Citation : 2014 Latest Caselaw 99 Del
Judgement Date : 6 January, 2014
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ I.A. No. 17982/2011 (O.XXXVII R.3 (5) CPC) in CS (OS) No.
1142/2011
% Reserved on: 19th November, 2013
Decided on: 6th January, 2014
YUVRAJ SINGH ..... Plaintiff
Through: Mr. S.K. Jain, Advocate.
versus
DELHI DEVELOPMENT AUTHORITY ..... Defendant
Through: Mr. M.K. Singh, Advocate.
CORAM:
HON'BLE MS. JUSTICE MUKTA GUPTA
1.
By this application the Defendant seeks leave to defend the suit.
2. Learned counsel for the Defendant contends that the present suit for
recovery does not fall within the scope and ambit of Order XXXVII CPC.
No cause of action ever accrued in favour of the Plaintiff and against the
Defendant. The Defendant constituted a Committee to look into the matter
relating to bills of the Plaintiff which found certain lapses and thus a
Vigilance Inquiry has been ordered into the same. The entire records relating
to the concerned Division Office and the works in dispute are in the custody
of the Vigilance Branch. It is the case of the Defendant that the Claims No.
6 to 10 are beyond the scope of the agreement and the Defendant is not
entitled to pay anything to the Plaintiff on the said count. Further as regards
the Claim No. 1 the Third Running Bill is under scrutiny and necessary
action will be taken only after the administrative decision by the department.
Regarding Claim No. 2 it is contended that the security can only be released
after the payment of the final bill. The payment, if any, regarding Claim No.
3 can only be made after taking of the administrative decision after the
inquiry is over. Regarding Claim No. 4, the payment, if any, for the work
executed will be duly considered at the time of payment of the final bill.
Further the Claim No. 5 is not tenable as the quantum of work was washed
away with water and is not required to be paid by the Defendant. The case
of the Plaintiff is unsubstantialed and sham and no case for summary trial is
made out. Hence the Defendant be granted unconditional leave to defend to
contest.
3. Learned counsel for the Plaintiff on the other hand contends that the
defence taken by DDA is not defence in the eyes of law and thus the
application is liable to be dismissed. Merely because an inquiry is pending
before the Vigilance Department of the Defendant, the claim of the Plaintiff
cannot be denied. The vigilance inquiry is only against Shri S.K. Sethi, the
then Executive Engineer of the Defendant on the complaint of the Plaintiff
regarding demand of bribe for releasing the payment. It is an unequivocal
admission on the part of the defendant DDA, its officials and the Committee
that the plaintiff has done the work for which the plaintiff is entitled to
payments.
4. I have heard learned counsel for the parties.
5. The Plaintiff has filed the present suit for recovery of Rs.
1,99,18,881/- against the Defendant for construction of internal road/foot
path and parking at Yamuna River, West Bank, Vijay Ghat, Pushta. The bid
of the Plaintiff was accepted and he was awarded a tender vide letter dated
28th June, 2007. The case of the plaintiff is that the parties agreed that the
time for completion of work would be four months, the date for starting the
work was 8th July, 2007 and the date for completion of work was set as 7th
November, 2007. The estimated cost put to tender was Rs. 35,81,969/- and
the accepted tender amount was Rs. 44,06,973/-. After receipt of the Award
Letter, the Plaintiff arranged infrastructure, labour, material etc. for
execution of the work as per the schedule of quantities and thus invested a
huge amount of money for execution of work. The site was full of bushes
and long grass which was required to be cleared. The Plaintiff submitted
these facts and also submitted the rates to be charged for the extra work of
jungle clearing and total station survey along with the detailed analysis of
rates in the last letter. The Plaintiff mentioned in the said letter dated 10th
July, 2007 that he would not be accepting any rate less than the market rates.
The Plaintiff also informed the Defendant about the resources deployed by
him at the site. The Defendant directed the Plaintiff to clear the Jungle under
the extra item and the Plaintiff executed the work accordingly which can be
verified from the Hindrance Register. The Defendant failed to provide
required drawings to the Plaintiff and recorded in the Hindrance Register at
site on 24th July, 2007 that alignment plan and sections for the road to be
constructed were not available with them. Thus the Defendant felt that total
station survey is necessary for preparation of working drawings. However,
the Defendant failed to conduct the survey work. The Plaintiff informed the
Defendant that the labour, material and staff etc. of the Plaintiff were lying
idle at the site and made requests to the Defendant to issue working drawings
so that the work could be taken up, but to no avail. The Defendant was not
having the full working drawings of the project and therefore, the Defendant
directed the Plaintiff to conduct the total station survey of the site under
extra item for preparation of the working drawings. The Plaintiff executed
the work on total station survey and completed the job on 21 st August, 2007
to the satisfaction of the Defendant. There were other various hindrances
which had to be resolved by the Defendant.
6. From the narration of the facts in the plaint itself it is evidently clear
that the Claims No. 6 to 10 were beyond the agreement. In view thereof the
Plaintiff is required to prove by leading evidence that there was an
agreement between the Plaintiff and the Defendant for the said work and the
Defendant is liable to pay for the same. Further the facts mentioned in the
plaint are disputed by the defendant. As per the documents filed by the
plaintiff, the defendant had given extension of time reiterating clearly that
time was the essence of the contract. Thus which of the parties caused the
delay is required to be adjudicated. The case of the defendant as per the
letters is that the claim of the plaintiff regarding deployment of staff was
false, as on surveys by the officers of the defendant the same was found to be
incorrect. At this stage the only thing which has to be seen is whether the
defendant has made out triable issues. In view of some of the claims being
beyond the agreement and others denied by the defendant, I am of the
considered opinion that the Defendant has made out a case for grant of leave
to defend.
7. Application is, therefore, disposed of granting leave to defend.
CS (OS) No. 1142/2011
8. Written statement be filed within four weeks. Replication be filed
within four weeks thereafter.
9. List before the learned Joint Registrar on 18th March, 2014 for
admission/denial of the documents.
(MUKTA GUPTA) JUDGE JANUARY 06, 2014 'vn'
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!