Citation : 2014 Latest Caselaw 3634 Del
Judgement Date : 11 August, 2014
$~14
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ O.M.P. No.415/2013
% Judgement Reserved on: 22nd July, 2014
Judgement pronounced on: 11th August, 2014
UNION OF INDIA THROUGH THE CONTROLLER OF STORES
NORTHERN RAILWAY
..... Petitioner
Through: Mr.Nitish Gupta, proxy
counsel for Mr.Ravi Prakash,
Adv.
versus
MANOJ CABLE COMPANY PVT. LTD. ..... Respondent
Through: Mr.Amit Singh Narag, Adv.
CORAM:
HON'BLE MS. JUSTICE DEEPA SHARMA
JUDGMENT
1. Vide this petition a challenge has been placed to an award
dated 30.11.2012 whereby while rejecting the claim of the petitioner,
learned arbitrator has allowed the claim of the respondent and held
that the act of the petitioner by not allowing the price variation
beyond March, 2009 was contrary to the terms of the contract and
therefore contractually and legally not justified and issued directions
to Northern Railway, COS's office to suitably settle the claim of the
respondent.
2. The admitted brief facts of the case are that the petitioner had
floated a tender for the supply of cable against which three Pos were
awarded to the respondent. These Pos were numbered as
08089519194045 dated 14.01.2009 for the supply of 414.50 km
quantity of cable, P.O.NO.08089519193100 dated 14.1.2009 for the
supply of 90.25 km quantity of cable and P.O.No.0809519163176
dated 24.02.2009 for supply of 24.00 km quantity of cable. The
Delivery Period of the said P.Os was upto 15th June, 2009, 15th June,
2009 and 30th July, 2009 respectively. The respondent manufactured
the cable quantity and had offered the material for inspection vide
their call letter dated 24.03.2009 in respect of 528.75 km quantity of
cable. Meanwhile the respondent had also participated in the fresh
bids invited by petitioner for supply of cables and the new tender was
opened by the petitioner on 13.03.2009. The petitioner found that the
rates quoted by the respondent in its subsequent fresh tender, which
was opened on 13.03.2009, were much less than the rates quoted by
the respondent in its previous tenders which was awarded vide above
mentioned P.Os. Accordingly, the petitioner, instead of inspecting
the 528.75 km quantity of cable which they were required to inspect
pursuant to call letter dated 24.3.2009, wrote a letter dated 6.4.2009.
In the said letter the petitioner had written as under:
"As per the provisions contained in 'IRS Conditions of Contract', 'General & Financial Rules' and 'Manual on Policy & Procedures for procurement of Goods' issued by Ministry of Finance, as a Railway approved vendor you are expected to be fair and transparent in your business dealings with the Government, insofar as the pricing of the product is concerned. Since the price of the subject item has gone down considerably, as is evident from your offer against the tender opened on 13.03.09, as a Railway approved RDSO Part-I source, it will be in the fitness of things to supply the entire quantity against the existing POs cited above at the prevailing rates, in tune with your offer against the tender opened on 13.03.09. In addition to being a gesture of goodness and equity, it will also avoid a violation of the provisions contained in IRS Conditions of Contract, General and Financial rules & other conditions governing a contract between Union of India and a private contractor. It will be pertinent to mention here that in the event of your not offering to supply the entire quantity at the lower/prevailing rates, Railways shall be at liberty to invoke, inter-alia, the book examination clause and/or to exercise the option of reduction in order quantity by 30%."
3. It was this communication of the respondent which is the basis
of the counter claim of the petitioner before the arbitrator.
4. The said letter was replied by the respondent vide their letter
dated 10.4.2009 asking the petitioner to supply the copies of the
conditions of contract, General and Financial Rules and Other
Conditions, authorising the railways to invoke the book examination
and to exercise the option of reduction in rates unilaterally. The
respondent had challenged the authority of the petitioner to
unilaterally change or deviate from the accepted conditions of the
tender. This letter of the respondent dated 10.4.2009 was duly
replied by the petitioner vide its letter dated 5.5.2009 informing the
respondent that the contract was governed by IRS Conditions of
Contract, and clause 3300 of IRS Conditions of Contract, General
and Financial Rules and Other Conditions give the purchaser the
right for book examination as well as the right to reduce the contract
price and also enclosed the copy of the relevant clause. The
petitioner also asked the respondent to confirm acceptance of the
lower rates as mentioned in their letter dated 6.4.2009 vide their letter
dated 5.5.2009. The letter is reproduced as under:
"NORTHERN RAILWAY
Headquarters'Office, Baroda House, New Delhi No.08079516193002 Dated 05.05.2009
M/s Manoj Cable Company Pvt.Ltd., 90/3, Industrial Complex, Haidarpur, Delhi - 110088 Fax No.011-27499055
Sub.: Acceptance of lower rate
Ref.(i) (a) PO No.08089519.194045 dated 14.01.09 for 414.5 Km
(b) PO No.08089519.193100 dated 14.01.09 for 90.25 Kms
(c) PO No.08089519.163176 dated 24.02.09 for 24.00 Kms
For supply of Underground Railway Signalling Cable Size 19 Core x 1.5 sq. mm issued against tender No.4008086431 Opened on 27.06.08
(ii) Your letter No.MCCPL/N.RLY/POS19C/839-840-853/09-10/22 Dated 10.04.2009
In reference to your letter cited above, it is informed that the above contracts are governed by IRS Conditions of Contract, and Clause 3300 of IRS Conditions of Contract gives the purchaser the right for Book Examination, as well as the right to reduce the contract price. A copy of the relevant clause is enclosed herewith.
You are again requested to confirm acceptance of lower rates as mentioned in this office letter of even no. dated 06.04.2009. In the event of your not offering to supply the entire quantity at the lower/prevailing rate, Railways shall be a liberty to take further necessary action in accordance with the terms and conditions of the contract.
Sd/-
(Rajesh Abrol) Dy.CMM/Sig/C-I"
5. Since as per the terms of the P.Os, the delivery date was
15.6.2009 for two P.Os dated 14.1.2009, the respondent wrote to the
petitioner a letter dated 15.6.2009, alleging that despite they being in
continuous touch with them and corresponding the delivery was not
taken by petitioner. The respondent further informed the petitioner
that the last date of delivery period was approaching and that they
were finding it difficult to hold the material for so long, requested the
petitioner to re-fix the delivery date. In response of the said letter,
the petitioner wrote a letter dated 21.7.2009 and refixed the delivery
date by extending it for 45 days i.e. upto 8.9.2009 with advise to
supply the material at the earliest and complete the delivery within
the refixed delivery period. They also wrote to respondent (the
relevant portion is reproduced):
"You have stated in your letters cited above that you had offered the entire ordered quantity for inspection on 24.03.09. Thus the material was due for inspection during the month of April 09. Therefore, in accordance with the contract conditions, for the purpose of price variation the final price payable shall be the IEEMA prices prevailing on the 1st working day of March, 2009, and any subsequent variation in the IEEMA prices of raw materials shall not be applicable."
6. The inspection was done subsequently and the goods were
supplied by the respondent to the petitioner within the re-scheduled
period. The respondent, however, did not agree to the proposal of
petitioner for taking the date of first working day of March, 2009 as
date for reckoning the IEEMA price for calculation of price variation
and raised the dispute. The dispute was referred for arbitration and
the learned arbitrator gave its findings which are under challenge.
7. It is a settled law that an arbitration award can be challenged
only on the grounds mentioned in Section 34 of the Arbitration and
Conciliation Act, 1996 (hereinafter referred to as 'the Act'), that is,
on the ground that there is an error apparent on the face of the award
or that the award is against the public policy or that the arbitrator
exceeds its jurisdiction.
8. The argument of the learned counsel for the petitioner is two-
fold. The first argument is that the learned tribunal has wrongly held
that the petitioner was not entitled to calculate the price variation as
per the rates of IEEMA prevalent on first working day of March,
2009. It is submitted that the inspection could not be done due to the
fault on the part of the respondent. It is also argued that vide letter
dated 21.7.2009, when the petitioner had extended the delivery
period, all the propositions in the letter were accepted by the
respondent unconditionally. It is also argued that the findings of
learned arbitrator on clause 0402 of IRS of the Conditions of
Contract are erroneous.
9. It is settled principle of law that this court cannot sit as an
appellate court over the award. The award can be challenged only on
the grounds mentioned in Section 34 of the Arbitration and
Conciliation Act, 1996, that is when a party is incapacitated, when
the learned arbitrator has violated the procedure, when the award is
contrary to the arbitration agreement or when the learned arbitrator
has travelled beyond the reference, or the award is patently wrong,
against substantive law of land or shocks the conscience and is
suffering with an illegality which goes to the very root of the award.
The award can also be challenged on the ground that it is against the
public policy. The Supreme Court in the case 2003 (2) RAJ 1 (SC)
titled as Oil & Natural Gas Corporation Ltd. vs. Saw Pipes Ltd. had
the occasion of discussing the expression "Public Policy" and after
extensive discussion concluded as under:
"31. Therefore, in our view, the phrase 'Public Policy of India' used in Section 34 in context to be given a wider meaning. It can be stated that the concept of public policy connotes some matter which concerns public good and the public interest. What is for public good or in public interest or what would be injurious or harmful to the public good or public interest has varies from time to time. However, the award which is, on the face of it, patently in violation of statutory provisions cannot be said to be in public interest. Such award/judgment/decision is likely to adversely affect the administration of justice. Hence, in our view in addition to narrower meaning given to the term 'public policy' in Renusagar's case (supra), it is required to be held that the award could be set aside if it is patently illegal. Result would be award could be set aside if it is contrary to: -
(a) fundamental policy of Indian law; or
(b) the interest of India; or
(c) justice or morality, or
(d) in addition, if it is patently illegal.
Illegality must go to the root of the matter and if the illegality is of trivial nature it cannot be held that award is against the public policy. Award could also be set aside if it is so unfair and unreasonable that it
shocks the conscience of the Court. Such award is opposed to public policy and is required to be adjudged void."
10. In view of the settled law the petitioner is required to show that
award is patently wrong, against public policy or there is an error
apparent on face of award. The award shows that the learned
arbitrator has dealt with each and every contentions of parties.
11. While dealing with clause 0402 of IRS conditions of contract,
General and Financial Rules and Other Conditions, the learned
arbitrator has quoted the clause 0402 of the Conditions of Contract,
General and Financial Rules and Other Conditions and has given the
following findings:
"As per clause 0402 of IRS conditions of contract also "Any variation or amendment of the contract shall not be binding (on the purchase) unless and until the same is duly endorsed on the contract incorporated in a formal instrument in exchange of letters and signed by (both) the parties." The amendment in this case is therefore unilateral as not signed by both the parties and, therefore, not binding."
12. The petitioner has totally failed to bring on record the fact that
the respondent had consented to the offer of petitioner to calculate the
price variation on the basis of IEEMA base price on the date
1.3.2009. So this offer remained unilateral and clause 0402 of IRS
conditions of contract, General and Financial Rules and Other
Conditions clearly prohibits unilateral amendment in contract. It is a
fact that although on receiving letter dated 21.7.2009 the respondent
supplied the goods within extended period of delivery but the offer of
the petitioner to calculate the price variation by invoking the IEEMA
price prevalent on first working day of March, 2009 was not accepted
by respondent and he raised the dispute. It, therefore, cannot be said
that the respondent agreed to fixation of price variation as per
IEEMA price on 1.3.2009.
13. It is also an undisputed fact that under the original contract the
petitioner had no authority to change the terms of the contract
unilaterally. Even the clause 0402 of IRS Conditions of contract
prohibits the unilateral variation or amendment in any contract. The
findings of the learned tribunal, therefore, cannot be said to suffer
with any infirmity or illegality or against the substantive laws.
14. The next contention of petitioner is that the provisions of
clause 3300 and clause 300 were binding on the parties and that
under these clauses the petitioner was at liberty to invoke inter alia
the book examination clause (Clause 3300 of IRS conditions of
Contract, General and Financial Rules and Other Conditions) and
exercise the option of reduction of tender quantity by 30%.
15. The learned tribunal has also dealt with these contentions and
has given the findings that "the respondent itself did not follow its
own chartered course of action by initiating action against the
claimants under IRS Conditions 0300 and 3300 which resulted in
delay in supply of material by claimant". From content of the letters
dated 6.4.2009 and 25.5.2009 of the petitioner written to respondent
and discussed in earlier part of this judgment, it is apparent that the
petitioner although informed the respondent about his rights to book
examination and exercise of option of reduction in tender quantity by
30% but at no stage the petitioner cared to invoke those options.
16. The contention of petitioner is that the award is liable to be set
aside since learned arbitrator has wrongly taken the date of inspection
as August, 2009, when delay in inspection is attributable to
respondent.
17. The learned arbitrator has elaborately dealt with this aspect of
case and did not find any merit in contentions of petitioner. It is not
in dispute that the actual date of inspection by the petitioner was in
August, 2009. As per the price variation formula for railway
signaling cable, which is binding on both the parties, the price
variation has to be calculated after taking IEEMA price of the goods
on the date one month prior to the date of inspection. The award
does not suffer with any infirmity and is based on the rules,
regulations, binding the parties under the contract. The learned
tribunal has not travelled beyond the four corners of the Contract
which has given it the authority to act.
18. The petitioner has further argued that learned tribunal has
wrongly rejected his claim. The rejection of his counter claim is
against public policy as it affects the public exchequer as the payment
is required to be made by petitioner from public exchequer. It is
stated that the respondent obtained the work order of Rs.1,22,679.09
while the respondent had himself quoted a much lower all inclusive
rate of Rs.1,06,783.52 per km against the tender opened on 13.3.2009
and the difference in the two rates works out to be Rs.87,59,057.64.
19. There is no dispute to the fact that Annexure II to purchase
order, determines the terms and conditions governing the contract
between the parties. Clause no.17 clearly on this Annexure clearly
states that the FALL CLAUSE: NOT APPLICABLE. The learned
counsel for the petitioner has failed to point out that the reliance of
the learned arbitrator on the fall-clause at item no.17 in annexure II to
the purchase order amounts to travelling beyond the terms and
conditions of the contract/tender/purchase order which had created
the legal relationship between the parties. Since, as per clause 17, the
fall-clause was not applicable, the tribunal has held that the
respondent was not entitled for difference in two rates, and has thus
rejected the counter claim. In the light of these facts it cannot said to
be against the public policy, causing loss of public money since
money was paid to respondents in term to the contract. Learned
arbitrator has relied upon the table showing the IEEMA basic price
circular issued every month by petitioner and has observed that there
was always a substantial amount of price variation from month to
month. It is also observed that the tender against which the P.Os
were granted to the respondent were submitted in June, 2008 and the
rates quoted in the tender were based on raw material rates as per
IEEMA price index, which were significantly higher at that time, and
a contractor while submitting a tender is required to calculate its price
of the raw material on the basis of the prevalent IEEMA rate of the
raw material. It is not in dispute that the rates so quoted by the
respondent in its tender were accepted unconditionally by the
petitioner and thereafter P.Os dated 14.1.2009 and 24.2.2009 were
issued to the respondent. It, therefore, is clear that the contract was
not fraudulently obtained by the respondent. After discussing the
variations in IEEMA price of raw material, the learned arbitrator
concluded that the prices quoted in tender by respondent were as per
the rates of raw material declared by petitioner from time to time.
The findings of learned Arbitrator are thus well reasoned duly
supported by documentary evidences on record.
20. It is further argued by the petitioner that the terms of reference
was to decide the legality of the restrictions imposed by Northern
Railway on price variation beyond March, 2009, but the learned
arbitrator has wrongly dwelt and judged the whole matter on the
aspect of whether the imposition of said restriction was justified or
not and thus has travelled beyond the terms of reference.
21. To my mind, the arbitrator has considered all the relevant
contentions and submissions raised by the parties in their claim and
counter claim relied on the relevant documents produced and dealt
with the arguments addressed by parties on the issue, and then
answered the terms of reference. At no stage, learned arbitrator has
travelled beyond the terms of reference or in violation of terms and
conditions of the agreement governing the parties.
22. It is also contended in the petition in clause Q and D of the
petitioner that the arbitrator has shown bias in favour of the
respondent, while ignoring crucial facts and invoking clause 0402 of
IRS Conditions of Contract. There is no dispute to the fact that the
clause 0402 of IRS Conditions of Contract, General and Financial
Rules and Other Conditions governs both the parties, and so invoking
the provisions of IRS Conditions of Contract cannot be said to be an
act of bias, and the petitioner has failed to point out 'the crucial fact'
which was ignored by learned Arbitrator.
23. The petitioner has failed to point out any error apparent on the
face of award or that the award is apparently and patently illegal or
that it is unfair, unreasonable and shocks the conscience of the court
or is against any Public Policy.
24. No ground has been made out to interfere with the award. The
petition is hereby dismissed.
25. No orders as to costs.
DEEPA SHARMA (JUDGE) AUGUST 11, 2014 rb
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!