Citation : 2014 Latest Caselaw 2052 Del
Judgement Date : 24 April, 2014
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ FAO No.264/2011
% 24th April, 2014
UNION OF INDIA ..... Appellant
Through: Mr. Anuj Aggarwal, Advocate.
Versus
TIRUPATI TEXCO PRODUCTS (P) LTD. ..... Respondent
Through: Mr. B.S. Mathur, Advocate.
CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA
To be referred to the Reporter or not?
VALMIKI J. MEHTA, J (ORAL)
1. At the outset it is stated that there was a delay of 48 days in re-
filing the appeal and therefore while issuing notice in the appeal, delay of 48
days in re-filing the appeal was condoned by allowing C.M. No.11020/2011.
Counsel for the respondent contends that delay in re-filing the appeal ought
not to have been condoned. I note that there is no application for recalling
of the order dated 31.5.2011. Even assuming that there was such an
application, yet, the delay of 48 days in re-filing the appeal is condoned
inasmuch as delay of 48 days causes no real prejudice to the respondents and
which period of 48 days is for removing objections raised by the registry. I
therefore refuse to recall the order of condonation of delay in re-filing the
appeal as passed on 31.5.2011 including because no application is filed for
recall of this order.
2. This first appeal is filed under Section 37 of the Arbitration &
Conciliation Act, 1996 (hereinafter referred to as 'the Act') impugning the
judgment of the court below dated 10.11.2010 by which objections filed
under Section 34 of the Act by the respondent herein, petitioner before the
trial court were allowed and the Award dated 13.2.2001 was set aside
whereby the appellant/claimant was granted a money decree of Rs.29,925/-.
The court below has set aside the Award which granted damages on risk
purchase caused to the appellant/Union of India as the contract with the
respondent was cancelled as the respondent had failed to supply the
contracted goods/cotton ropes within the delivery period. The court below
held that there was no concluded contract and therefore there does not arise
any issue of the appellant/Union of India contending that losses are to be
compensated on account of risk purchase.
3. The facts of the case are that the appellant invited offers for
supply of cotton ropes. Respondent submitted its tender on 28.9.1990 which
was accepted by the appellant. Three different types of ropes measuring
69210 mtrs, 94350 mtrs, and 50,000 mtrs were ordered from the respondent
in terms of the tender. The quantity was subsequently enhanced to 86512
mtrs from 69210 mtrs so far as first item is concerned, and from 94350 to
117938 mtrs so far as second item is concerned, and this was done vide letter
dated 25.10.1990 of the appellant because the contract contained a + 25%
variation clause. So far as the delivery period was concerned for item nos.1
and 2 it was extended upto 31.12.1990 and for item no.3 the date of delivery
was 31.8.1990. There was a mistake on behalf of the appellant because
whereas the amendment letter was issued on 25.10.1990 the delivery period
so far as item no.3 was given as 31.8.1990 and consequently a fresh
amendment was issued for supply by 28.2.1992. The issue is that whether
this fresh amendment dated 13.12.1991 issued by accepting of the letter of
the respondent dated 20.11.1991, and received by the appellant on 2.1.1992,
amounted to a concluded contract and which would be if the request of the
respondent for extension of the delivery period to 28.2.1992 in terms of the
letter of the respondent dated 20.11.1991 was accepted by the appellant by
the appellant's letter dated 13.12.1991. In sum and substance, the issue is
whether the letter of the respondent dated 20.11.1991 amounted to an offer
and the same on being accepted by the appellant by issuing its letter dated
13.12.1991 results in a concluded contract.
4. The arbitrator held that the letter dated 20.1.1992 showed that
the contract stood concluded and not that this letter of the respondent dated
20.1.1992 was a fresh counter offer. The court below has however accepted
this letter dated 20.1.1992 as a counter offer and therefore objections of the
respondent were accepted and the Award was set aside.
5. Since for determination of the issue, language of the letter dated
20.1.1992 is relevant, I reproduce the same alongwith another letter dated
10.2.1992 issued by the appellant to the respondent as under:-
"Letter dated 20.1.1992
No.476/RC/91 Dated 20.1.92 Asstt. Director (Supplies) 7/29-B, Tilak Nagar, KANPUR Sub:- A/T No.101/504/K2/Tirupati/476/COAD dt.28.9.90 for supply of Rope Cotton.
Dear Sir, With reference to the above A/T we are in receipt of your Regd. Letter No.101/504/K2/476/Amd. No.465 dt.13.12.91 by which you have refixed the D.P. upto 28.2.92 as requested vide our letter No.476/RC/91 dt.20.11.91 and thanks for the same. Your above letter was received by us on 2.1.92.
In this regard we draw your kind attention towards personal meeting held with you on 19.11.91 in your office. It was requested by the undersigned to refix the D.P. upto 31.3.92 as requested in our letter dt.15.11.91. In response to our letter you have assured that the refixation of the delivery shall be given to us immediately upto 28.2.92. But the refixation of the D.P. letter No.101/504/K2/476/Amdt. No.465 dt.13.12.91 was only received by us on 2.1.92.
We therefore, request you to kindly refix the D.P. upto 31.3.92 as more than 45 days have passed from the Date of our discussion and receipt of your letter.
Thanking you,
Yours faithfully, For Tirupati Texco Products (P) Ltd.
DIRECTOR.
Letter dated 10.2.1992
No.101/584/K-2/476 Dated: 10.2.92
M/s Tirupati Texco Products (P) Ltd.,
132-B, Cooperative Industrial Estate,
Kanpur-22.
Sub:- A/T No.101/584/K-2/476/COAD dt.28.9.90 for supply of
Rope Cotton.
Ref:- Your letter No.476/RC/91 dt. 20.1.92.
Dear Sirs,
Please refer to your letter cited under reference, this is to inform you that the delivery period was refixed accordingly as per your offer. Any how you are hereby advised to supply the stores and regarding delivery period when you will approach for extension of D.P. The delivery period shall be considered. You are requested to inform the latest development of supplies to this office within 10 days.
This is however without any prejudice to the terms & conditions of the contract.
Yours faithfully
(D.N. SINGH) ASSTT. DIRECTOR OR D.S. & D."
6. The court below has relied upon second para of the letter dated
20.1.1992 whereby the respondent has asked for extension of delivery
period, however, in my opinion the court below has fallen into a clear error
in overlooking the first para of this very letter which showed that the
respondent thanked the appellant for re-fixing the delivery period i.e the
respondent accepted the amended delivery period for supply. The respondent
however only prayed for further extension of the delivery period because the
fresh delivery period would expire on 28.2.1992. Delivery extension was
asked because as per the respondent there was delay in receipt of the letter
issued by the appellant dated 13.12.1991 inasmuch as the same was received
by the respondent only on 2.1.1992. Whatever doubt remained that the
contract was concluded/entered into by the appellant's letter dated
13.12.1991 becomes clear from the letter of the appellant to the respondent
dated 10.2.1992 and which makes it more than abundantly clear that the
delivery period upto 28.2.1992 was fixed/refixed according to the 'offer' of
the respondent i.e the appellant re-affirmed the fact that the letter of the
respondent dated 20.11.1991 was an offer and appellant accepted the offer
by issuing its letter dated 13.12.1991. In my opinion, therefore, there cannot
be any doubt that the contract stood concluded when the appellant issued its
letter dated 13.12.1991 because this letter dated 13.12.1991 was an
acceptance of the offer of the respondent given by the respondent's letter
dated 20.11.1991 for re-fixing the delivery period upto 28.2.1992. As
already stated above, the respondent thanked the appellant for accepting the
fresh delivery period ending on 28.2.1992 but only requested a further
extension of the same, however, such request cannot take away the fact that
there was a finality with respect to a specific date of the delivery period
being arrived at and hence a concluded contract.
7. In my opinion therefore the arbitrator was justified in referring
to this letter dated 20.1.1992 for holding that contract was concluded, and
this becomes clear from the first para last few lines of internal page 4 of the
Award dated 13.2.2001. The court below accordingly was not justified in
accepting the objections and setting aside the Award and therefore the
findings and conclusions of the court below are set aside and the Award is
restored.
8. Learned counsel for the respondent however vehemently argued
that even assuming the respondent was guilty of breach of contract, yet, the
risk purchase amount of Rs.29,925/- ought not to have been awarded to the
appellant because this risk purchase amount is on account of the acceptance
of the fresh risk purchase tender ignoring the six other offers which were
lower than the offer given by the respondent pursuant to the risk purchase
tender. Learned counsel for the respondent however does not dispute that
the case of the appellant before the arbitrator was that the persons whose
tenders were not accepted were unregistered partnership firms, and appellant
did not accept the tenders from them for that reason and also for the reason
that those entities were not having requisite experience. Therefore once
legitimate reasons exist for accepting a particular tender at a higher rate,
because of lack of reliability and other factors pertaining to other tenderers,
it cannot be said that respondent is not liable for the risk purchase amount of
Rs.29,925/-. I may note that the appellant has claimed this amount of risk
purchase because the risk purchase tender was ultimately awarded to one
M/s. S.R. Enterprises from Kanpur.
9. Learned counsel for the respondent sought to place reliance
upon the judgment of this Court in the case of Union of India Vs. Daisy
Trading Corporation 2006 (130) DLT 471 to argue that once the terms of
the risk purchase tender are different than the tender which is cancelled on
account of breach, then, the arbitrator has committed an error in awarding
the amount of the higher risk purchase tender. I do not agree because no
doubt ordinarily the amount of damages is as per the lowest risk purchase
tender however if the lower tenders are for valid reasons not accepted by the
Union of India, there is justification, and accordingly, the risk purchase
amount for the higher cost would be payable by the respondent.
10. In view of the above, appeal is allowed. Impugned judgment of
the court below dated 10.11.2010 is set aside and the Award of the arbitrator
dated 13.2.2001 is restored whereby the appellant has been awarded a
money decree for a sum of Rs.29,925/-. Parties are left to bear their own
costs.
APRIL 24, 2014 VALMIKI J. MEHTA, J. Ne
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!