Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

P.D. Verma And Co. vs Laxmi Builders
2014 Latest Caselaw 5336 Del

Citation : 2014 Latest Caselaw 5336 Del
Judgement Date : 29 October, 2014

Delhi High Court
P.D. Verma And Co. vs Laxmi Builders on 29 October, 2014
$~R-51
*     IN THE HIGH COURT OF DELHI AT NEW DELHI
                                               Decided on 29th October, 2014
+     RFA 359/2005

      P.D. VERMA AND CO.                                 ..... Appellant
                    Through            : Mr. K.R. Chawla, Adv.

                          versus

      LAXMI BUILDERS                                   ..... Respondent
                   Through             :Mr. P.D. Gupta and Mr. Abhishek
                                       Gupta, Advs.

CORAM:
HON'BLE MR. JUSTICE A.K. PATHAK

A.K.PATHAK, J.(ORAL)

1. By the impugned judgment and decree suit of the appellant-plaintiff

for recovery of `6,45,300/- against the respondent-defendant has been

dismissed by the Trial Court. Aggrieved by the judgment and decree,

appellant has preferred this appeal.

2. Appellant alleged in the plaint that appellant was sole proprietorship

firm of Sh. Prabhu Dayal Verma and was engaged in carrying out work of

fixing pipes and sanitary installations on job work basis. In the month of

April, 1991 respondent awarded contract to appellant for fixing of water

supply pipes and sanitary installations in the residential flats constructed by

Indraprastha Cooperative Group Housing Society Ltd. Delhi. Appellant was

given a room for storing the tools and equipments. Appellant carried out

work in the said society pursuant to the work order and raised running bills

from time to time. On 5th June, 1991 appellant submitted first running bill

amounting to `63,000/- against which respondent paid only `59,025/-.

Thereafter, a formal contract was reduced in writing on 22 nd June, 1991. On

6th August, 1991 appellant raised second running bill for `64,830/- against

which `64,243/- was paid. Third running bill for `40,054.50 was raised on

7th September, 1991, against which `39,527/- was paid. Fourth running bill

dated 22nd September, 1991 for a sum of `81,495/- was raised by the

appellant, against which `79,052/- was paid. On 5th January, 1992 fifth

running bill for a sum of `1,46,925/- was raised, against which respondent

paid `99,108/-. Against sixth running bill dated 10th February, 1992 of

`1,50,838.50, respondent paid only `74,160/-. Against seventh running bill

dated 7th March, 1992 for `1,46,437.50, respondent paid only `84,048/-.

Similarly, against eighth and ninth running bills dated 1 st August, 1992 and

25th September, 1992 for `2,63,989.50 and `5,63,946.50, respondent paid

only `98,880/- and `1,83,917/-, respectively. After completion of work,

appellant raised final bill dated 29th May, 1993 for `6,36,349.50, against

which only `88,992/- was paid on 27th March, 1993. All the payments were

made through cheques. Respondent did not pay remaining amount of

`5,47,357.50, inasmuch as did not allow the appellant to remove his

equipments and other materials valuing `10,500/- which were lying in the

store room. Since dues of the appellant were not paid despite legal notice

dated 20th September, 1993, hence the suit for recovery of `6,45,300 which

amount included interest @12% per annum from 29th May, 1993 to 24th

April, 1995.

3. In the written statement, respondent alleged that suit was not

maintainable as the same was filed by a sole proprietor ship firm. In fact,

appellant was a partnership firm. Respondent alleged that appellant was

engaged by the respondent only for carrying out the works relating to water

supply and sanitary installations in few blocks of the residential flats. It was

denied that bills as mentioned in the plaint were submitted by the appellant.

Respondent alleged that running bills were never submitted by the appellant.

Respondent had been making payments to appellant from time to time on

the basis of works executed by it. Works done by the appellant were

assessed and calculated by the staff of respondent, on the basis whereof

payments were made through cheques on regular basis, so as to enable the

appellant to arrange for labour for execution of the work. Work order dated

22nd June, 1991 did not provide for execution of any additional works other

than water supply and sanitary installation works. There was no provision in

the work order for making payment for any such additional work. As per

the respondent, bills as detailed in the plaint were never submitted with the

respondent. Respondent alleged that bills were fabricated by the appellant

and were false. Appellant was a plumber / contractor for executing sanitary

installations only on labour rate contract basis. Accordingly, work order

was given by the respondent to appellant for executing of such works only.

Respondent had paid a total sum of `8,46,410/- to appellant, after deducting

TDS of `9,590/-, against the total works done by the appellant. Details of

the cheques were given in the written statement, which reads as under:-

Cheque         Date           Amount           TDS            Total
No.
044229         09.07.1991     60,000.00        675.00         59,325.00
98015          13.08.1991     65,000.00        728.00         64,272.00


98042          16.09.1991     40,000.00        448.00         39,552.00


98083          24.10.1991     80,000.00        896.00         79,104.00



 48996           10.01.1992     75,000.00       840.00         74,160.00
51849           10.02.1992     75,000.00       840.00         74,160.00
101543          29.02.1992     85,000.00       952.00         84,048.00
102184          05.08.1992     80,000.00       896.00         79,104.00
105501          19.08.1992     20,000.00       224.00         19,776.00


105584          29.09.1992     95,000.00       1,064.00       93,936.00
148611          23.10.1992     91,000.00       1,019.00       89,981.00
157026          24.03.1993     90,000.00       1,008.00       88,992.00
                Total          85,56,000.00    9,590.00       8,46,410.00



4. Respondent further alleged that another total sum of `1,24,000/- was

paid to appellant in cash between 1st May, 1991 to 29th July, 1992 so as to

enable the appellant to make day-to-day payment to his labour at the spot.

In fact appellant had received `9,80,000/- for sanitary works executed by it

for which no bills were submitted with the respondent. As per the

respondent, appellant was not entitled to any amount and suit was liable to

be dismissed.

5. In the replication, appellant denied averments made in the written

statement and reiterated what was stated in the plaint. It was denied that

`1,24,000/- was paid in cash during the period as alleged in the written

statement. Other payments were not disputed.

6. Following issues were framed on 16th August, 2002:

1. Whether plaintiff was awarded and it executed works other than sanitary, as alleged?

2. Whether plaintiff is entitled to recover `5,47,357/- towards principal amount and `87,443/- towards interest @ 12% per annum from 29th May, 1993, to 21st May, 1995, as claimed?

3. Whether plaintiff left the equipments, tools and other materials worth `10,500/- in the storeroom at the site and the same was removed by the defendant?

4. Whether the suit as framed is not legally maintainable as alleged in para no.1 of the preliminary objections of written statement?

5. Whether defendant made payment of `1,24,000/- in cash on various dates from 1st May, 1991, to 21st May, 1992, to the defendant?

6. Relief.

7. It may be noted here that suit was initially filed in the High Court but

was subsequently transferred to District Court on 23rd September, in view of

increased pecuniary jurisdiction of the High Court.

8. Appellant examined Sh. Prabhu Dayal Verma as PW1 who filed his

affidavit in his examination-in-chief. He exhibited certain documents as Ex.

PW1/1 to Ex. PW1/14. He was cross-examined by the Appellant's counsel.

Appellant also examined one Sh. Omkar Singh as PW2. As against this,

respondent examined its partner Sh. Sunil Khemani as DW1, who filed his

affidavit and exhibited certain documents as Ex. DW1/1 to Ex. DW1/13.

After hearing the learned counsel for the parties and upon scrutiny of entire

documentary as well as ocular evidence on record, trial court vide impugned

judgment and decree has dismissed the suit. Issue-wise findings have been

given by the Trial Court. As regards issue no. 4, trial court has held that sole

proprietorship firm M/s. P.D. Gupta and Co. was not a legal entity and could

not have sued in its own name inasmuch as suit ought to had been filed in

the name of proprietor instead of in the name of proprietorship firm. As

regards issue no. 5 is concerned, trial court has held that respondent had

failed to prove that `1,24,000/- was paid by it to appellant in cash on various

dates between 1st May, 1991 to 29th July, 1992. Issue nos. 1 to 3 have been

decided together. Trial court has held that the bills Ex. PW1/1, Ex. PW1/3 to

Ex. PW1/10 were not reliable to foist any liability on the respondent, in as

much as were fabricated documents. Trial court has held that payments

made against each bill could not have been reflected in the bills which

indicated that some were fabricated. As per the usual practice, bills are

raised first and then the payment is made. Payment would not precede the

bill, more so, when the same was not given as advance. As regards non-

production of original bills by the respondent despite order of the Court is

concerned, trial court has held that no adverse inference can be drawn, since

the bills were found suspicious, inasmuch as PW1 had admitted in his cross-

examination that whenever bills were tendered, same were not accepted by

the respondent. As regards non-production of measurement book is

concerned, trial court has held that no such adverse inference can be drawn

when the bills Ex. PW1/1, Ex. PW1/3 to Ex. PW1/10 were found to be

tainted and unreliable. Trial court has further observed that appellant had

failed to lead any convincing evidence on record to show that he had left

equipments, tools and other materials worth `10,500/- at the site and the

same were removed by the respondent.

9. I have heard learned counsels for the parties and perused the entire

trial court record carefully and do not find any illegality or perversity in the

impugned judgment and decree, inasmuch as I am of the opinion that view

taken by the trial court is a possible view. It is trite law that burden to prove

a fact lies on such person, who alleges the same. Accordingly, burden to

prove the facts, as alleged in the plaint, heavily rests on the appellant.

Plaintiff cannot rely on the weakness of defence of the defendant and has to

stand on his own legs. Plaintiff is under legal obligation to lead cogent

evidence to substantiate the pleas taken in the plaint to prove the case as set

in the plaint. In Rangammal vs. Kuppuswami and Anr. AIR 2011 SC 2344,

Supreme Court has held thus: "Section 101 of the Indian Evidence Act, 1872

defines 'burden of proof' which clearly lays down that whosoever desires

any court to give judgment as to any legal right or law dependent on the

existence of facts which he asserts, must prove that those facts exist. When a

person is bound to prove the existence of any fact it is said that the burden of

proof lies on that person. Thus, the Evidence Act has clearly laid down that

the burden of proving fact always lies upon the person who asserts. Until

such burden is discharged, the other party is not required to be called upon

to prove his case. The court has to examine as to whether the person upon

whom burden lies has been able to discharge his burden. Until he arrives at

such conclusion, he cannot proceed on the basis of weakness of the other

party."

10. The case, as set up by the appellant before the trial court, was that it

had executed various works as mentioned in the bills but only part payments

thereof were made by the respondent. The payments in respect of running

bills were not fully paid. Only part payment was made against each running

bill. Accordingly, a final bill was raised after completion of the work,

against which also only part payment was made. Accordingly, onus was on

the appellant to prove the above plea by leading cogent evidence. In my

view plaintiff has failed to prove its case. First of all, a perusal of bills Ex.

PW1/1, Ex. PW1/3 to Ex. PW1/6 shows that these bills are in respect of civil

work and do not pertain to the sanitary work. Appellant has admitted in his

cross-examination that he was not a civil contractor. He was a plumber and

was doing sanitary work. It has been further admitted that sanitary work

was awarded to him, inasmuch as this fact is established from a perusal of

work order Ex.PW1/2. If no such work was awarded, question of raising

any bills in this regard does not arise. It has not been pleaded in the plaint

that any civil work was awarded to the appellant by the respondent. Even in

the affidavit of evidence, no such plea has been taken. It is only in his cross-

examination PW1 has volunteered that respondent had orally asked him to

execute the civil work as well. His this statement being beyond pleadings,

cannot be accepted. Even otherwise, it is improbable that appellant, who

was specialized in sanitary works, would have been asked by the respondent

to perform civil works by giving oral instructions, more so, when a written

contract (Ex. PW1/2) was executed between the parties on 22nd June, 1991

with regard to sanitary works alone.

11. Secondly, these bills are suspicious since payments made by the

respondent through cheques have been duly reflected in these bills. As per

the normal practice, the bill is raised first and only thereafter payment is

made. Bill is normally raised after execution of work and payment follows

the bill. If any advance is paid same is given adjustment of. It is not the

case that the payments, as reflected in these bills, were made as advance

payments. In his cross-examination, appellant has stated that the payment

used to be made after 5/7 days of submission of the bills. If that is so, then

payments made against each work, as mentioned in the bills, could not have

been reflected in the bills. Trial Court has rightly held that the bills were

tainted and suspicious and appears to have been fabricated.

12. Learned counsel for the appellant has vehemently contended that

since original bills were not produced by the respondent, therefore adverse

inference has to be drawn against the respondent. I do not find any force in

this contention. PW1 in his cross-examination has himself admitted that the

bills were not submitted to respondent. His plea is that whenever appellant

tried to submit the bills, same were not accepted by the respondent.

Accordingly, no adverse inference can be drawn.

13. As regards issue no. 5 is concerned, same has been decided against

the respondent. Respondent has not challenged finding of Trial Court by

filing an appeal or cross objection, thus, I need not to delve on this issue. As

regards issue no. 4 is concerned, in my view, approach adopted by the trial

court is not correct. Shri Prabhu Dayal Verma is the sole proprietor of M/s.

P.D. Verma & Co. It is not the case that suit was filed only in the name of

M/s P D Verma & Co alone. In fact Shri Prabhu Dayal Verma has been

impleaded in the case as sole proprietor of the firm M/s. P.D. Verma & Co.

It is trite law that a sole proprietorship firm has no separate legal entity and

is nothing but creation and/or firm name of the sole proprietorship firm.

Meaning thereby, any reference made to sole proprietorship firm, shall mean

and include the sole proprietor and vice versa. Accordingly, it cannot be

said that suit filed by the sole proprietorship firm through its sole proprietor

was not maintainable.

14. For the foregoing reasons, appeal is dismissed.

A.K. PATHAK, J.

OCTOBER 29, 2014 rb

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter