Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Nimbus Communcations Ltd vs Prasar Bharti & Anr
2015 Latest Caselaw 2664 Del

Citation : 2015 Latest Caselaw 2664 Del
Judgement Date : 6 April, 2015

Delhi High Court
Nimbus Communcations Ltd vs Prasar Bharti & Anr on 6 April, 2015
Author: V. Kameswar Rao
*       IN THE HIGH COURT OF DELHI AT NEW DELHI

                                   Judgment reserved on March 09, 2015
                                    Judgment delivered on April 06, 2015

+                         O.M.P. 60/2015

NIMBUS COMMUNCATIONS LTD
                                                        ..... Petitioner

                          Through:     Mr.Jayant Bhushan, Sr. Adv.
                                       with Mr.Amol Chitala,
                                       Mr.N.Dube, Mr.Ankur
                                       S.Kulkarni, Mr.Anand
                                       Srivastava, Mr.Shubham
                                       Jaiswal, Advs.

                          Versus

PRASAR BHARTI & ANR
                                                     ..... Respondents

                          Through:     Mr.Rajeev Sharma, Adv.
                                       with Ms.Radha Laksmi R.,
                                       Adv. for R1/Prasar Bharti

CORAM:
HON'BLE MR. JUSTICE V.KAMESWAR RAO

V.KAMESWAR RAO, J.

1. The challenge in this petition under Section 34 of the Arbitration

and Conciliation Act, 1996 (Act, in short) is to the interim award dated

September 16, 2014 passed by the Arbitral Tribunal (Tribunal, in short),

by majority (Hon‟ble Mr. Justice S.P.Bharucha, Presiding Arbitrator and

Hon‟ble Mr. Justice B.P. Jeevan Reddy) whereby the Tribunal has

awarded in favour of the respondent No. 1 an amount of

Rs.22,77,67,422/-. By a dissenting order, dated September 18, 2014,

Hon‟ble Mr. Justice V.N.Khare has held that the application for interim

award be taken up for hearing after evidence is led by the parties on a

reasoning that the expression used „adjustment of liabilities cannot be

construed as an admission of claim by the petitioner.

The facts:

2. On November 11, 2005, the Govt. of India had notified guidelines

known as Downlinking Guidelines, which inter alia, provided in para 5.2

thereof, for compulsory sharing of signals of sporting events of national

importance by the rights holders with Prasar Bharti. The said guidelines

also provided that insofar as cricketing events are concerned, all cricket

matches featuring the Indian Team and the Semi-Finals and Finals of

International events would constitute sporting events of national

importance. The downlinking guidelines provided, the revenues

generated by the sharing of signals by the rights holders with Prasar

Bharti would be shared in the ratio of 75:25 between the rights holders

and Prasar Bharti. The guidelines also provided as to who, out of the

rights holders and Prasar Bharti would undertake the marketing of

commercial times associated with telecast. It is noted that the rights

holders had to provide the live signals of sporting events of national

importance to Prasar Bharti without advertisements and Prasar Bharti

had to retransmit the live signals on its terrestrial and DTH networks

(Doordarshan National and DD Direct). During the transmission of the

matches on Doordarshan National, opportunities for airing the

advertisements would arise. Therefore, it was also necessary to provide

as to who would book advertisements. The guidelines provided that the

party that offered to maximise, the revenue would be appointed as the

Revenue Management Company. The appointment was formalized

through a bidding process, whereunder, both parties would give sealed

bids in respect of their estimation of the revenues that could be generated

by way of advertisements to be carried on Doordarshan during the

telecast of the matches. The party which would give the higher

estimation would get the right to book the advertisements and the

revenues so collected would be shared in the ratio of 75:25 as between

the rights holders and Prasar Bharti.

3. On December 5, 2005, the uplinking guidelines were notified. I

note from record, the uplinking guidelines also contained a provision

similar to the one contained in downlinking guidelines insofar as the

sharing of signals of sporting events of national importance were

concerned.

4. The first Cricket Series played after the aforesaid guidelines was

India-England series in February 2006 for which, the petitioner was the

rights holder. By way of bidding process, the petitioner was appointed

as the RMC for the telecast to be made by the respondent No.1, Prasar

Bharti. To secure the rights of both the parties, it was agreed that all

money would be deposited in an Escrow Account and the RMC would

furnish a bank guarantee to the other party-Prasar Bharti for an amount

equal to 25% of the net projected revenue. Petitioner as RMC furnished a

bank guarantee to the respondent No.1 for an amount equal to 25% of

the net projected revenue.

5. In February 2007, the Sports Broadcasting Signals (Mandatory

Sharing with Prasar Bharti) Ordinance, 2007 was promulgated which

was subsequently replaced by the Sports Broadcasting Signals

(Mandatory Sharing with Prasar Bharti) Act, 2007. In terms of Section

1(3), the Act was deemed to have come into force on November 11,

2005, the day on which the downlinking guidelines were notified. The

Act provided the mandatory sharing of live signals of events of national

importance by the content rights owners or holders/Television or Radio

Service Providers with Prasar Bharti to enable it to retransmit such

signals on its terrestrial and DTH networks. The Act, inter alia, provided

that the revenues earned from such sharing of live signals would be

shared in the ratio of 75:25 between the rights holders and Prasar Bharti.

The rules made under the Act of 2007, inter alia, provides for a sealed

bid procedure to be adopted and the party bidding higher shall get the

marketing rights. The party getting marketing rights shall give a bank

guarantee to the other party for an amount equal to the other party‟s

share of guaranteed revenue, which shall be valid for a period of six

months from the first day of the month succeeding the month, in which

the sporting event comes to an end. The rules also contemplate, the

party having marketing rights shall be entitled to obtain all release orders

and payments in its name and all payments shall be received by it only

by way of account payee cheques which shall be deposited in a

designated Escrow Account from which the party shall be at liberty to

make withdrawals after discharging the tax liability. The rules also

contemplate the party having the marketing rights shall submit to the

other party, complete accounts of revenue earnings duly audited by

Chartered Accountant along with all the release orders and shall pay the

entire guaranteed amount as well as any other amount to which the other

party is entitled as per the revenue sharing formula under the Act and

Sub-Rule 3 of Rule 4 within 75 days from the first day of the month

succeeding the month in which the sporting events comes to an end.

6. It may be stated here that between the years 2007 and 2009, the

following seven cricketing events took place:

         S.No.    Event                                       Shared By
        1        India Bangladesh Series 2007                Nimbus Sport
                                                             International Pte Ltd.
        2        India Australia Cricket Series, 2007        Nimbus Communications
                                                             Ltd.
        3        India Australia T-20 match played on        Nimbus Communications
                 20.10.2007                                  Ltd.
        4        India Pakistan Cricket Series, 2007         Nimbus Communications
                                                             Ltd.
        5        India, Bangladesh & Pakistan Series, 2008   Nimbus Sport
                                                             International Pte Ltd.
        6        India England Series, 2008                  Nimbus Communications
                                                             Ltd.
        7        India Sri Lanka Series, 2009                Nimbus Sport
                                                             International Pte Ltd.




In the aforesaid cricketing events, the signals were shared by the

petitioner and the respondent No. 2 with the Prasar Bharti i.e. the

respondent No. 1.

7. It is noted that a formal agreement was entered between the

petitioner and Prasar Bharti (respondent No. 1) with respect to India

Pakistan Series 2007, Sl. No. 4 above, which provided resolution of

disputes by arbitration. As disputes arose between the Prasar Bharti and

the petitioner and the respondent No. 2 herein, clause 13 of the

agreement in respect of India Pakistan Series 2007, was invoked on June

1, 2009 for adjudication of the disputes. It was mutually agreed between

the parties that all disputes arising from the dealings between the parties

concerning the aforesaid seven events be adjudicated by the Tribunal

constituted pursuant to the invocation letter dated June 1, 2009.

Accordingly, as desired by the Tribunal (as submitted by learned counsel

for the respondent No.1), on the first date of hearing, calling upon the

parties to enter into an arbitration agreement for referring the disputes to

the Tribunal, the parties on August 31, 2011, signed an arbitration

agreement, whereby it was consented that all disputes arising out of the

cricketing events mentioned at Sl. Nos. 1 to 7 above between the

petitioner and respondent No. 1 and Nimbus Sports International Pte

Ltd.-respondent No.2 be adjudicated upon in accordance with clause 13

in the agreement dated November 3, 2007 by the Tribunal. Suffice to

state, the agreement also record that, "all contentions of the parties are

left open".

The Disputes:

8. The respondent No.1/Prasar Bharti‟s, the claimant before the

Tribunal, claim in brief was that the petitioner and respondent No. 2

have failed to pay their share of revenues for the respective series

marketed by them. It was the case of the respondent No. 1/Prasar Bharti

that it was at least entitled to the following amounts from the petitioner

and the respondent No.2:-

S.No.   Event          Due from Nimbus Sports Due from Nimbus   Interest            Total
                       International Pte. Ltd. Communications
                       Rs.                     Ltd.
1       India          14,16,633                                12,11,221           26,27,854
        Bangladesh
        Cricket
        Series 2007
2       India                                8,82,50,000        6,48,63,750         15,31,13,750
        Australia
        Cricket
        Series, 2007
3       India                                77,50,000          56,96,250           1,34,46,250



       Australia
      Twenty-20
      Cricket
      match 2007
4     India,        2,52,50,000                   1,55,28,750         4,07,78,750
      Bangladesh,
      Pakistan

5     India                         5,48,25,000   2,87,83.125         8,36,08,125
      England

6     India Sri     1,75,50,000                   86,99,625           2,62,49,625
      Lanka 2008




9. The prayers made in the claim petition by the respondent No. 1 are

reproduced as under:

i. direct respondent no.1 to render audited accounts in respect of revenue earnings from the following series: a. India - Australia Cricket Series, played from 29th September to 27th October, 2007;

b. India - Australia Twenty-20 Cricket Match played th on 20 October, 2007.

c. India - England cricket series; played from 14th November, 2008 to 2nd December, 2008.

ii. direct respondent No.1 to pay Rs. 15,31,13,750/- (Rs. Fifteen Crore Thirty One Lakh Thirteen Thousand Seven Hundred & Fifty) for the India-Australia Cricket Series, 2007 to the claimant which is inclusive of the principal sum of Rs.8,82,50,000/- (Rs. Eight .Crore Eighty Two Lakh Fifty Thousand) and interest thereon ^ 18% per annum for the period 15.1.2008 to 23.1.2012 amounting to Rs. 6,48,63,750/- (Rs. Six Crore Forty Eight Lakh Sixty Three Thousand Seven Hundred & Fifty) alongwith pendente lite and future interest @ 18% per annum till the date of payment or direct respondent No.1 to pay 25% of the actual net revenue for the India Australia series, 2007 if the actual net revenue was in excess of Rs. 36.30 crore alongwith interest thereon @ 18% per annum w.e.f 15.1.2008 upto the date of payment, direct respondent No.1 to pay Rs. 1,34,46,250/- (Rs. One Crore Thirty Four Lakh Forty Six Thousand Two Hundred & Fifty) to the claimant for the India-Australia T-20 match, 2007 which is inclusive

of the principal sum of Rs.77,50,000/- (Rs. Seventy Seven Lakh Fifty Thousand) and interest thereon @ 18% per annum for the period 15.1.2008 to 23.1.2012 amounting to Rs. 56,96,250/- (Rs. Fifty Six Lakh Ninety Six Thousand Two Hundred & Fifty) alongwith pendente lite and future interest @ 18% per annum till the date of payment or direct respondent No.1 to pay 25% of the actual net revenue for the India Australia T-20 match, 2007 if the actual net revenue was in excess of Rs. 3.10 crore alongwith interest thereon @ 18% per annum w.e.f 15.1.2008 upto the date of payment.

iv. direct respondent No.1 to pay Rs. 8,36,08,125/- (Rs. Eight Crore Thirty Six Lakh Eight Thousand One Hundred & Twenty Five) for the India-England Cricket Series, 2008 to the claimant which is inclusive of the principal sum of Rs.5,48,25,000/- (Rs. Five Crore Forty Eight Lakh Twenty Five Thousand) and interest thereon @ 18% per annum for the period 16.3.2009 to 23.1.2012 amounting to Rs. 2,87,83,125/- (Rs Two Crore Eighty Seven Lakh Eighty Three Thousand One Hundred &Twenty. Five) alongwith pendente lite and future interest @ 18% per annum till the date of payment:

or direct respondent No.1 to pay 25% of the actual net revenue for the India England series, 2008 if the actual net revenue was in excess of Rs. 22.05 crore, alongwith interest thereon @ 18% per annum w.e.f 16.3.2009 upto the date of payment

vi. direct respondent no.2 to render audited accounts in respect of revenue earnings from the following series: a. India - Bangladesh - Pakistan Triangular Cricket series played in June, 2008 b. India-Sri Lanka Cricket Series, 2009 played in January- February, 2009.

vii. direct respondent No.2 to pay Rs. 26,27,854/- (Rs. Twenty Six Lakli Twenty Seven Thousand Eight Hundred & Fifty Four) to the claimant for the India Bangladesh series, 2007 which is inclusive of the principal amount of Rs

14,16,633/- (Rs. Fourteen Lakh Sixteen Thousand Six Hundred &Thirty Three) and interest thereon @ 18% per annum for the period 14.8.2007 to 23.1.2012 amounting to Rs.12,11,221/- (Rs. Twelve Lakh Eleven Thousand Two Hundred & Twenty One) alongwith pendente lite and future interest @ 18% per annum till the date of payment;

vii. direct respondent No.2 to pay Rs. 4,07,78,750/- (Four Crore Seven Lakh Seventy Eight Thousand Seven Hundred &Fifty) for the India-Bangladesh-Pakistan Cricket Series, 2008 to the claimant which is inclusive of the principal sum of Rs.2,52,50,000/- (Rs. Two Crore Fifty Two Lakh Fifty Thousand) and interest thereon (g 18% per annum for Ihe period 13.9.2008 to 23.1.2012 amounting to Rs. 1,55,28,750/- (Rs. One Crore Fifty Five Lakh Twenty Eight Thousand Seven Hundred & Fifty) alongwith pendente lite and future interest 18% per annum till the date of payment

Or

direct respondent No.2 to pay 25% of the actual net revenue for the India-Bangladesh-Pakistan Cricket Series, 2008 if the actual net revenue was in excess of principal sum of Rs. 10.10 crore alongwith interest thereon @18% per annum w.e.f 13.9.2008 upto the date of payment.

viii. direct respondent No.2 to pay Rs.2,62,49,625/- (Two Crore Sixty Two Lakh Forty Nine Thousand Six Hundred & Twenty Five) for the India-Sri Lanka series, 2009 to the claimant which is inclusive of the principal sum of Rs. 1,75,50,000/- (Rs, One Crore Seventy Five Lakh Fifty Thousand) and interest thereon @ 18% per annum for the period 14.5.2009 to 23.1.2012 amounting to Rs.86,99,625/- (Rs. Eighty Six Lakh Ninety Nine Thousand Six Hundred & Twenty Five) alongwith pendente lite and future interest @ 18% per annum till the date of payment

Or

direct respondent No.2 to pay 25% of the actual net revenue

collections for the India-Sri Lanka series, 2009 if the actual net revenue was in excess of the principal sum of Rs. 7,02 crore alongwith interest thereon @ 18% per annum w.e.f 14.5.2009 upto the date of payment.

      ix.    Costs of the proceedings be awarded to the
      claimant;

      x.     such other order be passed as deemed fit in the
      circumstances of the case".


10. The petitioner/respondent No.2‟s case in the reply to the claim

petition was that the sums claimed by the respondent No. 1 have already

been adjusted against the amounts due to the petitioner. It was the case

of the petitioner that the respondent No. 1 had booked advertisements,

time totalling to 16,549 extra seconds but it accounted only for 30,000

seconds and had paid to the petitioner only Rs.60,93,75,000 towards

75% of the value of the 30,000 seconds. The value of the additional time

consumed by the respondent No. 1 of 16,549 seconds and 75% thereof

being 19,86,82,487/- is required to be paid by the respondent No. 1. In

fact, the reliefs prayed for in the counter claim by the petitioner were as

under:

(a) Be it declared that the adjustments made: by the Respondent No.1 vide its letter, as recorded In its Advocate's letter dated 24.10.2008 and as recorded in its Advocate's letter dated 16-05-2009 addressed to the Claimant-Exhibit-AN to the Statement of Claim

appearing on page 325 is valid and binding upon the claimant and the claimant be directed to record such adjustments in its books of accounts.

(b) For an award that adjustment of a sum of Rs.4,12,62,500/- originally owned by the respondent No. 2 to the claimant is validly adjusted against the amount of Rs.7,66,06,626/- owed by the claimant to respondent No.

1.

(c) For an award that the Claimant is liable to pay to the Respondent No.l a sum Rs.21,19,81,626/- as per particulars is annexed herewith.

(d) For an award that the adjustment of a sum of Rs.13,53,75,000/- claimed by the claimant from the respondent No. 1 against the sum of Rs.21,19,81,626/- owed by the claimant to the respondent No. 1 is valid and binding upon the claimant.

(e) For an award directing the claimant to pay to the respondent No. 1 a sum of Rs.3,53,44,126/- as per particulars is annexed herewith;

(f) For costs;

(g) For such other and further reliefs as the nature and circumstances of the case may require.

11. The basis for the aforesaid counterclaim of the petitioner as stated

by the petitioner in its notice dated May 16, 2009, got issued through its

lawyers, was that an amount of Rs.1,32,99,139/- was due to the

petitioner by the respondent No. 1 in respect of India-England 2006

Cricket Series. In relation to India-Pakistan November-December 2007

Series, the petitioner had demanded a sum of Rs.19,86,82,847/- which

amount as on the date of notice was said to be Rs.21,19,81,626/-. In

respect of India-Australia October 2007 Series and India-England

November-December 2008 Series, a sum of Rs.13,53,75,000/- was

claimed by the respondent No. 1/Prasar Bharti and on adjustment of the

claim of the respondent No. 1/Prasar Bharti against the petitioner‟s claim

of Rs.21,19,81,626, an amount of Rs.7,66,06,626/- was due on that date.

That apart, it was the case of the petitioner that it was nominated by the

Nimbus Sports International Singapore to be a Revenue Management

Company in respect of India-Bangladesh May 2007 Series, India-

Pakistan-Bangladesh June 2008 Cricket Series, and India-Sri Lanka

January-February 2009 Series. After adjusting a sum of Rs.15,37,500/-;

the net amount claimed by the respondent No.1/Prasar Bharti was Rs.

4,12,62,500/- from Nimbus Sports International Singapore and the

petitioner has procured from Nimbus Sports International Singapore-

respondent No.2 their mandate to adjust the amount of Rs. 4,12,62,500/-

owed by it to the respondent No. 1/Prasar Bharti, against the amount of

Rs.7,66,06,626/- owed by Prasar Bharti to the petitioner and after

adjustment, the net amount payable by Prasar Bharti/respondent No. 1 to

the petitioner was Rs.3,53,44,126/-.

Proceedings before the Tribunal:

12. It is noted that the Tribunal vide its order dated October 5, 2012

had directed disclosure of Revenue Generation Statements. The

petitioner furnished Revenue Generation Statements on July 11, 2013.

Based on these statements, the respondent No. 1 filed an application

under Section 17 of the Act before the Tribunal on July 15, 2013, inter

alia, contending that as per the petitioner‟s own showing, the petitioner

and the respondent No. 2‟s actual revenues were much less than

estimated revenue for all but one series. Even though, the respondent

No. 1/Prasar Bharti disputed the correctness but still it was its case that

one were to go by the same, the petitioner and the respondent No. 2 are

liable to pay the following admitted amount:-



Series (A)         Bid of the     Entitlement       Net Revenue    25% of the        Amount due to
                   Respondents    of the claimant   Earned as      Net Revenue       the claimant as
                   (B)            As per Bid        Per the        Earned            per the figures
                                  (25%) of (B)      Respondents    (E)               provided by the
                                  (C)               (D)                              Respondents
                                                                                     (F)
India              38,40,00,000   9,60,00,000       30,17,22,477   7,54,30,619.00    9,60,00,000
Australia 2007
India Bangla Pak   10,10,00,000   2,52,50,000       9,12,51,122    2,28,12780.50     2,52,50,000

India England      2,20,50,000,   5,48,25,000       13,21,76,437   3,30,44,109.25    5,48,25,000

India Sri Lanka    7,02,00,000    1,75,50,000       20,67,69,688   5,16,92,422.00    5,16,92,422

Total              57,72,50,000   19,36,25,000      73,19,19,724   18,29,79,930.80   22,77,67,422



 It accordingly made the following prayers:-

(a) direct the respondents to deposit an amount of Rs. 22,77,67,422/- alongwith appropriate interest and/or furnish a Bank Guarantee for the said, amount so as to secure the amount in dispute;

(b) secure the amount of Rs. 22,77,67,422/- alongwith appropriate interest in such other mariner is this Hon'ble Tribunal may deem fit; and

(c) pass such other order as deemed fit in the circumstances of the case.

13. Suffice to state, the petitioner and the respondent No. 2 had

opposed the application and sought the dismissal of the same.

14. It may be noted here that the respondent No. 1/Prasar Bharti had

also filed an application on September 13, 2013 for making an interim

award in the sum of Rs.22,77,67,422/-. In reply, the petitioner had

denied that it had made any admission as alleged by the respondent No.

1/Prasar Bharti. Both the applications were initially heard on November

11, 2013 when Mr.Rajeev Sharma, learned counsel for the respondent

No. 1 had concluded his submissions. On the request of the learned

Senior Counsel for the petitioner and the respondent No. 2, the matter

was adjourned to February 3, 2014. On that date, the petitioner filed two

applications; one for adjourning the matter and the other for allowing

inspection and discovery of a number of documents. The Tribunal

adjourned the matter to March 8, 2014 by directing the respondent No. 1

to give inspection of the documents required by the petitioner. On that

day, it was reported by the learned counsel for the petitioner and the

respondent No. 2 herein that the inspection was incomplete in certain

particulars. The matter was accordingly adjourned to May 2, 2014 on

which date, the counsel for the petitioner and the respondent No. 2 came

forward with fresh objections stating that inspection was not fully

granted, that the copies of the documents required, were not given. The

Tribunal thought it fit not to postpone the hearing of the respondent No.

1‟s application awaiting the result of the inspection and discoveries

sought by the petitioner and respondent No. 2. The reasoning given by

the Tribunal was admittedly inspection and discovery of the several

documents asked for by the petitioner and respondent No. 2 were either

to substantiate their claim/counterclaim or with a view to enable them to

increase the amount claimed by them by way of counterclaim and

because those claims were yet to be established at the trial. It may be

pointed out here that the Tribunal had heard the arguments of the learned

Senior Counsel for the petitioner and the respondent No. 2 on the

respondent No.1‟s application. The application under Section 17 dated

July 15, 2003 was decided on May 06, 2014 by the Tribunal (as per

majority) whereby it directed the petitioner and the respondent No. 2 to

furnish a bank guarantee in a sum of Rs.20 Crores in favour of the

respondent No. 1 within three weeks‟ from that date. The bank

guarantee was to be obtained from a nationalized bank in India and was

to be unconditional, payable on demand by the respondent No. 1 without

demur or objection. The said bank guarantee was to be kept alive by the

petitioner and the respondent No. 2 pending arbitral proceedings. At the

same time, the respondent No. 1 was to invoke the bank guarantee,

subject only to the orders of the Tribunal. It may be noted here that the

other application for interim award filed on September 13, 2013 was

kept pending awaiting the compliance of the order dated May 6, 2014.

15. Hon‟ble Mr. Justice V.N.Khare had given a dissenting order

whereby he was of the view that the respondent No. 1 herein, the

claimant before the Tribunal owed certain amounts to the petitioner and

the respondent No. 2 for which they have filed a counter claim.

According to him, the counter claim by the petitioner and the respondent

No. 2 was in the nature of set off, the amount due to them, being an

accounting adjustment which only could be done after looking into the

evidence led by the parties.

16. Justice V.N. Khare was of the view that the petitioner and the

respondent No. 2 in order to substantiate their case has prayed for

production and inspection of the documents by the respondent No. 1,

which has been allowed by the Tribunal and since the production and

inspection of the documents was not complete, the consideration of the

applications on merit be deferred and be taken after the evidence is led

by the parties. The order dated May 6, 2014 was challenged by the

petitioner herein in Arb. Appeal No. 15/2014 before this Court. The

initial hearing in Arb. Appeal No. 15/2014 was held on July 4, 2014

when notice was issued for July 7, 2014. On July 7, 2014, time was

sought by the learned counsel for the respondent No. 1/Prasar Bharti

which request was acceded to and the matter was posted for August 26,

2014. On August 26, 2014, further time was sought by the learned

counsel for the respondent No.1. On the said date, it was clarified by the

Court that there is no stay in the case and the Tribunal may continue with

the proceedings. Accordingly, the Tribunal heard the application dated

September 13, 2013 on September 12, 2014 and vide the order dated

September 16, 2014 (as per majority) was of the view that it was a fit

case where an interim award should be made. However, with a view to

provide a final chance to the petitioner and the respondent No. 2 to show

their bona fides, it was directed that they may deposit with the

respondent No. 1 an amount of Rs.22 Crores on or before November 1,

2014 through a bank demand draft from a nationalized bank in India.

The learned Tribunal also observed that in case the petitioner and the

respondent No. 2 failed to make such deposit, an interim award would

follow awarding a sum of Rs. 22,77,67,422/- in favour of the respondent

No.1. Justice V.N. Khare in his disserting order was of the view that the

petitioner and the respondent No.2 in their reply have used the

expression "adjustment of liabilities". The said expression cannot be

construed as admission of claim by them. In law, the admission must be

an equivocal and without reservation. The expression „adjustment‟ does

not amount to admission and in his view the consideration of the

application need to be deferred. I may state here that the learned Senior

Counsel for the petitioner and the respondent No. 2 had argued before

the Tribunal on September 12, 2014, only one aspect that when there is a

counter claim, no decree should follow in favour of the respondent No.1

even if the respondent No.1‟s claim is admitted by the petitioner and the

respondent No.2. In that regard, he had cited three judgments.

17. The order dated September 16, 2014 was also challenged by the

petitioner before this Court vide Arb. Appeal No. 30/2014. The learned

Single Judge directed the Arb. Appeal No. 30/2014 be listed along with

Arb. Appeal No. 15/2014

18. That on December 11, 2014, Tribunal, has by referring to its

earlier order dated September 16, 2014 and noting the failure of the

petitioner and the respondent No. 2 to deposit the sum of Rs.22 Crores

gave a declaration that the interim award has come into effect and issues

to be determined are the interest on the amount awarded by the interim

award and the counter claim of the petitioner and respondent No.2. It is

pursuant thereto, the present petition has been filed challenging the

interim award dated September 16, 2014.

The submissions:

19. Mr.Jayant Bhushan, learned Senior Counsel appearing for the

petitioner would submit that the petitioner had never acknowledged its

liability towards the respondent No. 1 nor admitted the claim of the

respondent No. 1 and the conclusion of the Tribunal is not tenable. He

would refer to the legal notice dated May 16, 2009 to contend that the

claim of the respondent No.1 against six matches need to be adjusted

against the money owed by the respondent No. 1 to the petitioner against

India-Pakistan Series 2007 for which the respondent No. 1 was the RMC

and also the money owed by the respondent No. 2 to the respondent No.

1/Prasar Bharti and on such adjustments, the respondent No. 1 rather

owes the petitioner an amount of Rs.3,53,44,126/-. The notice only

stated that liability was discharged by way of an adjustment. He would

also state that a reading of averments in paragraphs 36, 37, 61, 69, 78 of

the claim petition and paragraphs 27, 28, 47, 48, 54 and 61 of the

defence statement would show that the petitioner had specifically denied

the claims. He would also state that the claim of the respondent No. 1 in

its application for interim award was also denied by the petitioner in its

reply. He would rely upon the following judgments in support of his

contention that there was no unequivocal and/or absolute and/or

unconditional admission by the petitioner to the claims made by the

respondent No. 1:

(i) Valliamma Champaka Pillai Vs. Sivathanu Pillai and Ors.,

(1979) 4 SCC 429

(ii) Himani Alloys Ltd. Vs. Tata Steel Ltd., (2011) 15 SCC 273

(iii) Western Coalfields Ltd. Vs. Swati Industries, AIR 2003 Bom

20. Learned Senior Counsel also contends that the impugned order

could not have been passed without considering the counter claim of the

petitioner. According to him, it was the case of the petitioner that the

respondent No. 1 was the RMC for India-Pakistan Series 2007 and had

booked advertisements for 16,549 extra seconds over and above the

contractual time of 30000 seconds and the petitioner is entitled to the

revenue for those extra seconds. According to him, on the face of the

counter claim, the interim award overlooking the counter claim in a

piecemeal by accepting the version of the respondent No. 1, is not

tenable. He would rely upon the judgment of the Supreme Court in the

case of K.V. George Vs. Secretary to the Govt., Water and Power

Department, Trivandrum and Anr. (1989) 4 SC 595.

21. It was also his contention that the interim award is bad as the same

was passed without considering the issue of limitation specifically raised

by the petitioner. According to him, the issue of limitation was a

substantive issue having a bearing on the maintainability of the claims

and could not have been overlooked. He would also state that the

interim award passed on the ground of non-compliance of the interim

order is also bad in law. In that regard, he would reiterate that interim

award is in the nature of a final award, to the extent of the claims made

by the respondent No. 1 and such award ought to have been passed after

adjudicating the claims of the parties in accordance with the law on the

basis of the material available on record. He would also state that the

interim award passed on a speculation that the petitioner does not have

sufficient assets, is bad in law. He states that on May 2, 2014 while

hearing the application for interim order, the Tribunal, for the first time,

had asked the counsel for the petitioner about the assets of the petitioner

company. The counsel for the petitioner company sought time to seek

instructions. However, without providing an opportunity to furnish

details of assets of petitioner, the Tribunal passed the interim order.

Subsequently, on the same ground, interim award came to be passed. In

the last, it was his submission that the award is against the principles of

natural justice inasmuch as the petitioner had filed an application for

inspection of discovery of documents, to be furnished by the respondent

No.1. However, the inspection of the documents was not complete which

was noted by the Tribunal in its order dated March 8, 2014. By the said

order, the Tribunal directed the parties to file applications for the

discovery of documents and posted the matter for hearing the said

applications on May 02, 2014. Surprisingly, on May 2, 2014, the

Tribunal observed that it was not necessary to adjudicate the applications

for discovery of documents at that stage, and proceeded with the hearing

and passed the interim order and ultimately, for non-compliance of the

interim order, interim award came to be passed in favour of the

respondent No. 1.

22. It was his submission that the interim award need to be set aside to

enable the Tribunal to decide the respective claims and counter claim of

the parties together.

23. On the other hand, Mr.Rajeev Sharma, learned counsel for the

respondent No. 1 would justify the interim award dated September 16,

2014 (as per the majority), which according to him, was passed because

of unequivocal admissions in the pleadings. In this regard, he has drawn

my attention to averments made in paragraphs 24, 28, 36, 49, 60, 61, 63,

71 of the claim petition and paragraphs 23, 27, 38, 48, 50 and 56 of the

reply to the claim petition to highlight the admissions of the petitioner

and the respondent No. 2, which relates to the amounts payable for the

India-Australia ODI Series 2007, India-Australia T-20 Matches 2007,

India-England Series 2008, India- Bangladesh-Pakistan Triangular Series

June 2008 and India-Sri Lanka Cricket Series 2009. He would also refer

to the letter dated April 2, 2008 and its Annexure-I with regard to the

India-Australia Series 2007 to show that as per the petitioner itself,

respondent No. 1/Prasar Bharti‟s share of 25% of Net Projected Revenue

was Rs.9,00,84,643/- which along with notice dated May 16, 2009 is an

acknowledgement of the subsisting liability. He would state that the

mandate to adjust the amounts due from the petitioner to the respondent

No. 1/Prasar Bharti was unequivocal admission of its liability. He would

deny the counter claim of the petitioner with regard to the extra seconds

having not paid by the respondent No. 1/Prasar Bharti as fictional.

According to him, 75% of the revenue realized from the sale of

commercial time had already been paid to the petitioner and the amount

of Rs.60,93,75000/- is not limited to 75% of the 30,000 seconds. He

would state, till such time, the counter claim of the petitioner is

adjudicated, it is still a claim. In any case, it is his case that the counter

claim of the petitioner has not been admitted unlike the claims of the

respondent No. 1 by the petitioner and the respondent No.2.

24. On limitation, it is his submission that no such objection was

raised at the time of hearing. According to him, the same is clear from

the fact, even the dissenting order of Justice V.N.Khare dated September

18, 2014 does not refer to the point of limitation. According to him, the

only point urged before the Tribunal was, even if the claims have been

admitted by the petitioner, no decree should follow, since there is a

counter claim. He would state that even in the petition before this Court,

it is not averred that the issue of limitation was pressed at the time of

hearing and the same was ignored. The only reference to the limitation

in the petition is in the ground, in paragraph 3.20, which also does not

state, the issue was pressed at the time of hearing.

25. Even on merits, it is his submission that the dealings between the

parties took place between the years 2007-09, the arbitration was

invoked by the respondent No. 1 in June, 2009; statement of claim filed

in January 2012, which is within limitation period. According to him,

even if the limitation is accounted from the date of adjustment was

conveyed i.e. May 16, 2009, the claim is within limitation. He would

state that explanation to Section 18 of the Limitation Act provides that

an acknowledgement can be coupled with a refusal to pay or claim for

set off.

26. It is his case that the pendency of the counter claim was no bar to

the passing of an interim award to the extent the claim was admitted.

According to him, a counter claim is nothing but a cross suit. A Court,

in its discretion, can order it to be tried separately. So, can the Tribunal.

According to him, the claim was admitted and counter claim was

disputed. He would state, any view contrary, would reduce the

provisions of Order 12 Rule 6 CPC a dead letter inasmuch all one has to

do to avoid a decree on admission, is only prefer a counter claim. He

would state that the judgment of the Supreme Court in K.V.George

(supra) is not an authority for proposition that an interim award cannot

be made on the basis of an admission on account of a pendency of a

counter claim. It is his submission that the petitioner, all throughout, had

avoided to discharge its liability towards the respondent No. 1 on one

pretext or the other. The initial order to give a bank guarantee was not

complied with by the petitioner. Even the impugned order dated

September 16, 2014, directs the petitioner to deposit the amount of Rs.22

Crores on or before November 1, 2014 which was also not complied

with. He would also state that between the period 2007-2009, the

petitioner neither opened an Escrow Account; nor gave bank guarantee

for 25% nor paid any amount for the Series/events where the petitioner

and the respondent No. 2 were the RMC, despite the Act and the Rules

stipulated so. He has relied upon the following judgments in support of

his case and would seek the dismissal of the petition:-

(i) State of Maharashtra Vs. Ramdas Shrinivas Nayak, (1982) 2 SCC 463

(ii) Union of India Vs. Karam Chand Thappar and Bros. (Coal Sales) Ltd., (2004) 3 SCC 504

(iii) Numero Uno International Ltd. Vs. Prasar Bharti, FAO

(OS) 507/2007

(iv) Nagindas Ramdas Vs. Dalpatram Ichharam (1974) 1 SCC

(v) Mcdermott International Vs. Burn Standard Co. Ltd., (2006)

11 SCC 181

(vi) Shikharchand Vs. M/s. Bari Bai and Ors., AIR 1974 MP 75

(vii) Iron & Hardware (India) Co. Vs. Firm Shamlal & Bros,

AIR 1954 Bombay 423

(viii) Jabed Sheikh Vs. Taher Malik, 45 CWN 519

(ix) Gammon India Ltd. Vs. Sankaranarayanan Construction,

OMP No. 628/2008 (Madras High Court)

27. Mr.Jayant Bhushan, learned Senior Counsel for the petitioner, in

his rejoinder to the submissions made by Mr.Rajeev Sharma would state

that the interim award can only be passed when there is no counter claim

by the other party. In other words, according to him, if there are claims

by one party and no counter claim by the other to the extent the claims

are admitted by the other party, the interim award can be passed.

According to him, the judgment of the Supreme Court in K.V.George

(supra) is exactly on this proposition where the claim was adjudicated

overlooking the counter claims and the Supreme Court has held that the

High Court could not have done it. He would state that even if there

were admissions, interim award could not be passed in view of the

counter claim. He would lay stress on the fact that the claims made by

the respondent No. 1 were beyond the period of three years. He would

refer to Section 18 of the Limitation Act to contend, there was no

acknowledgement of debt/liability. He states, that, even assuming there

was an acknowledgment of liability, still, the claims need to be within

limitation w.e.f. April 2, 2008. He reiterated his submission on extra air

time to contend that the petitioner was entitled to revenue for 16549

extra seconds which amounts to Rs. 19,86,82,487/-.

28. On the other hand, Mr.Rajeev Sharma would reiterate that even

the letter to set off dated May 16, 2009 is an acknowledgement and the

time would get extended in terms of Explanation to Section 18 of the

Limitation Act. He would refer to the order dated September 16, 2014 to

highlight, the limited submission made by the learned Senior Counsel for

the petitioner.

29. Both the parties have filed their respective written submissions.

30. Having heard the learned counsel for the parties and considered

the written submissions made by them, the first and foremost point need

to be decided is whether, there was an unequivocal admission on the part

of the petitioner and the respondent No. 2 of their liability towards

respondent No. 1. In this regard, it is relevant to refer to the averments

made in the claim petition and the corresponding reply of the petitioner

and the respondent No. 2 before the Arbitral Tribunal. I reproduce the

relevant paragraphs to appreciate the respective stand of the parties:

Series             Averments in the claim                               Reply to claim
India Australia    24. That in September-October, 2007 an India-        Reply to para 24 (Not replied).
Cricket Series,    Australia series, was scheduled to be played in.
2007               India. The said series comprised of seven ODI's      Reply to para 27:
(Refer to letter   and one T-20 match. Nimbus Communications            22.With reference to paragraph 27,
dated              Ltd. was the rights holder in respect of the said     this respondent repeats and reiterates
02.04.2008)        series. Meetings took place on September 17, 18,     the reply to paragraph 26 and the
                   19 & 20, 2007 between the officials of the           contents of the record of discussions
                   claimant and respondent no. 1 for finalising         are evident from the documents

arrangements for the sharing of the signals of the except that it was not binding upon the matches by respondent No. 1 with the claimant respondent No. 2. and marketing of commercial time associated with such telecasts.

XXX

28. Thereafter by way of a bidding process held Reply to para 28: on 20.9.2007, Respondent No. 1 was appointed 23. The contents of paragraphs 28 as the Revenue Management Company for the and 29 do not call for any comments ODI matches since it had offered a net projected from this Respondent. revenue of Rs. 35.30 crore as against the offer of Rs. 35 crore made by the claimant for the ODI's. The bids submitted by the parties for the ODI's are annexed as ANNEXURE-G. A separate meeting for appointing the RMC for the T.20 match was held on 19.10.2007. Respondent No.1 was appointed as the RMC since it had offered Rs. 3.10 crore for the T-20 match as against the offer of Rs. 2.8 crore by the claimant. The bids submitted by the parties for the T-20 match are annexed as ANNEXURE-H.

                   XXXX                                                 Reply to para 36:
                   36. In response to the letter dated 31.3.2008,       27. With reference to paragraph 36, it is denied
                   respondent No.1 sent a letter dated 2.4.2008         that the 1st Respondent's plea that its auditors had
                   along with which it forwarded an unaudited            refused to conduct the audit till the signed
                   revenue generation statement on the specious          agreement was shown to them was a specious
                   plea that "our auditors have refused to conduct       plea. As a matter of fact and, practice and order



                    an audit, till we share with them the signed          requirement, the auditors always require a signed
                   agreement between PB/Nimbus for this event".          agreement before they can conduct an audit. In
                   As per the said statement also an amount of            the instant case Prasar Bharati failed and neglected to sign
                   Rs.8,23,24,643/- was payable to the claimant for      the agreement and as such the auditors did not
                   the ODI series and an amount of Rs.77,50,000/-         proceed with their task of conducting the audit.
                   was payable for the T-20 match. Thus the total         There are no payments due from the Respondents
                   amount payable as per respondent No.1 itself           towards the Claimant and all payments have
                   was Rs.9,00,74,643/-. A copy of the letter dated       already been, made by the Respondents. No claim
                   2.4.2008 sent by respondent No.1 is annexed as        can now subsist from the Claimants against the
                   ANNEXURE-R.                                            Respondent.

                   37. Thereafter by a letter dated 26.6.2008 the        Reply to paragraph 37:

claimant called upon respondent No.1 to at least 28. With reference to paragraph 37, it is denied pay the amount, which as per its own unaudited that a sum of Rs.9,00,74,643/- was due or payable statement was due to the claimant. A copy of the from the Respondent No.1 to the Claimant, letter dated 26.6.2008 is annexexd as The letters of demand notwithstanding it is ANNEXURE-S. Thereafter a reminder dated submitted that the Claimant's share would have 18.7.2008 was sent to respondent No.1, whereby become due after the audit process was completed it was called upon t pay Rs.9,00,74,643/- and to and this could not be carried out since there was provide an audited statement of account. A copy no signed agreement: In the circumstances of the letter dated 18.7.2008 is annexed as there is no question of making any payment of the ANNEXURE-T. Subsequently by a letter dated amount demanded. 16.10.2008 respondent No.1 was again called upon to pay Rs.9,00,74,643/-, i.e. the amount, which admittedly was due from it to the claimant as per its own unaudited revenue generation statement. A copy of the letter dated 16.10.2008 is annexed as ANNEXURE-U. However, no response was given by respondent No.1 to the claimant's said letter.

India Bangladesh 49. That an India-Bangladesh-Pakistan cricket Reply to paragraphs 49 to 52 and 51-52 Pakistan, 2008 series was scheduled to be played in Bangladesh, 38. The contents of paragraphs 49 to 52 are Cricket Series in June, 2008. The said series comprised of four substantially correct and contents of paragraph GDI's, of which three ODI's (two ODI's featuring 51 and 52 are matters of record and do not call India and the final) were sporting events of for any comments from this respondent. national importance. Respondent No. 2, Nimbus Sports International Pte Ltd. was the rights holder in respect of the said series. By a bidding process held on 21.5.2008, it was decided that respondent No. 1 would market the air time associated with the event, since it had offered net projected revenue of Rs. 10.10 crore as against the offer of Rs. 4,0 crore made by the claimant.

Accordingly Respondent No. 2 was appointed as the Revenue Management Company. The bid documents for the India- Bangladesh-Pakistan cricket series are annexed as ANNEXURE-X.

associated with the event, since it, had offered net projected revenue of Rs. 81.25 crore as against the offer of Rs. 75.60 crore net made by respondent No. 1. A formal agreement dated 3.11.2007 was executed between the parties.

XXX

60. That in the absence of the furnishing of a Reply to paragraph 60 revenue generation statement by the respondent With reference to paragraph 60, the claimant would No. 2, it is not possible for the claimant to give Have become entitled to its share of revenue an exact estimate of the amount due to it. The only upon signing of the agreement acceptable to claimant was entitled to 25% of the actual both the parties. In the circumstances the claim revenue or 25% of the net projected revenue, is vague and lacks material particulars. The whichever was higher. claimant has also made an attempt to specify its claim dispute, having knowledge of the advertisers' telecast on its own channel. It is

estopped from making any claim on this basis.

61. However, what can be stated with certainty is Reply to para 61 that if the revenue earned was less than the net- 48. With reference to paragraph 61, the contents projected revenue of Rs. 10.10 crore of which thereof are denied as speculative Rs.2,52,50,000/- constituted the guaranteed revenue share of the claimant, the claimant was at least entitled to that amount or 25% of the actual revenue, if actual revenue exceeded Rs.

10.10 crore, The requisite amount was payable to the claimant on or before 13.9.2008 but has not been paid till date. The claimant is also entitled to interest @ 18% per annum on the amount due to it w.e.f. 13th September, 2008.

India England 63. That an India-England cricket series was Reply to paras 63 to 65 Series, 2008 scheduled to be played in November-December, 50. With reference to paragraphs 63 to 65, the 2008. Respondent No. 1, Nimbus same are matters of record and do not call for Communications Ltd. was the rights holder in any specific response except that the respondent respect of the said series. The said series No. 1 is not bound to sign any agreement as comprised of seven ODI's. By the bidding proposed since the terms proposed were not process held on 27.10.2008, it was decided that acceptable to it. respondent No. 1 would market the air time associated with the event, since it had offered net projected revenue of Rs. 22.05 crore as against the offer of Rs.6.80 crore made by Prasar Bharati.

Accordingly Respondent No. 1 was appointed as the Revenue Management Company. The bid documents are annexed as ANNEXURE-AD.

India Sri Lanka 71. That an India-Sri Lanka cricket series was Reply to paras 71 and 72 Series, 2009 scheduled to be played in Sri Lanka in January- 56. With reference to paragraph 71 and 72, the February, 2009. contents are matters of record and are not in Respondent No. 2, Nimbus Sports International dispute. Pte Ltd,, was the rights holder in respect of the said series. The said series comprised of five ODI's & one T-20, out of which an arrangement under the Act was made for the four ODI's & the T-20 match (one ODI not being telecast on account of the demise of Mr. R. Venkataraman, former President of India). By the bidding process held on 27.1.2009, it was decided that respondent No. 2 would market the air time associated with the event, since it had offered net projected revenue of Rs. 7.02 crore as against the offer of Rs. 4.0 crore made by the claimant.

Accordingly Respondent No.2 was appointed as the Revenue Management Company. The bid documents are annexed as ANNEXURE-AH.

31. It may be noted here, vide letter dated April 2, 2008 the petitioner

in its communication to the respondent No. 1 has shown the sharable

revenue computation for the India Australia Series 2007 in terms of

Annexure I. The Annexure I depicts an amount of Rs.8,23,24,643/-, the

share of the respondent No. 1/Prasar Bharti i.e. 25% of the Net Projected

Revenue for the seven ODIs played in that series and Rs.77,50,000/- for

the T-20 matches. In fact, respondent No.1/Prasar Bharti, vide its letter

dated June 26, 2008 had called upon the petitioner to deposit the said

amount.

32. Also for India Pakistan Bangladesh Triangular Series, 2008, the

petitioner had bid for appointment as a Revenue Management Company

on the projected net revenue of Rs.10.10 Crores against which, the

respondent No.1/Prasar Bharti‟s share is of at least 25% i.e.

Rs.2,52,50,000/-.

33. That apart, I note, in the legal notice dated May 16, 2009, the

petitioner had acknowledged the respondent No.1‟s claim of

Rs.13,53,75,000/- and also the amount of Rs.4,12,62,500/- owed by

Nimbus Sports International Singapore to the respondent No. 1/Prasar

Bharti. Even though, in the said letter, the petitioner mentioned about

adjustment of the amount payable against the amount payable to the

petitioner on account of India Pakistan Cricket Series, 2007, the

respondent No. 1 has denied such a claim. In this regard, I may point out

the response of the respondent No. 1/Prasar Bharti in its letter dated June

24, 2009 addressed to the lawyers of the petitioner, wherein, it has taken

the following stand:

"Your letter also wrongly mentions that a sum of Rs.13,53,75,000/- is due from your client to Prasar

Bharti for the India Australia, 2007 Series comprising 7 ODIs, India Australia, 2007 T-20 match and the India England, 2008 Series. The correct amount is Rs.15,08,25,000/-. The said amount has not been paid despite numerous reminders.

In addition, Nimbus Sports International, Singapore owes to my client a sum of Rs.4,42,16,633 for the India in Bangladesh Series, 2007 India Bangladesh Pakistan Series, 2008 and the India in Sri Lanka Series, 2009. The said sums are covered by separate agreements between Prasar Bharati and Nimbus Sports International, Singapore and have not been paid despite numerous reminders.

With a view to avoid paying the legitimate dues of Prasar Bharati, which are held in trust by it, your client has raised false disputes regarding the India Pakistan and India England Series and come up with false and untenable claims. Whatever be the claims, your client has no right to withhold amounts collected for and on behalf of Prasar Bharti and due to it, nor has it the right to adjust the amounts collected for an on behalf of Prasar Bharati by Nimbus Sports International, Singapore and payable by Nimbus Sports International Singapore to Prasar Bharati. The alleged mandate by Nimbus Sports International, Singapore in favour of your client is illegal, of no avail and indicative of the criminal conspiracy between your client and Nimbus

Sports International Singapore to misappropriate amounts held in trust for and on behalf of Prasar Bharati.

In the circumstances, we hereby call upon your client to pay to Prasar Bharti the aforesaid sum of Rs.15,08,25,000/- alongwith interest thereon @ 18% per annum in terms of my client's letters dated May 26, 2009 (bearing Nos. 2/41/2007-PX, 2/41/2007-PX & 2/20/2008-PX) within fifteen days of the receipt of this notice, failing which we shall be constrained to initiate appropriate criminal and civil proceedings against your client and all persons in charge of and in control of its affairs".

34. That apart, from the pleadings of the parties before the Tribunal ,

it is noted, the petitioner has not denied the offer of net projected

revenues, for the India England Series 2008, and India Sri Lanka Series,

2009, which would entail Prasar Bharti/respondent No. 1 a revenue of at

least 25% of the projected revenues.

35. In the application filed under Section 17 of the Act, the respondent

No. 1/Prasar Bharti, has stated that the amounts due to it is as per the

figures provided for by the petitioner and the respondent No. 2. In reply

to para 11 of the application, on a stand of the respondent No. 1 for a

claim of Rs.22,77,67,422/-, the petitioner has stated as under:

"11. The respondent No. 1 is, therefore, entitled to receive

the said sum of Rs. 19,86,82,487/- with interest thereon at such rate as this Tribunal may grant from the date on which the claimant paid to the respondent No. 1 the sum of Rs. 60,93,75,000/-. It is further submitted that the claimant has filed audited revenue statement on or about 22.07.2013 in this proceeding in an attempt to show that the shareable revenue generated on the telecast of the India Pakistan 2007 Cricket Series was Rs.83,10,74,358/-. The said certification is far from accurate and it has suppressed additional time sold by the claimant such special properties and standard commercial elements such as Aston Bands, Action Reply Bugs, Third Umpire Lights, On Air Graphics, Two Super (All pull through) per Over, End of Match packages etc. contemplated in Clause 10 of the agreement for revenue management dated 3.11.2007 between the claimant and respondent No. 1. It is denied that the respondents were liable to pay a sum of Rs.19,36,25,000/- or any part thereof or that it raised false claim of Rs.21 Crores as alleged or at all. It is vehemently denied that the respondent is making any fraudulent claim in relation to the Indi Pakistan Series as alleged or at all".

36. There is no whisper in reply to para 11 that the amount of

Rs.22,77,67,422/- was not payable to the respondent No. 1/Prasar Bharti

against the four series/events. I note, the petitioner had raised the issue

of India Pakistan Series 2007 in reply to this para, the same shall be

subject to the determination by the Tribunal.

37. Suffice to state, from a reading of the letters/legal notice, the

pleadings referred to above, the petitioner claims to have adjusted the

amounts payable by it against the revenue it has to get for the India

Pakistan Series 2007. The petitioner and respondent No. 2 admit their

liability to that extent by giving credit to the respondent No. 1. In other

words, the admission is implicit in the very stand of the petitioner. On

admissions, an interim award can be passed as admissions are best proof

of facts admitted. It has been held in Nagindas Ramdas's case (supra)

as under:

Admissions if true and clear, are by far the best proof of the facts admitted. Admissions in pleadings or judicial admissions, admissible under Section 58 of the Evidence Act, made by the parties or their agents at or before the hearing of the case, stand on a higher footing than evidentiary admissions. The former class of admissions are fully binding on the party that makes them and constitute a waiver of proof. They by themselves can be made the foundation of the rights of the parties. On the other hand, evidentiary admissions which are receivable at the trial as evidence, are by themselves, not conclusive. They can be shown to be wrong".

38. The question which is required to be answered is whether the

amount of Rs.22,77,67,422/- can be a subject matter of an interim award

when a counter claim has been filed by the petitioner. The issue is no

more res-integra having been decided by a Division Bench of this Court

in the case of Numero Uno International Ltd. (supra) wherein the

Division Bench on an identical issue on more or less identical facts was

of the following view:-

"6.What then remains to be examined is whether the pendency of a counter claim made by the appellant before the arbitrator was sufficient to dis-entitle the respondent Prasar Bharti from claiming even the admitted amount due from the appellant by way of an interim award in its favour. According to Mr.Jaitley, since the claim made by the respondent and the counter claim of the appellant were eventually to result in a net amount which one or the other party would be required to pay, the payment of any amount which the appellant may have admitted to be due and payable out of the claim made by the respondent would not meet the ends of justice nor was any such payment otherwise necessary. We do not however think so. The legal position as regards the nature of a set off and counter claim was examined in Canara Bank's case (supra) and summarised thus:

"34. The following things are in common in set off and counter claim:

(1) None should exceed the pecuniary limits of the jurisdiction of the Court;

(2) Both are pleaded in the written statement, if the law governing the Court permits such plea being raised by the defendant in the written statement;

(3) The plaintiff is expected to file a written statement in answer to a claim for set off or to a counter claim;

(4) Even if permitted to be raised, the Court may in appropriate cases direct for set off or counter claim being tried separately;

(5) A defendant cannot be compelled to plead a set off nor a counter claim; he may as well maintain an independent action for enforcing the claim forming subject matter of set off or counter claim;

(6) Both are liable to payment of court fee under Sch. 1 Art. 1 of Court-fees Act, 1870; (7) Dismissal of suit or its withdrawal would not debar a set off or counter claim being tried, may be followed by a decree against the plaintiff."

7. In the light of the above, there is no gainsaying that the making of a counter claim is tantamounting to institution of an independent suit for the adjudication of

the claim of the defendant. Not only court fee is payable on the counter claim but the counter claim remains unaffected by the claim is a suit in itself. So also the court has always the power to direct a set off or counter claim being tried separately from the original suit. Such being the legal nature and character of a counter claim, its pendency does not denude the arbitrator of the power to make an interim award in the original suit/claim if such an interim award is otherwise justified. What is significant is that the legality of an interim award may be tested by reference to the material on which it is based rather than the areas of dispute that may still call for adjudication between the parties. If an interim award on the basis of material available on record is not justified, the Court may set aside the same under Section 34 of the Act. No interference with an interim award would, however, be permissible only because the defendant has made a counter claim or because some areas of dispute independent of the area covered by the interim award remains to be resolved."

39. It may be noted here that the judgment of Division Bench of this

Court in Numero Uno International Ltd. (supra), has been followed by

a Single Judge of the High Court of Madras in Gammon India Ltd.

(supra).

40. Insofar as the judgment of the Supreme Court in K.V. George

(supra), on which reliance has been placed by Mr.Jayant Bhushan, is

concerned, I note the said judgment is distinguishable on facts. In K.V.

George (supra), the Supreme Court was considering a case where the

appellant before the Supreme Court, a contractor entered into an contract

with respondent on April 22, 1978 in connection with a construction of

an embankment across Musaliyar Podom between chainage 2573.5 M

to 2827 M of E.B. Main canal of Kallada Irrigation Project. Under the

contract-agreement, the work was to the completed by March 30, 1980

i.e. two years from the date of selection notice which was dated March

30, 1978. The appellant having failed to complete the work as per the

terms of the contract, the respondent by a notice dated April 26, 1980

cancelled the contract at his risk and cost. Consequent there-to the

appellant filed a claim being Arbitration Case No.132/1980 before the

named Arbitrator claiming enhancement of rates in respect of the earth

work involved in the contract. He also claimed interest on delayed

payment and costs. The second respondent i.e. respondent, No. 2-

Superintendent Engineer (KIP Circle), filed a defence statement denying

its liability for enhancement of rates. It was their case that the extra and

excess items were covered by the supplemental agreement. The

department has also alleged, the delay was attributable to the contractor.

A counter claim was made by the Superintending Engineer

(K.I.P.Circle), for Rs.28,84,000/-. The Arbitrator by his order dated

January 22, 1981 made an award in regard to claim No. 1 directing the

respondents to pay 35% increase in the agreed rate for the item of Earth

work excavation and filling for forming the compacted embankment

with earth from barrow area. Claim No. 1 was thus allowed. Claim Nos.

2 and 3 regarding interest were disallowed. As regards counter-claim

Nos. 1 and 2, it was ordered that those issues will be considered

separately and no award was made. The appellant thereafter filed O.P.

(Arb.) No. 81 of 1981 in the court of Sub-Judge, Trivandrum under

section 14 of the Arbitration Act for making the award a rule of the

court. On objections being raised by the respondents, the Court of the

Sub-Judge after hearing the parties by order dated August 18, 1981

remitted the reference to the Arbitrator for fresh consideration on the

ground that the Arbitrator did not consider the counter claims made by

the respondents. The appellant thereafter filed an application in the court

of Sub-Judge praying that the order dated August 18, 1981 may be

reviewed. In the, meantime, the appellant filed another Arbitration Case

No.276/1980 before the same Arbitrator in respect of the wrongful

termination of the contract and also raised 13 items of claims therein.

The Arbitrator after going through the objections of the respondents

made an award on October 29, 1981 whereby he ordered that the re-

arrangement of the work should not be at the risk and cost of the

appellant. As regards claim No. 2, he ordered 30% increase in rates (as

per original and supplemental agreement) for all items of work carried

out by the appellant except on items covered by Award No. 132 of 1980

dated January 22, 1981. Claim Nos. 3 and 5 were rejected. As regards

claim No. 4 an increase of 20% in the agreed rates for these items was

allowed. Claim No. 11 regarding interest was disallowed. It was also

stated in the award, inter alia, that the claimant shall be entitled to the

refund of the security amount as well as refund of the retention amounts,

the claimant shall be entitled to his final bill in terms of the Award, the

counter claim for recovery of costs of rearrangement of work and also

the counter claims filed by the respondent dated April 8, 1981 were

declined. The appellant filed O.P. (Arb) No. 296 of 1981 for making the

second award a rule of the court. A statement of defence was filed by the

respondents. The respondents raised a plea of res judicata. The Sub-

Judge, vide order dated March 18, 1982 made the award the Rule of the

Court, dismissing the plea of res-judicata raised by the respondents. The

respondents filed two appeals before the High Court at Ernakulam,

which held that the Arbitrator could not review its order on the facts of

the present case, so allowed one appeal. Insofar as the other appeal is

concerned, the same was allowed holding that the principles of

constructive res judicata would apply to the arbitration case. The

question which fell for consideration before the Supreme Court was

whether the Sub Judge could have remanded the case back to the

Arbitrator insofar as the first case is concerned. The Supreme Court was

of the view that the Arbitrator, without considering the counter claims

and keeping the same for subsequent consideration made an award. It

held that the award made by the Arbitrator is not sustainable in law. It

upheld the order of the High Court whereby the High Court held that the

Arbitrator misconducted himself and had set aside the proceedings by

directing the Arbitrator to dispose of the reference in accordance with the

law, considering the claim of the contractor and the counter claim of the

respondents.

41. It is clear from the above, in K.V. George (supra), the claim of the

petitioner allowed by the Arbitrator was for enhancement of rates which

claim was denied by the department. Some counterclaims were made by

the department. The claim allowed, was not on an admission by the

department. Unlike in K.V. George (supra), where there was no

admission of liability, in the case in hand there were admissions of

liability by the petitioner herein and on admissions, the interim award is

justified.

42. It is a settled position of law that a judgment is only an authority

for what it actually decides in particular facts.

43. Insofar as the reliance placed by Mr.Bhushan on the case of

Himani Alloys Ltd. (supra) is concerned, the Supreme Court was

dealing with a case wherein a suit was filed by the respondent TISCO

against the appellant for recovery of sum of Rs.2,02,72,505/40 in regard

to supply of steel. The respondent filed an application praying for a

decree upon admission for Rs.74,57,074/50 alleging that the appellant

has admitted the liability for such sum. The said application was resisted

by the appellant contending that there was no such admission and was

only a tentative agreement to have the accounts verified and not a final

settlement or admission of liability. The Supreme Court in para No.9 was

of the view that a judgment can be given on an admission but the

admission should be categorical. The Supreme Court was also of the

view that Order 12 Rule 6 being an enabling provision the power of the

Court is discretionary. The Supreme Court further observed that on

examination of facts and circumstances the Court has to exercise its

judicial discretion keeping in mind that a judgment on admission is a

judgment without trial which permanently denies any remedy to the

defendant by way of an appeal on merits. The Supreme Court in the

facts has held that the Minutes of Meeting on which reliance was placed

by the TISCO could not be termed as an admission for the purpose of

Order 12 Rule 6 CPC. The facts in the said case are different from the

facts in the case in hand. Hence, the said judgment is distinguishable. In

this case the pleadings and the communications/correspondence are clear

and have been dealt with above and on the basis of which this Court has

held that the petitioner and the respondent No.2 have accepted their

liability towards the respondent No.1.

44. Insofar as the judgment of Bombay High Court in the case of

Western Coalfields Ltd. (supra) is concerned, the said case has been

decided keeping in view the fact situation. The Court on a reading of the

pleadings has come to a finding that the admissions made by the

defendant are not absolute but were conditional and it has been

specifically stated that in terms of another contract the said amount is

already appropriated. Unlike in Western Coal Fields Ltd's case (supra),

in the case in hand the liability towards the respondent No.1 is not

disputed even though plea of set off was taken, which was disputed by

the respondent No.1, as such a plea need to be decided and till such time

it is decided it would, remain a claim and not a debt, for the respondent

No. 1 to be pecuniarily liable. Even though Mr. Rajeev Sharma has

made submissions on the merit of the counter claim of the petitioner, I

refrain from saying anything as the same needs to be decided by the

Tribunal. That would not stop the entitlement of the respondent No.1 to

get money on the basis of admissions with regard to 4 series/events. As

held by the Division Bench of this Court in Numero Uno International

Ltd.'s case (supra), if a liability is admitted the amount can be awarded

by the Arbitrator, which has been done in the present case.

45. Insofar as the submission of Mr.Jayant Bhushan, learned Senior

Counsel for the petitioner, on limitation is concerned, on a reading of the

impugned award it is seen and noted that no such plea was urged before

the Tribunal. The only submission advanced by the learned Senior

Counsel for the petitioner before the Tribunal was that the interim

award/decree cannot be granted in view of the counterclaim. In the

absence of any submission on limitation, there was no occasion for the

Tribunal to consider and decide the issue of limitation. There is no

jurisdictional error.

46. The submission of Mr.Jayant Bhushan that the legal notice dated

May 16, 2009 cannot be construed as an acknowledgement of existing

liability as the liability was discharged by way of an adjustment by

relying on the judgment of the Supreme Court in Valliama Champaka

Pillai's case (supra) is concerned, the same also need to be rejected in

view of my conclusion above that till such time, the claim of the

petitioner with regard to India Pakistan Series 2007 is decided, it would

remain a claim and would not fructify as a "liability" to be adjusted.

47. In Valliama Champaka Pillai's case (supra), the Supreme Court

was dealing with a case where the release deed executed by the original

mortgagee referred to a past liability. The deed also recorded that the

payment has been made. It was in that context, the Supreme Court held

that it does not amount to a subsisting liability.

48. Insofar as the submission of Mr.Jayant Bhushan that the limitation

had started running on April 02, 2008 and the reference having been

made to the Arbitral Tribunal on August 31, 2011 the claims were barred

by time, is concerned, this submission of Mr.Jayant Bhushan also need

to be rejected for the reason that vide letter dated April 02, 2008 the

petitioner had acknowledged the liability of the petitioner and the

respondent No.2 towards the respondent No.1/Prasar Bharti with regard

to India Australia Series 2007 only. Vide notice dated May 16, 2009 the

acknowledgment of liability was with regard to most of the matches

played between the years 2007-2009 and included the India Australia

Series, 2007 as well. I agree with the submission of Mr.Rajeev Sharma,

learned counsel for the respondent No. 1 who had placed reliance on

Explanation to Section 18 of the Limitation Act which stipulates that for

the purpose of the said Section, acknowledgment may be sufficient if it

is coupled with a claim to set off. The letter dated May 16, 2009 is an

acknowledgement of liability with a stand of adjustment and the

invocation of arbitration clause was vide letter dated June 1, 2009, the

agreement executed between the parties to refer to the disputes to the

Arbitral Tribunal was on August 31, 2011 and the claims having been

filed in January 2012, the claims would be within time.

49. Insofar as the submission of Mr. Jayant Bhushan that the interim

award was passed only because the petitioner had not complied with the

interim order is concerned, I do not see anything illegal. The Tribunal

has granted the interim award after noting the non compliance of first

interim order dated May 6, 2014 to furnish a bank guarantee; failure to

deposit an amount of Rs.22 Crores on or before November 1, 2014, and

also failure to state clearly whether they possess any assets within India.

In fact I note, despite order dated October 31, 2014 in Arb. Appeal

No.30/2014, the petitioner neither in that appeal nor even in this petition

has filed details of its unencumbered assets located in this country. In the

given circumstances, as it is a settled law, a decree on admission under

Order 12 Rule 6 C.P.C. is a discretionary relief and the Tribunal having

exercised the discretion by way of an interim award, the same cannot be

interfered with.

50. Insofar as, the submissions of Mr. Jayant Bhushan that the

Tribunal without allowing the petitioner to complete the inspection of

the documents and adjudicating the application for discovery of

documents had proceeded with the hearing and passed an interim

order/interim award in favour of the respondent No.1 is concerned, the

inspection of the documents sought for by the petitioner and respondent

No.2 were with regard to India Pakistan Series 2007 and the said

documents have no concern with the application for interim award filed

by the respondent No.1 with regard to other four series/events. The

Tribunal was justified to hold that the inspection and discovery of the

documents asked for by the petitioner and the respondent No.2 was

either to substantiate their claim/counter claim or with a view to enable

them to increase the amount claimed by them by way of counter claim

and the said documents are yet to be established at trial. Meaningfully

read, the application for inspection and discovery of documents had no

effect/bearing on the application for interim award. No prejudice was

caused to the petitioner. There was no violation of principle of natural

justice as alleged by Mr. Bhushan. This objection also need to be

rejected. No submission has been made on the competency of the

Tribunal to pass an interim award.

51. In view of above discussion and keeping in view the position of

law that passing of an interim award based on admissions is matter of

discretion and this Court while exercising power under Section 34 of the

Act, would not like to interfere with the impugned interim award dated

September 16, 2014. The petition is accordingly dismissed with no order

as to costs.

(V.KAMESWAR RAO) JUDGE

APRIL 06, 2015 akb

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter