Citation : 2013 Latest Caselaw 4474 Del
Judgement Date : 27 September, 2013
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Reserved on : 01.08.2013
Date of Decision : 27.09.2013
+ WP(C) NO. 6941/2011
BHOLA RAM ..... Petitioner
Through: Mr. Rakesh Tiku, Sr. Adv., with Mr.
Prakash Gautam and Mr. Vivek Ohja, Advocates.
versus
GNCTD ..... Respondent
Through: Ms. Rachna Srivastava, Adv. for R1
Ms. Saroj Bidawat for UOI
Ms. Ferida Satarawala, Adv. for PWD-R3
CORAM:
HON'BLE MR. JUSTICE S. RAVINDRA BHAT
HON'BLE MR. JUSTICE NAJMI WAZIRI
MR. JUSTICE NAJMI WAZIRI
1. The petitioner seeks the quashing of Notification dated 9 th August,
2010 issued by the respondent, Government of National Capital
Territory of Delhi ("GNCTD") under sections 4 and 17 (1) and (4) of
the Land Acquisition Act, 1894 ("Act") dispensing with the hearing
under section 5A of the Act, as well as Notification dated 4 th August,
2011 under section 6 of the Act, declaring that the land was required
for „public purpose‟ i.e. modification and improvement of the T-
WP(C) No.6941 /2011 Page 1
junction of Anuvrat Marg and Aurobindo Marg. The petitioner also
seeks quashing of the undated notice purported to have been issued
under sections 9 and 10 of the Act.
2. The land in question is 4 biswas in Khasra No. 169/2 in Lado Sarai,
New Delhi ("property"), measuring about 200 square yards. The
petitioner claims adverse possession of the property by virtue of being
in continuous possession of it since 1948. To demonstrate his
continuous possession, he relies upon an order of 22nd February 1979
passed by the Court of Sh. S.C. Poddar, SDM (Revenue Assistant) in a
suit titled Kumari Keertika Vardhan v Bhola Ram, filed under section
84 of the Delhi Land Reforms Act, 1954, which order recorded under:
"The evidence and documents on record therefor prove
clearly that the defendant was in possession of the suit
land for much longer than three years before the date of
filing of the Application under section 84 of the Delhi
Land Reforms Act and obviously the suit is barred by
limitation and is decided in favour of the defendant."
3. The revision preferred against the said order was rejected by the
Financial Commissioner on 13th March, 1980. The property is adjacent
to a petrol pump and a ground floor structure has been built upon it.
The petitioner has also annexed municipal records showing that he had
WP(C) No.6941 /2011 Page 2
a cycle shop registered at the said address under the Delhi Shops and
Establishments Act, 1954 vide a certificate dated 7th December, 1984
issued by the Chief Inspector, Shops and Establishments, Delhi.
Documents of proceedings to assess property tax apropos 1A, Lado
Sarai, New Delhi (being the property, identified by its postal address),
are also annexed alongwith supporting receipts of payment of property
tax for the years 2005 and 2010. The petitioner claims to be enjoying
the property exclusively and in his individual right. Ms. Kanika Devi
Verma, in whose name the land is recorded in the Revenue Records,
was proceeded ex parte in these proceedings after service of notice.
4. The petitioner argues that his property alone is sought to be acquired,
whereas the land immediately behind his property, which would
necessarily be required for widening of the T-junction, has not been
notified for acquisition. Therefore, the purported acquisition is
evidently not for the professed public purpose. He contends that unless
all requisite lands are acquired for widening of the road at the said T-
junction, including the area under the petrol pump adjacent to the
property and also the area behind it, the project could neither be
WP(C) No.6941 /2011 Page 3
initiated nor could it be viably completed. Therefore, he sought to
contend, the section 4 notification would itself be without basis and a
blatantly arbitrary exercise of power.
5. Evidently, the notification of 9th August, 2010 under sections 4 and 17
of the Act, was issued because the property was ostensibly required
urgently for the stated public purpose. However, for almost 360 days of
the year thereafter, the government did not take any action to
demonstrate urgency in the acquisition of the property. Mr. Rakesh
Tiku, learned Senior Advocate, submits on behalf of the petitioner that
the notification under section 6 was issued on 4 th August, 2011, i.e.,
merely four days before the expiry of the one year statutory period for
the section 6 declaration. He contended that the lackadaisical approach
of the government shows that there was no real urgency for acquisition
of the property, and it was only for denying a fair hearing under section
5A, that the notification under section 17 (4) was issued. He contended
that the same was an arbitrary and a colourable exercise of power; it
also resulted in denial of the valuable right of hearing under section 5A.
Therefore it ought to be quashed
WP(C) No.6941 /2011 Page 4
6. In its counter affidavit, as well as in its submissions before the Court,
the government contends that over the years, like its population, the
volume of traffic has increased manifold in the National Capital
Territory of Delhi. One consequence of the profusion of vehicular
traffic is a daily traffic bottleneck due to the narrow approach leading
to the T-junction in question. This required urgent attention and a
lasting solution, all-the-more-so in view of the then ensuing
Commonwealth Games ("CWG"). It was further submitted by Ms.
Rachna Srivastava, Counsel for the Land & Building Department/Land
Acquisition Commissioner, i.e., R2, that keeping the CWG in view, a
requisition was sent by the Public Works Department ("PWD") of the
GNCTD on 9th February, 2009 for acquisition of the 4 biswas of land
(the property). This requisition was supported by a recommendation of
the Delhi Traffic Police. It is stated that on either side of Anuvrat Marg
(the road concerned), approximately 250 square metres each were
required for widening of the road under the guidelines for the CWG.
Accordingly, the location plan for requisition was sent to the Land
Acquisition Commissioner (South) ("LAC") on 13th May, 2009 to
WP(C) No.6941 /2011 Page 5
ascertain the availability of land and to elicit the relevant records of the
Revenue for acquisition proceedings. It is further submitted that the
latter took almost a year to send his joint survey report on 4th April,
2010 to the PWD, after computing 80% of the acquisition-
compensation amount. Thereafter, another four months were spent over
drafting a notification, conducting survey, etc., with respect to issuance
of the notifications under sections 4 and 17 on 9th August, 2010 and as
aforesaid, about 360 days thereafter the notification under section 6
was issued. Thus, Counsel for the Respondent No. 1 submitted, there
was actually no delay in the matter and that the time taken in the
processing of the file was on account of official movement of the same
and issuance of notifications was in the ordinary course.
7. Learned Senior Advocate for the petitioner, placed reliance upon the
judgement of the Supreme Court in Anand Singh and Anr. v State of
Uttar Pradesh and Ors., reported in (2010) 11 SCC 242. In that case,
referring to various precedents on the issue, the Supreme Court held
inter alia as under:
"40. "Eminent domain" is the right or power of a
sovereign State to appropriate the private property
WP(C) No.6941 /2011 Page 6
within the territorial sovereignty to public uses or
purposes. It is exercise of strong arm of the
Government to take property for public uses without
the owner's consent. It requires no constitutional
recognition; it is an attribute of sovereignty and
essential to the sovereign government. [Words and
Phrases, Permanent Edn., Vol. 14, 1952 (West
Publishing Co.).]
41. The power of eminent domain, being inherent in
the Government, is exercisable in the public interest,
general welfare and for public purpose. Acquisition of
private property by the State in the public interest or
for public purpose is nothing but an enforcement of the
right of eminent domain. In India, the Act provides
directly for acquisition of particular property for
public purpose. Though the right to property is no
longer a fundamental right but Article 300-A of the
Constitution mandates that no person shall be deprived
of his property save by authority of law. That Section
5-A of the Act confers a valuable right to an individual
is beyond any doubt. As a matter of fact, this Court has
time and again reiterated that Section 5-A confers an
important right in favour of a person whose land is
sought to be acquired.
42. When the Government proceeds for compulsory
acquisition of a particular property for public purpose,
the only right that the owner or the person interested
in the property has, is to submit his objections within
the prescribed time under Section 5-A of the Act and
persuade the State authorities to drop the acquisition
of that particular land by setting forth the reasons such
as the unsuitability of the land for the stated public
purpose; the grave hardship that may be caused to him
by such expropriation, availability of alternative land
for achieving public purpose, etc. Moreover, the right
conferred on the owner or person interested to file
WP(C) No.6941 /2011 Page 7
objections to the proposed acquisition is not only an
important and valuable right but also makes the
provision for compulsory acquisition just and in
conformity with the fundamental principles of natural
justice.
43. The exceptional and extraordinary power of doing
away with an enquiry under Section 5-A in a case
where possession of the land is required urgently or in
an unforeseen emergency is provided in Section 17 of
the Act. Such power is not a routine power and save
circumstances warranting immediate possession it
should not be lightly invoked. The guideline is inbuilt
in Section 17 itself for exercise of the exceptional
power in dispensing with enquiry under Section 5-A.
Exceptional the power, the more circumspect the
Government must be in its exercise. The Government
obviously, therefore, has to apply its mind before it
dispenses with enquiry under Section 5-A on the aspect
whether the urgency is of such a nature that justifies
elimination of summary enquiry under Section 5-A."
(Emphasis supplied)
Dwelling further upon the issue of how mere likelihood of delay (in the
acquisition proceeding) ought to not be the only consideration for dispensing
with hearing under section 5A, the Supreme Court observed:
"46. As to in what circumstances the power of emergency
can be invoked are specified in Section 17(2) but
circumstances necessitating invocation of urgency under
Section 17(1) are not stated in the provision itself ... In
many cases, on general assumption likely delay in
completion of enquiry under Section 5-A is set up as a
reason for invocation of extraordinary power in dispensing
with the enquiry little realising that an important and
valuable right of the person interested in the land is being
WP(C) No.6941 /2011 Page 8
taken away and with some effort enquiry could always be
completed expeditiously."
8. Mr. Tiku further sought to rely upon the judgement of the Supreme
Court in the case of Devender Kumar Tyagi and ors. v State of Uttar
Pradesh, (2011) 9 SCC 164, wherein the observations made in Radhey
Shyam v State of Uttar Pradesh, (2011) 5 SCC 553 were reiterated:
"77 ...
(iv) The property of a citizen cannot be acquired by the
State and/or its agencies/instrumentalities without
complying with the mandate of Sections 4, 5-A and 6 of
the LA Act. A public purpose, however, laudable it may
be does not entitle the State to invoke the urgency
provisions because the same have the effect of depriving
the owner of his right to property without being heard.
Only in a case of real urgency, the State can invoke the
urgency provisions and dispense with the requirement of
hearing the landowner or other interested persons.
...
(v) Section 17(1) read with Section 17(4) confers extraordinary power upon the State to acquire private property without complying with the mandate of Section 5-A. These provisions can be invoked only when the purpose of acquisition cannot brook the delay of even a few weeks or months. Therefore, before excluding the application of Section 5-A, the authority concerned must be fully satisfied that time of few weeks or months likely to be taken in conducting inquiry under Section 5-A will, in all probability, frustrate the public purpose for which land is proposed to be acquired.
..."
WP(C) No.6941 /2011 Page 9 The Supreme Court further referred to its earlier dictum in Dev
Sharan v State of Uttar Pradesh, (2011) 4 SCC 769, where it had held
as under:
"37. Thus the time which elapsed between publication of Section 4(1) and Section 17 notifications, and Section 6 declaration in the local newspapers is 11 months and 23 days i.e. almost one year. This slow pace at which the government machinery had functioned in processing the acquisition, clearly evinces that there was no urgency for acquiring the land so as to warrant invoking Section 17(4) of the LA Act."
9. On the strength of the above judgements, Learned Senior Advocate
sought to urge that the present case is clearly one where exercise of the
power of judicial review of this Court is warranted, inasmuch as not
only was there no urgency requiring the exercise of the powers under
section 17 (4), but any urgency even if it did exist, would have long
perished due to the delay - both pre and post-notification. This delay is
exclusively by the government‟s own volition, inaction, indifference,
lethargy, call it whatever one may.
10. This Court finds merit in the contentions of the petitioner. It is settled
law that the right to hearing under section 5A is a valuable right and it
WP(C) No.6941 /2011 Page 10 cannot be taken away from the citizen by merely recording in the file
that the land is required urgently. The corresponding facts and
circumstances of each case would have to be examined to establish that
the invocation of section 17 (4) is just and fair.
11. This court notices that more recently the Supreme Court, in Darshan
Lal Nagpal (Dead) by LRs. v Government of NCT of Delhi and ors.,
(2012) 2 SCC 327 had occasion to deal with a similar fact situation of
emergency provisions under section 17 being invoked, interestingly
again in the context of the upcoming CWG. Striking down the action of
the government as being wholly unjustified in the facts of the case,
given the undue delay both pre and post-notification, the Court,
observed:
"38. A recapitulation of the facts would show that the idea of establishing 400/220 kV substation was mooted prior to August 2004. For next almost three years, the officers of DTL and DDA exchanged letters on the issue of allotment of land. On 28-7-2008 the Secretary (Power), Government of NCT of Delhi-cum-CMD, DTL made a suggestion for the acquisition of land by invoking Section 17 of the Act. This became a tool in the hands of the authorities concerned and the Lieutenant Governor mechanically approved the proposal contained in the file without trying to find out as to why the urgency provisions were being invoked after a time gap of five
WP(C) No.6941 /2011 Page 11 years. If the substation was to be established on emergency basis, the authorities of DTL would not have waited for five years for the invoking of urgency provisions enshrined in the Act. They would have immediately approached the Government of NCT of Delhi and made a request that land be acquired by invoking Section 17 of the Act. However, the fact of the matter is that the officers functionaries/concerned of DTL, DDA and the Government of NCT of Delhi leisurely dealt with the matter for over five years. Even after some sign of emergency was indicated in the letter dated 9-9-2008 of the Joint Secretary (Power), who made a mention of the Commonwealth Games scheduled to be organised in October 2010, it took more than one year and two months to the competent authority to issue the preliminary notification. Therefore, we are unable to approve the view taken by the High Court on the sustainability of the appellants' challenge to the acquisition of their land.
(Emphasis supplied)
12. It is clear from the precedents cited above, that power under section 17
(4) to dispense with the hearing under section 5A must not only be
exercised sparingly and only in cases where the public purpose for
which the acquisition is sought brooks no delay, but the government
ought to exhibit such urgency in its actions as well - during the process
of acquisition - both pre and post-notification. While it cannot be held
that delays by the government, whether pre or post-notification would,
by itself be good ground for the courts to interfere with the State‟s
WP(C) No.6941 /2011 Page 12 invocation of the power under section 17 (4), the court would rightly
exercise its power of judicial review and restore to the land owner
his/her right to be heard under section 5A where the delay is of such a
nature as to negate the very urgency claimed for invoking section 17
(4).
13. We have had the benefit of perusing the file pertaining to the property,
and note that subsequent to a draft letter being prepared on 13 th May
2009 which admittedly was issued to the LAC on the same date, there
is a perplexing silence of inactivity till 20th April 2010. This stares in
the face of the professed urgency which was otherwise vigorously
emphasised by the respondent for the sake of invocation of section 17
(4). The records also reflect that indeed the PWD had requested the
Delhi Development Authority ("DDA") for acquisition of the aforesaid
land way back on 14th January, 2009. Therefore, one could safely
presume that the preparatory work for widening of the T-junction
would have started some time towards the end of 2008 i.e. at least 2-3
months earlier.
WP(C) No.6941 /2011 Page 13
14. From the aforesaid narration of facts, it is evident that although the
acquisition was requisitioned in February 2009 to remove the perennial
traffic bottleneck, coupled with the sense of urgency for a smooth flow
of traffic especially in view of the then ensuing CWG in October, 2010
yet the respondent itself took about nineteen months to issue the section
4 notification. This, by no stretch of imagination, can be said to
demonstrate any urgency.
15. Even thereafter, once the notifications under sections 4 and 17 were
issued, the Government took almost a year (less four days) to issue the
section 6 notification. Where both the requisitioning and the acquiring
authority took almost twenty months to two years in issuing the
section 4 notification and then another year in issuing the section 6
notification, it could hardly be said that there was any urgency.
Allthemoreso when only one land owner was concerned for a small
parcel of around 200 square yards.
16. There is no gainsaying the fact that when traffic causes bottleneck on a
main traffic artery especially with the ever burgeoning traffic volume,
the sense of urgency ought be of an immediate and an escalating degree
WP(C) No.6941 /2011 Page 14 with every passing day. Neither the records, nor the actions of the
respondent reflect any such urgency or responsible exercise of
authority as would be expected in such cases. Therefore, the ground for
invocation of powers under sections 17 (1) and (4) is untenable.
17. Whatever urgency there may be with respect to the need for the
property and consequently the compelling reason for issuance of
notification under section 17 (4) for dispensing with the section 5A
hearing, had been frittered away by the lethargic and indeed
lackadaisical approach in the processing of the file by both - the
requisitioning and acquiring authorities. The Lt. Governor, on 16 th July
2010, recorded his satisfaction for the urgent acquisition of the land in
question and accordingly dispensed with the application of section 5A.
The notification under sections 4 and 17(4) was issued three weeks
thereafter. However, the same records before the Lt. Governor would
have also borne out that for almost 18 months, since the requisition for
land was made by the PWD by their letter-way back on 9th February
2009, no action would be found evidencing urgency in the acquisition
proceedings. In the circumstances, the Lt. Governor‟s satisfaction
would be without basis and not borne out from the records. The mere
WP(C) No.6941 /2011 Page 15 statement of the urgent requirement of the land would itself not be
sufficient reason to enable invocation of that provision of statute. The
claim of urgency is further defeated by the fact that the LAC himself
took almost a year simply to survey the lands (along with officials of
the PWD) to prepare the aks shajra.
18. In view of the above discussion, this court is of the opinion that there
was clearly no justification for the invocation of the urgency provision
of section 17 (4) and the consequent denial to the petitioner of the
valuable right of hearing under section 5A. Consequently, we quash the
notification dated 9th August 2010 under section 17 (4), as well as the
notification of 4th August 2011 under section 6, along with the undated
notice purported to be issued under sections 9 and 10 of the Act.. The
respondent would accord the petitioner his rights under section 5A.
The GNCTD is at liberty to complete the acquisition proceeding, if
advised, after the hearing under section 5A and after considering the
Collector‟s report.
19. Before disposing off this petition this court notices, not without some
concern, that in the present case, evidently, the action of the
WP(C) No.6941 /2011 Page 16 government authorities both pre and post-notification was
lackadaisical, even phlegmatic. The notification under section 6, issued
on 4th August, 2011 appears to have been done so in a hurry possibly to
meet the statutory limitation of one year. No explanation, however,
appears either from the acquisition notifications file or from the
submissions made before this court as to why the PWD had not taken
any action since January 2009 or why the LAC failed to take any action
between May 2009 and April 2010. Even assuming that urgency
existed in early 2009 when the PWD had originally requisitioned the
land because of the emergent situation as then recorded, such urgency
has perhaps been frittered away by the authorities by their lethargic and
lackadaisical approach. The file languished. It holds no evidence
apropos the professed urgent need of the property in public interest.
While it is incontrovertible that the right or power of eminent domain
cannot be abused by the government, so also is it indisputable that
authorities charged with exercising such power ought to act with as
much efficiency and promptitude as warrants the urgency and exigency
of the situation. It would be a worthwhile exercise for a diligent
administration to identify officials who, because of their slothful or
WP(C) No.6941 /2011 Page 17 indifferent disposition or for other reasons, fail to accord the requisite
attention to the provision of adequate remedies to acknowledged urgent
needs of a people. This need is allthemore acute in the National Capital
Territory bearing in mind its fast burgeoning population and traffic
density and projected growth. Accountability ought to be fixed on such
officers who let project files languish which in turn delays the creation
of adequate civic infrastructure, thus compounding the problems of the
city and subjecting the citizens to unwarranted sufferings.
20. The writ petition is allowed but in the abovementioned terms. There
shall be no order as to costs.
NAJMI WAZIRI (JUDGE)
S. RAVINDRA BHAT (JUDGE)
27th September, 2013
WP(C) No.6941 /2011 Page 18
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!