Citation : 2014 Latest Caselaw 3958 Del
Judgement Date : 27 August, 2014
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Order delivered on: 27thAugust , 2014
+ CS (OS) No.2269/2009
M/S. SURVI PROJECTS PRIVATE LIMITED ..... Plaintiff
Through Mr.Kawaljit Singh, Adv.
versus
M/S. OM BUILDERS ..... Defendant
Through Defendant is ex-parte
CORAM:
HON'BLE MR.JUSTICE MANMOHAN SINGH
MANMOHAN SINGH, J. (Oral)
1. This is a suit for recovery filed by the plaintiff against the defendant. The defendant is ex-parte.
2. Brief facts of the case are that the plaintiff, engaged in the business of civil construction, was allotted work of Civil Construction at Village Prithla, Tehsil & Distt. Palwal by M/s Mahindra & Mahindra vide letter dated 21st February, 2008 in terms of the agreement dated 29th February, 2008.
3. In terms of the said agreement, the plaintiff engaged one M/s Lord Krishna, as a sub-contractor to work at sight vide letter dated 24th March, 2008. However, the said sub-contractor could not execute the work within the stipulated time and as agreed by the plaintiff, due to which the sub-contractor absolved itself from the
conditions of sub-contract vide letter dated 23rd July, 2008 and further assigned the work to the defendant herein.
4. Vide letter dated 23rd July, 2008 (Ex. P-6), the defendant conveyed their consent and agreed to do the assigned work for the plaintiff on the basis of same agreed terms and conditions. The defendant started the work in terms of letter dated 23rd July, 2008 as per agreed terms and the plaintiff started making payments to the defendant from time to time.
5. It has been stated by the plaintiff that the defendant always insisted and requested for instant payments for the work undertaken with assurance that it is going on speedily as they are heading towards the execution of work in time as agreed and the defendant used to raise bills later on, on completion of particular work/job.
6. The defendant did not complete its work within the agreed time and abandoned the site time and again despite many requests of the plaintiff. There was regular pressure from M/s. Mahindra & M/s. Mahindra for completion of the construction in time which the plaintiff could not do on account of defendant's fault and abandoned the site without completing the work for which a penalty of Rs.20,00,000/- was imposed by M/s Mahindra & Mahindra on the plaintiff.
7. It is averred that the defendant is liable to bear the proportion of the penalty from Rs.20,00,000/- imposed on the plaintiff as per agreed terms and conditions dated 23rd July, 2008. Accordingly, Rs.9,84,425/- becomes due from the defendant. Also, when the
plaintiff reconciled its accounts, it was revealed that the plaintiff has paid an excess payment of Rs.14,40,281/- to the defendant for which the work had not been done.
8. The plaintiff called upon the defendant to make the due payment of Rs.24,24,706/- but the defendant instead of paying the plaintiff rather started threatening the plaintiff of dire consequences if the amount is demanded from the defendant.
9. To avoid the liability of the due payment, the defendant has been filing false complaints against the plaintiff before the police and the defendant has been threatening that it will get the plaintiff implicated in criminal cases if the due payment is demanded from the defendant.
10. Plaintiff got a Legal Notice dated 25th June, 2009, served upon the defendant despite of receiving which the defendant has not paid the said amount. Aggrieved thereof the plaintiff filed the present suit for recovery of Rs.24,24,706/- against the defendant.
11. The suit was listed before Court on 2nd December 2009 when summons were issued to the defendant in the suit.
12. Though the defendant was served with summons as per record on 13th March, 2011, no written statement was filed. Despite repeated opportunities, admission/denial of plaintiff documents was not carried out. Ultimately, admission/denial of documents was closed and vide order dated 1st May, 2012 it was held that documents of the plaintiff are deemed to have been admitted by the defendant.
13. The defendant was proceeded ex-parte vide order dated 16th July, 2012. In the evidence, the plaintiff proved the facts stated in the plaint by evidence by way of affidavit of Mr. Neeraj Bhagat, Director of the plaintiff as Ex. PW-1/X, and also exhibited certain documents exhibited as Ex. P-1 to Ex. P-10 in support of its case. The same are as follows:
Original copy of Memorandum and Articles of association of M/s Survi Projects Private Ltd., Ex P-1.
Extract of Board Resolution dated 26th October, 2009, Ex P-
2. Photocopy of Agreement dated 29th February, 2008, Ex P-3. Original letter dated 24th March, 2008 by M/s Lord Krishna, Ex P-4.
Original Sub-contract, Ex P-5.
Original letter dated 23rd July, 2008 by M/s Om builders, Ex
P-6.
Original letter dated 23rd July, 2008 by M/s Lord Krishna, Ex
P-7.
Account statement, Ex P-8.
Debit Note dated 6th October, 2008, Ex P-9.
Office copy of legal notice dated 25th June, 2009, Ex P-10.
14. The defendant did not appear to contest the matter. No written statement was filed by the defendant. PW-1 was also not cross- examined by the defendant.
15. The ex parte evidence of the plaintiff was closed on 7th May, 2014. The evidence filed by the plaintiff has gone unrebutted as no cross-examination of the plaintiff's witness was carried out, therefore, the statements made by the plaintiff are accepted as correct deposition. Under these facts and circumstances, the plaintiff is entitled for a decree for recovery of Rs. 24,24,706/- in terms of the prayer clause of the plaint. The same is accordingly passed in favour of the plaintiff and against the defendant. The plaintiff is also entitled for costs. The decree be drawn accordingly. The suit is disposed of.
(MANMOHAN SINGH) JUDGE AUGUST 27, 2014
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!