Citation : 2014 Latest Caselaw 6606 Del
Judgement Date : 9 December, 2014
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ ARB.A. 21/2014
Judgment reserved on: 01.12.2014
Judgment pronounced on: 09.12.2014
ARDEE INFRASTRUCTURE PVT. LTD. ..... Appellant
Through: Mr.Anil Kr.Mishra, Advocate alongwith
Mr.Saurabh Mishra, Advocate.
versus
ANURADHA BHATIA ..... Respondents
Through: Mr.Kirti Uppal, Sr.Advocate alongwith
Ms.Aastha Dhawan, Advocate.
AND
+ ARB.A. 22/2014
ARDEE INFRASTRUCTURE PVT. LTD. ..... Appellant
Through: Mr.Anil Kr.Mishra, Advocate alongwith
Mr.Saurabh Mishra, Advocate.
versus
YASHPAL AND SONS ..... Respondents
Through: Mr.Kirti Uppal, Sr.Advocate alongwith
Ms.Aastha Dhawan, Advocate.
CORAM:
HON'BLE MS. JUSTICE DEEPA SHARMA
JUDGMENT
1. Vide this judgment, I dispose of both the appeals as the matter
in issue is involved in both the cases is the same and both the cases
are between the same parties and facts are also similar in both the
cases.
2. The present appeals have been filed against the order of the
arbitrator dated 10.07.2014 whereby the arbitrator has directed the
appellant to furnish the security to the extent of claim in dispute in
favour of the respondents. The facts of the present cases which led to
the arbitration proceedings in short are as under:
3. In both the cases, there were two separate Flat Buyer
Agreements between the respondents and the appellant for sale of two
flats measuring 15000 sq. ft. on the second floor in Plaza Gardenia,
Ardee City, Gurgaon for a total consideration of Rs.45 lacs each. On
the same day, two separate a Memorandums of Understanding
(MOU) were also drawn between the parties and according to the said
MOUs the sale consideration of Rs.45 lakhs was to be paid by the
respondents to the appellant by transfer of certain lands owned by the
respondents in the name of the appellant company. It was agreed in
the said MOUs that the appellant would continue to pay rental
compensation of Rs.3,75,000/- per month in each MOU to the
respondents till the time the possession of the said flats at Plaza
Gardenia, Ardee City, Gurgaon is handed over to the respondents.
Appellant paid the rental compensation in terms of the MOU till
16.09.2010 and thereafter they stopped paying the money. The
respondents invoked the arbitration clause of each MOU vide
arbitration petitions no.239/2011 & 240/2011 and also filed a
petitions under Section 9 of the Arbitration and Conciliation Act
(hereinafter referred to as 'the Act') as O.M.P.Nos.583/2011 &
584/2011. This court disposed of the OMP No.583/2011 & 584/2011
filed under Section 9 of the Act with direction that the petitioners can
seek the interim relief before the arbitrator in terms of Section 17 of
the Act. In Arb.P.Nos.239/2011 & 240/2011 the arbitrator was
appointed by this court. The arbitral proceedings had started before
the arbitrator and the petitioner also filed the applications under
Section 17 of the Act. The said applications were disposed of by the
arbitrator on 05.03.2014 whereby the appellant was directed to pay to
the respondents the compensation amount as agreed between the
parties in the MOUs from October, 2010 onward. The said order was
challenged by the appellant vide Arbitration Appeal Nos.18/2014 &
19/2014. Meanwhile the arbitrator passed another order dated
10.07.2014 in both the arbitral proceedings, which amounts to
modification of the order and the order dated 05.03.2014 culminated
into the said order. The appellant had withdrawn the Arbitration
Appeal Nos.18/2014 & 19/2014.
4. Vide the present appeals, order dated 10.07.2014 has been
challenged by the appellant before this court on the ground that the
arbitrator has no authority to modify his order dated 05.03.3014 and
that the order amounts to deciding the dispute finally which is not
permissible under the law and that the arbitrator was not authorised to
appreciate the documents and evidence at this interim stage and the
application has been decided without considering the contentions of
the appellant. It is further submitted that arbitrator has wrongly held
that the land were duly transferred to the appellant by the respondents
whereas the documents show that the respondents did not fulfil their
part of obligations and since they have not performed their part of
obligation under the MOUs the respondents cannot enforce their
performance upon the appellant. On these facts it is submitted that
the said order is liable to be set aside.
5. Reply has been filed by the respondents. It is submitted that
arbitrator is fully empowered under Section 17 of the Act to direct the
appellant to furnish security at an interim stage. It is further
submitted that farm lands which were to be transferred to the
appellant already stood transferred through General Power of
Attorney and therefore, the respondents have complied with the terms
and conditions of the MOUs. It is further submitted that the appeals
have no merit and are liable to be dismissed.
6. I have heard the arguments and have perused the relevant
record.
7. It is clear from the above narrated facts that the respondents had
filed a petition under Section 9 of the Act seeking interim protection
from this court by way of O.M.P.Nos.583/2011 & 584/2011. The
court while disposing of the said OMPs had directed the respondents
to approach the arbitrator under Section 17 of the Act. Pursuant to
that the respondents had filed the applications under Section 17 of the
Act before the arbitrator. During the course of the arguments, learned
counsel for the appellant has argued that the applications of the
respondents under Section 17 of the Act is dated 15.3.2012 and the
arbitrator has disposed of them only on 05.03.2014 i.e. after two years
and it has been done at the stage when the matter was ripe and was
already fixed for final arguments and part of the final arguments have
also been heard. It is argued on behalf of the respondents that Section
17 of the act empowers the arbitrator to pass an interim order at any
stage during the arbitral proceedings. It is submitted that arbitral
proceedings were already going on and that it was the appellant who
had been seeking adjournments from the arbitrator for settlement and
on 14.02.2014 they even informed the arbitrator that they were taking
expeditious steps to restore the monthly rent/compensation and hence
it cannot be said that the arbitrator has intentionally delayed the
disposal of the applications under Section 17 of the act. It is
submitted that the arbitrator is empowered to pass an interim order on
applications under Section 17 of the Act at any stage of the
proceedings. It is further argued that while vide 05.03.2014 the
arbitrator had directed the appellant to make the payment of the
rent/compensation under MOUs with effect from October, 2010, the
said order has been modified by the arbitrator to the benefit of the
appellant whereby the appellant has only been asked to secure the
said money by furnishing security to the satisfaction of the
Coordinator, Delhi International Arbitration Centre.
8. I have given careful consideration to the rival contentions and
arguments of the parties.
9. It is pertinent to take note of the proceedings before the
arbitrator since one of the contentions of the appellant is that the
arbitrator had unduly delayed the disposal of the applications of the
petitioner under Section 17 of the act and when the case was fixed for
final arguments instead of passing any order for interim measure
ought to have disposed of the matter finally. This court is considering
the proceedings before the arbitrator in relation to the application
under Section 17 of the Act. The proceedings before the arbitrator
dated 28.05.2012 show that the respondents did not file their reply to
the application under Section 17 of the Act and also did not deposited
the charges of the arbitrator fee etc. and therefore, the arbitrator
adjourned the matter for the next date i.e. 03.07.2012. On 03.07.2012,
the respondents had filed the reply to the applications under Section
17 of the Act as well as reply to the statements of claim and rejoinder
was also filed. The arbitrator thereafter adjourned the matter to
26.07.2012 for argument hearing on the applications under Section 17
of the act and for framing of issues. The arbitral proceedings of
26.07.2014 shows that the arbitrator was informed that the parties
were desirous of settlement, for which they had fixed up time and
place for their meeting. On this basis, the arbitrator adjourned the
matter for hearing for 28.08.2012. Arbitral proceedings dated
28.08.2012 show that the parties had informed the arbitrator that they
were in the process of settling their dispute and sought adjournment.
The arbitrator fixed up the matter for 12.10.2012. On 12.10.2012,
issues were framed and the matter was fixed for evidence. Therefrom
the proceedings before the arbitrator continued till 06.08.2013, during
which period evidence etc. were recorded. The matter was fixed for
final arguments on 05.09.2013. On that date, adjournment was sought
on behalf of the respondents and the matter was again fixed for
21.09.2013 for final arguments. On 21.09.2013 the arguments could
not be concluded and the matter was fixed for 18.11.2013. The
proceedings dated 18.11.2013 clearly show that on that day the
appellant's counsel represented to the arbitrator that they were still in
the process of settling their dispute with respondents and for that
purpose Mr.Amit Kaicker, consultant of appellant also met
Mr.Yashpal Mehra, the respondent and discussed some proposal and
adjournment was sought and also represented that in case efforts of
settlement fails, the arbitrator could take up the matter for final
disposal including the question of interim order regarding payment of
compensation as provided in agreement. The arbitrator thereafter
adjourned the matter and the date was fixed as 05.12.2013. Arbitral
proceedings dated 28.01.2014 show that the parties were still engaged
in the process of settling their disputes. The arbitrator listed the
matter again for 14.02.2014. The proceedings before the arbitrator
dated 14.02.2014 clearly show that the appellant had informed the
arbitrator that they were taking expeditious steps to restore the
payment of monthly rent/compensation. The relevant portion of the
order dated 14.02.2014 of the arbitrator is reproduced hereunder:
"Mr.Mishra on instructions states that after the meeting between claimants and one of the directors of the respondents there appears to be an agreement on the part of respondents to take expeditious steps to restore the payment of monthly rent/compensation. On the tribunal's insistence and on instructions Mr.Mishra states that concrete schedule of payment and the rent/compensation will be conveyed within ten days from today to the claimants. Mr.Mishra submits that above is without prejudice to respondents' pleas in defence. Mr.Mehra, one of the claimants is not opposed to ten days time being given. He submits that date when the payment will commence should also be communicated forthwith. Counsel for respondents states that such date will also be communicated within 10 days from today. The schedule of dates of payment should also cover the
arrears, if any. Other items in dispute will be taken up and dealt with before this tribunal after 10 days."
10. The proceedings dated 05.03.2014 show that the parties could
not reached to any settlement regarding fixing up the schedule of
payment of arrears of monthly rent/compensation and the arbitrator
proceeded to deal with the question of interim relief to the
respondents and thereafter directed to make the payment of monthly
rent/compensation starting from October, 2010 till date to the
respondents. Thereafter, arbitrator in modification of his order dated
05.03.2014 directed the appellant to furnish the security of the
Coordinator of Delhi International Arbitration Centre instead of
making the payment to the respondents. The above proceedings
before the arbitrator clearly show that the parties have been constantly
seeking time for settling their dispute. It is apparent from the
proceedings that the arbitrator refrained himself from passing any
interim order since parties were interested in settling their dispute,
and arbitrator has been facilitating them in their efforts. It is also
reflected in the proceedings dated 14.02.2014 that the appellant
pursuant to a meeting between the claimants and the directors of the
appellant appeared to have been in agreement to take expeditious
steps to restore the payment of monthly rent/compensation. It,
therefore, cannot be said that delay on the part of the arbitrator in
taking up the matter for taking interim measures have in any way
caused any prejudice to appellant. Also the modification of the order
dated 05.03.2014 of the arbitrator is not prejudicial to the interest of
the appellant since while vide order dated 05.03.2014 they were
directed to make the payment of the rent/compensation from October,
2010 to the respondents, by modification order dated 10.07.2014, they
were directed to secure the said amount. Section 17 of the Act
empowers the arbitrator to pass any order as part of interim measures
for protection of the subject matter of the dispute. In the present case,
one of the subject matter of the dispute is payment of
rent/compensation under MOU to the respondents. The order of the
arbitrator protecting the subject matter of the dispute therefore is not
contrary to law. This order does not amount to final adjudication of
the dispute between the parties because the arbitrator has directed the
appellant to secure this amount with the Coordinator, Delhi
International Arbitration Centre.
11. For the reasons discussed above, it is apparent that there is no
force in the appeals. The appeals are, therefore dismissed with no
order as to costs.
DEEPA SHARMA, J
DECEMBER 09, 2014 rb
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!