Tuesday, 28, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Vishwa Bvsr (Jv) vs Ministry Of External Affairs & ...
2014 Latest Caselaw 6148 Del

Citation : 2014 Latest Caselaw 6148 Del
Judgement Date : 25 November, 2014

Delhi High Court
Vishwa Bvsr (Jv) vs Ministry Of External Affairs & ... on 25 November, 2014
Author: Rajiv Shakdher
$~45
*    IN THE HIGH COURT OF DELHI AT NEW DELHI
+      O.M.P. 1483/2014 and IA No.23047/2014 (u/o. 39 R. 1 & 2 CPC)
       VISHWA BVSR(JV)                         ..... Petitioner
                    Through: Mr. Arun Kathpalia and Mr. Angad
                    Mehta, Advocates

                           versus

       MINISTRY OF EXTERNAL AFFAIRS & ORS ..... Respondents
                      Through: Mr. Sanjay Jain, ASG with Mr. B.S.
                      Shukla, CGSC, Ms. Pallavi Shali and Mr. Rajur
                      Jain, Advocates for the respondent/UOI
       CORAM:
       HON'BLE MR. JUSTICE RAJIV SHAKDHER
                ORDER

% 25.11.2014

1. Issue notice to the respondents.

2. Mr. Shukla accepts notice on behalf of respondent no.1.

3. I am informed by Mr. Jain, the learned ASG that the contract in issue is being executed through the Engineering Consultant i.e., RITES Ltd. (respondent no.2). Therefore, in view of the order that I propose to pass, both counsels say that the notice need not be issued to the other respondents including respondent no.2.

4. Mr. Kathpalia, the learned counsel for the petitioner at the very outset says that the letter dated 19.11.2014 issued by respondent no.2 which, inter alia, issues a notice of termination of the contract in issue can operate as an order of termination; albeit without prejudice to the petitioner's rights and contentions, to agitate the legality of the termination.

O.M.P. 1483/2014 page 1 of 3

5. At the outset, Mr Jain, the learned ASG, submitted that he is agreeable to the following offer made by the petitioner:

(i). out of the six bank guarantee, four bank guarantees bearing nos.0192111BG0000715, dated 12.02.2011, for Rs.1,92,49,000/-; and no.0192111BG0000716, dated 12.02.2011, for Rs.1,92,49,000/-; no.0192111BG0000717, dated 12.02.2011, for Rs.1,92,49,000/-; and no.0192111BG0000718, dated 12.02.2011, for Rs.1,92,49,000/- (which are in the nature of advance bank guarantees) will be encashed by respondent no.1 subject to the petitioner's lodging their claim with respect to work done before the learned arbitrator;

(ii). in so far as remaining two bank guarantees bearing no. 110133IBGP00070, dated 08.02.2011, for Rs.7,70,00,000/-; and no.110133IBGP00071 dated 08.02.2011 for Rs.7,70,00,000/- (which are in the nature of performance bank guarantees), are concerned, they shall not be encashed, till such time, respondent no.1 moves an appropriate application before the arbitrator, to be appointed in the matter. The result of these bank guarantees will abide by the order(s) of the arbitrator, subject to the said bank guarantees being kept alive;

(iii). the claims of the petitioner with regard to retrieval of plant and machinery, tools, etc. lying at site will be agitated before the learned arbitrator by way of an application under Section 17 of the Arbitration and Conciliation Act, 1996 (in short the Act);

(iv). the petitioner will give name of their nominee for his appointment as an arbitrator out of the approved panel of Indian Roads Congress, within two weeks from today. Respondent no.1 shall do likewise within two weeks O.M.P. 1483/2014 page 2 of 3 from today. The third arbitrator will be appointed by the two nominees of the petitioner and respondent no.1, who shall act as a Presiding Officer;

5.1 In view of what is stated by the learned ASG, whereby in effect he has accepted the offer of the petitioner, no further orders are called for in the petition filed under Section 9 of the Act. Parties will abide by the contents of paragraph 5(i) to (iv), which have fructified into a consent order. 5.2 Needless to say, the parties will be free to lodge their claims and counter claims, as they may be advised in the matter.

6. Since, counsels for parties are agreed that the procedure of DRE, as encapsulated in the contract in issue, has been rendered inefficacious, the parties will proceed to arbitration straightaway, as indicated above.

7. With the aforesaid observations in place, the captioned petition is disposed of.


                                               RAJIV SHAKDHER, J
NOVEMBER 25, 2014
Yg


O.M.P. 1483/2014                                                   page 3 of 3
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter