioner had tried to justify the petition being

within limitation by stating that the limitation must count from the date

when the party has received the arbitral award and not the erstwhile

Advocates. In the second additional affidavit, the petitioner concedes

that it had inadvertently stated in the first additional affidavit that the

petitioner had received the impugned arbitral award on March 28, 2012.

The second additional affidavit reveals, some enquiries have been made

after the mistake was detected possibly in view of the hearing before this

Court on November 22, 2014 when learned counsel for the petitioner had

sought time to file a better affidavit. The second additional affidavit also

does not disclose the date on which the impugned arbitral award was

received by the petitioner in Norway. The petitioner has not produced

the receipt given by it to the postal authorities in Norway nor the

envelope through which the arbitral award was received. The petitioner

has left it to the Court to do the guess work. The receipt of the arbitral

award can be in the second or third week of February, 2012 as well, but

it cannot be before February 07, 2012 as that was the date of receipt of

award by the erstwhile Advocates of the petitioner in Mumbai. The

transmission to Norway would take more time. Mr.Wadhwas‟s

submission, (even though, contrary to the position of law, that the

limitation starts from the date of receipt of the Award by the party), as an

alternative plea that even assuming the date of February 07, 2012 is

taken as the date of receipt of the arbitral award, the delay is of 21 days

beyond 3 months and sufficient cause having been shown, the delay need

to be condoned is appealing. It is one thing to allege that the conduct of

the petitioner in pleading its case seeking condonation of delay in the

application, affidavits is improper/casual, but different to allege lack of

bona-fide on the part of the petitioner to pursue its remedy challenging

the arbitral award by filing a proper petition. The facts as pleaded that

the petitioner sought legal advice and engaged the present counsel, who

after perusing the documents prepared the petition cannot be doubted.

There is some explanation. It is not the case of the respondent that the

counsel for the petitioner is same who pleaded the case before the

Arbitrator. The manner in which the petitioner had pleaded its case by

filing application and affidavits without verifying the material particulars

may not show a deliberate act to hoodwink the Judicial Process, but

reflects the casualness, disregard and indifferent attitude with which this

application has been prosecuted. That cannot be a ground to deny the

relief to the petitioner in the application whereby the petitioner has called

upon this Court to allow it to cross the hurdle of limitation so that it can

put forward its case on the merit of the challenge to the arbitral award,

but surely considering the manner in which the condonation was sought,

some conditions which act as a deterrent and the majesty of law is

upheld need to be imposed.

26. Accordingly, I deem it fit to allow this application by condoning

the delay of 21 days in filing the petition under Section 34 of the Act,

subject to the petitioner paying a cost of Rs.1 lakh (Rupees One Lakh) to

the respondent on or before the next date of hearing.

27. The application is accordingly disposed of.

28. List the OMP 573/2012 for directions on 27th July, 2015.

(V.KAMESWAR RAO) JUDGE APRIL 21, 2015/km

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter