Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Bharat Heavy Electricals Ltd. vs Aanuj Infra Projects Pvt. Ltd.
2014 Latest Caselaw 5976 Del

Citation : 2014 Latest Caselaw 5976 Del
Judgement Date : 19 November, 2014

Delhi High Court
Bharat Heavy Electricals Ltd. vs Aanuj Infra Projects Pvt. Ltd. on 19 November, 2014
$~31
*    IN THE HIGH COURT OF DELHI AT NEW DELHI
+      O.M.P. 1408/2014
       BHARAT HEAVY ELECTRICALS LTD             ..... Petitioner
                   Through: Mr Ajay Kapur, Sr. Adv. with Mr
                   Arvind Chaudhary, Adv.

                          versus

       AANUJ INFRA PROJECTS PVT LTD               ..... Respondent
                      Through: Mr Sameer Parekh, Ms R.S. Bodbe &
                      Ms Sanjana Ramachandran, Advs.
       CORAM:
       HON'BLE MR. JUSTICE RAJIV SHAKDHER
                ORDER

% 19.11.2014

OMP 1408/2014 & IA 22133/2104 (Condonation of delay in re-filling)

1. This is a petition filed under Section 34 of the Arbitration & Conciliation Act, 1996 (in short 1996 Act). By virtue of this petition, award dated 06.06.2014, passed by the learned arbitrator, is impugned.

2. Mr Ajay Kapur, learned senior counsel for the petitioner, assails the award on one singular ground, which is that, the interest awarded by the learned arbitrator was contrary to the provisions of the contract. In this connection, he referred me to clause 6.7 of the contract, which is also extracted in the petition. The said clause reads as follows: "No interest shall be payable by BHEL on Security Deposit or on any money due to the contractor".

2.1 The learned arbitrator has directed not only payment of interest but also directed its compounding.

3. Quite clearly, therefore, the directions contained in paragraphs 62.2 to 62.4 in the award, in this regard appear to be ex-facie contrary to the provisions of the contract and, the principle of law enunciated by the Supreme Court.

3.1 In respect of payment of interest by the arbitral tribunal, where there is a bar provided in the agreement for grant of interest, the arbitrator's power under the 1996 Act to grant interest from the date of cause of action till the date of award, is circumscribed. The reason for this is that Section 31(7)(a) of the 1996 Act begins with expression "unless otherwise agreed by parties". In this case parties have agreed otherwise and, therefore, the arbitrator could not have granted interest for either the pre-reference period or the pendente lite period. [See Sayeed Ahmed & Co. vs State of U.P. & Ors. (2009) 12 SCC 26 paragraphs 7 to 10 and Sree Kamatchi Amman Constructions vs The Divisional Railway Manager (Works), Palghat & Ors. (2010) 8 SCC 767 paragraphs 5 & 10]. The prohibition in contract qua interest would not be beyond the date of the award. Under section 31(7)(b) of the 1996 Act, unless the award directs otherwise, interest would run at 18% per annum from the date of the award till payment. (See paragraph 15 of the judgement in the case of Sayeed Ahmed & Co. vs State of U.P. & Ors.) 3.2 As regards the other direction, whereby the compounding of interest is mandated in the impugned award, the same, as is obvious, could not have been granted because there is a bar on grant of interest. Even otherwise, compounding of interest cannot be directed by an arbitrator unless the contract provide for the same. [See State of Haryana & Ors. vs S.L. Arora & Company (2010) 3 SCC 690].

3.3 These aspects were put to the learned counsel for the respondent.

4. Learned counsel for the respondent sought to give some explanation as to why the directions contained in paragraphs 62.2 to 62.4 of the award, were tenable.

5. However, after arguments, both counsels agree that the petition could be disposed of based on the following directions:

(i) That the award could be sustained after excising the directions contained in paragraphs 62.2 to 62.4 of the award.

(ii) The sum crystallized in paragraph 62.1 of the award, which is, Rs. 32,28,570/- would be paid by the petitioner, as expeditiously as possible, though not later than four weeks from today.

(iii) In case the amount, as referred to in clause (ii) above, is not paid, interest at the rate of 18% would run on the said amount.

6. Accordingly, the petition and the captioned application stand disposed on the aforesaid agreed terms.

7. Dasti under the signatures of the Court Master.

RAJIV SHAKDHER, J NOVEMBER 19, 2014 kk

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter