Citation : 2013 Latest Caselaw 4397 Del
Judgement Date : 25 September, 2013
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ I.A. No. 9164/2012 in CS(OS) 1318/2011
% Reserved on: 19th September, 2013
Decided on: 25th September, 2013
RAJESH KUMAR GUPTA ..... Plaintiff
Through: Mr. Naresh Khanna, Advocate.
versus
SONIA BALA JAIN ..... Defendant
Through: Mr. Manoranjan, Advocate.
CORAM:
HON'BLE MS. JUSTICE MUKTA GUPTA
1.
By this application the Plaintiff seeks a decree as per provisions of
Order XXII Rule 4 r/w Section 151 CPC in favour of the Plaintiff and
against the Defendant directing the Defendant to execute and register sale
deed in favour of the Plaintiff in respect of the suit property and release the
balance sale consideration of Rs. 15 lakhs which stands deposited in this
Court to the Defendant and in case of failure on the part of the Defendant, to
appoint an officer of this Court to execute and register the sale deed of the
suit property in favour of the plaintiff.
2. Learned counsel for the Plaintiff/applicant contends that the
Agreement to Sell dated 3rd April, 2010 between the parties has not been
denied by the Defendant. Further the payment of Rs. 30 lakhs to the
Defendant has also not been denied. The Plaintiff had sent a notice dated
27th April, 2011 to the Defendant seeking specific performance of the
contract and in reply thereto no such defence has been taken which has been
now pleaded in the written statement. Only in the reply dated 15 th May,
2011 it is stated that the Plaintiff was required to pay a further sum of Rs. 10
lakhs beyond Rs. 15 lakhs. The claim of further sum of Rs. 10 lakhs is
clearly an after thought and there is no document in relation thereto. Hence
in view of the admissions made, the Plaintiff is entitled to decree as prayed
for.
3. Learned counsel for the Defendant on the other hand contends that the
Agreement to Sell cannot be read in piecemeal. Para-2 of the Agreement to
Sell dated 3rd April, 2010 clearly contemplates that the amount given would
be forfeited if the balance sale consideration was not paid by 10th November,
2019. The Defendant was only required to provide the approval certificate
for the lift. However, the Plaintiff started demanding the lift as well. In para-
9 of the plaint it is stated that the lift was not provided. There is no notice
before 10th November, 2010, which was the date when the contract was
required to be concluded, stating that the Plaintiff inspected the premises and
the work had not been completed. Thus the Plaintiff is not entitled to a
decree as prayed for as there is no admission of the facts mentioned in the
plaint.
4. I have heard learned counsel for the parties.
5. A brief exposition of the facts is that the Plaintiff had entered into an
Agreement to Sell dated 3rd April, 2010 with the Defendant for sale of
property bearing No. C-9/77, Upper Ground Floor (First Floor), Yamuna
Vihar, Delhi-110053 on the plot of land measuring approximately 80 sq.
yards comprising two bed room, drawing, dining, two toilets, kitchen etc., as
per the tentative site plan along with the car parking on the ground floor
(hereinafter referred to as 'the suit property') for a total sale consideration of
Rs. 45 lakhs. The Plaintiff paid a sum of Rs. 30 lakhs out of the said Rs. 45
lakhs and thus the balance of Rs. 15 lakhs remained. It is stated by the
Plaintiff that the Defendant assured that best available material would be
used for the construction and the building so constructed will be having
approved lift, independent car parking for each floor on the ground floor;
modular kitchen and the construction would be as per the duly approved plan
and design and as per earthquake zone 5 specification. The Plaintiff time
and again requested the Defendant to complete the construction and finish
the work within the stipulated time, that is, by 10th November, 2011 as per
the agreement when the Plaintiff was to give the balance payment of Rs. 15
lakhs. However, the Defendant continued to avoid the Plaintiff on one
pretext or the other objecting to the visit of the Plaintiff to the site to inspect
the construction, material, design, finish work etc. In the first week of April,
2011 when the Plaintiff impressed upon the Defendant and her husband to
complete the construction, finishing work and called upon them for
inspection, the Defendant and her husband demanded the balance payment
of Rs. 15 lakhs from the Plaintiff to complete the remaining work on the first
floor of the building contrary to the terms of the subject agreement. Thus the
Defendant has committed breach of agreement having failed to hand over the
possession of the suit property within the stipulated time, that is, 10 th
November, 2010 with complete works like complete wall stone in the
staircase; lift, floor grinding and finishing, electric fittings and fixtures,
electric connection/meter, kitchen, wood work and installation, water
connection etc. Despite the Defendant having failed to comply with the
terms, the Defendant got issued a legal notice dated 15 th April, 2011 to the
Plaintiff through the Advocate asking the Plaintiff to make the balance
payment as per the Agreement dated 3rd April, 2010 and in the event of
failure on the part of the Defendant it was stated that the Defendant would
initiate legal proceedings. The Plaintiff replied to the legal notice on 25th
April, 2011 stating the true and correct facts and failure/breach committed by
the Defendant as per the terms of agreement and asking her to hand over the
possession of the suit property after inspection. The Plaintiff also issued a
legal notice dated 27th April, 2011.
6. In the written statement the stand of the Defendant is that the
Defendant duly constructed the suit property as per the agreement dated 3 rd
April, 2010 and also in accordance with the changes as pointed out later by
the Plaintiff however, the Plaintiff deliberately avoided taking the possession
of the suit property and the payment of the balance amount. Since the
Plaintiff has failed to perform his part of the Agreement to Sell there is no
cause of action in favour of the Plaintiff. Since the Plaintiff asked for certain
changes in the building material and the other works, the Defendant and her
husband duly informed the Plaintiff that these changes as asked for will cost
another Rs. 10 lakhs apart from the agreed cost to which the Plaintiff duly
agreed. Thus the Defendant proceeded with those changes and completed
the construction work as agreed to by the Agreement to Sell. Since 10th
November, 2010 the Defendant had approached the Plaintiff several times
asking him to take possession of the property and for payment of the balance
amount. However, the Plaintiff deliberately avoided the balance payment as
well as taking the possession of the aforesaid suit property wherein the
Defendant has invested much more of money to fulfill the demands of the
Plaintiff. After November, 2010 the Plaintiff stopped visiting the site and
when the Defendant asked for the balance payment and for extra expenses
the Plaintiff started avoiding her. The Defendant carried out the works like
false ceiling in all the rooms, imported fancy lights (LED), imported tiles,
exclusive imported sanitary fittings in the bathroom, woodwork in all the
rooms with specific carving for LCDs and other, metal sheet work was
replaced by stainless steel work, complete wall stone in the staircase, the
heights and width of the doors were altered, supreme quality polish costing
three times the ordinary one. There was no agreement between the parties to
install the lift and the Defendant had only agreed to provide approval
certificate for installation of the lift. Admittedly the legal notice of the
Plaintiff dated 27th April, 2011 was an after thought and a counter blast to
the legal notice of the Defendant.
7. There is no doubt that the Defendant has not denied the Agreement to
Sell or receipt of part consideration of Rs. 30 lakhs. However, a perusal of
the Agreement to Sell shows that the Defendant in parat-4 only agreed to
provide the approval certificate for installation of the lift at the premises at
his own cost and not the lift. Further a perusal of the Ex. P2 i.e. the
specifications for construction that has to be carried out in the suit property
entered into between the parties along with the Agreement to Sell also did
not provide for false ceiling, lift, wall stone, earthquake zone 5 specification
etc. as stated by the Plaintiff in the plaint. Further the notice of the
Defendant dated 15th April, 2011 Ex. P5 states that the Defendant
approached the Plaintiff a number of times since 10 th November, 2010 to
take the possession of the property and make the balance payment. It is also
stated that the Defendant invested a large sum of money in order to fulfill the
demands and desire of the Plaintiff in view of the Agreement to Sell dated
3rd April, 2010 and the Agreement of specification of construction. A
perusal of the reply to the notice by the Plaintiff dated 25 th April, 2011
shows that number of requirements which were not specified in the
agreement have been stated to have not been done. In view of this specific
stand in the written statement which is also evident from the documents filed
by the Plaintiff, the Plaintiff is required to prove that the Plaintiff did not ask
for any extra specification resulting in escalation in the price and that the
Plaintiff was ready and willing to perform his part of the contract. The
Plaintiff is not entitled to a decree at this stage on the basis of the averments
made in the written statement.
Consequently, the application is dismissed. However, the observation
made hereinabove will have no bearing on the final decision of the suit.
(MUKTA GUPTA) JUDGE SEPTEMBER 25, 2013 'vn'
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!