Citation : 2013 Latest Caselaw 5252 Del
Judgement Date : 18 November, 2013
*IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of decision: 18th November, 2013
+ RFA 232/2013 & CM No.15440/2013 (for stay).
RAJIV MAIRA & ANR. ..... Appellants
Through: Mr. Sudhanshu Batra, Sr. Adv.
with Mr. Sushil Shukla, Selender
Singh & Mr. Arjun Mahajan, Advs.
versus
M/S APEX APARTMENTS PVT LTD & ORS. ..... Respondents
Through: Mr. Harish Malhotra, Sr. Adv. with
Ms. Radhika Chandrasekher, Adv.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
RAJIV SAHAI ENDLAW, J
1. The appeal impugns the judgment and decree dated 23rd January, 2013
of the Court of the Addl. District Judge-04, South District, Saket Court
Complex, New Delhi of in limine dismissal, of the CS. No.366/12 filed by
the two appellants for specific performance of an Agreement of Sale of
immovable property being space No.S-4 on the second floor of plot No.E-
480, Greater Kailash Part-II, New Delhi and for permanent injunction, on
the ground of the claim of the appellants/plaintiffs being barred by time. The
learned Addl. District Judge thus rejected the plaint under Order VII Rule 11
(d) of the CPC.
2. The senior counsel for the appellants/plaintiff on 30 th August, 2013
contended, (a) that the appellants / plaintiffs had agreed to purchase
apartment / space / unit No.S-4, admeasuring 1500 sq.ft., second floor of E-
480, Greater Kailash-II, New Delhi proposed to be constructed by the
respondents; (b) that though in the Agreement to Sell dated 14.10.1987, it
was mentioned that the building was proposed to be completed by 30 th
September, 1989 but the construction was stalled for long and has
recommenced 'now' only and since the respondents refused to honour the
Agreement, the suit was filed; (c) that the learned Additional District Judge
has been unduly swayed by the clause in the Agreement of the construction
being proposed to be completed by 30th September, 1989; and, (d) that the
purchase consideration was payable by the appellants / plaintiffs as per the
stage of construction and since the construction was stalled, the question of
the Agreement becoming enforceable on an earlier date did not arise.
3. On the aforesaid contentions, notice of the appeal was issued and even
though the appeal was not accompanied with any application for interim
relief but on the oral prayer, the respondents were till the next date of
hearing restrained from alienating, encumbering or parting with possession
of the apartment/space/unit agreed to be sold to the appellants/plaintiffs.
4. The respondents filed reply, but upon the appellants/plaintiffs on 27th
September, 2013 seeking time for rejoinder, the senior counsel for the
respondents/defendants expressed readiness to argue even without reference
to the reply. However on request of the appellants/plaintiffs, hearing was
adjourned.
5. During the hearing on 4th October, 2013 the issue between the parties
was found to boil down to, whether the second floor of property No.E-480,
Greater Kailash-II was constructed in the year 1988-89 as contended by the
senior counsel for the respondents or in the year 2011-2012 as contended by
the senior counsel for the appellants/plaintiffs. The senior counsel for the
respondents/defendants on that date showed the House Tax Survey Report
dated 1st December, 1988/January, 1989 showing the second floor in
existence and Form-C and Form-D under the Building Bye-Laws having
been issued on 5th January, 1988 and 7th December, 1988 respectively and
which suggested that the construction activity had been completed by that
time. The hearing was however again adjourned on the request of the senior
counsel for the appellants/plaintiffs to enable the appellants/plaintiffs to
enquire further into the matter, however cautioning the appellants/plaintiffs
that if inspite of satisfactory proof of construction in the year 1988-89 being
available the appellants/plaintiffs insist upon trial, the same would be on
such terms as may be imposed by the Court.
6. The senior counsel for the appellants/plaintiffs has today handed over
a list of documents dated 18th November, 2013 which is taken on record and
has invited attention to the report dated 15th May, 1995 of a Local
Commissioner appointed in a Court proceeding relating to ground floor of
the property, at pages 66 to 68 and an order dated 19th November, 1991 of
the MCD Appellate Tribunal pertaining to the said property at pages 44 to
47 thereof to contend that the construction was not complete even on the
ground floor on that date. However the documents at pages 66 to 68 are only
with respect to the ground floor and the documents at pages 44 to 47 clearly
refer to the existence of a ground, first as well as second floor. The same are
thus not found to support the case of the appellants/plaintiffs of the
construction having been raised only in the year 2011-12.
7. The senior counsel for the appellants/plaintiffs faced therewith has
contended that as per the plans sanctioned in the year 1987 only a barsati
comprising of two bed rooms, dining room, kitchen, lobby etc. could be
constructed on the second floor.
8. However that is not the case with which the appellants/plaintiff have
approached the Court; rather it is the case of the appellants/plaintiffs at page
74 in para 27 of the plaint that till the year 2009-10 only basement roof slab
was constructed. The appellants/plaintiffs claim to have made the payment
till stage no.6 of the Agreement to Sell i.e. the payment due on the
commencement of casting of the ground floor roof slab and have not paid
the payment due w.e.f. commencement of casting of the first floor roof slab.
The documents prima facie suggest that not only the first floor but even the
second floor was in existence as on 12th August, 1991 when the MCD had
issued notice for demolition, the order on appeal whereagainst is at pages 44
to 47 supra of the compilation handed over today.
9. However this is not the stage to adjudicate the matter further. In the
light of the aforesaid though the impugned judgment cannot be sustained but
it has been enquired from the senior counsel for the appellants/plaintiffs that
since the appellants/plaintiffs are insisting on trial when prima facie it
appears that the appellants/plaintiffs did not make the requisite enquiries or
did not perform their part of the Agreement (the contention of the senior
counsel for the appellants/plaintiffs is that the appellants/plaintiffs were to
perform their part only upon demand being made by the
respondents/defendants and which was not made), why terms should not be
imposed on the appellants/plaintiffs including of making it clear that the
principles of lis pendens as enshrined in Section 52 of the Transfer of
Property Act, 1882 would not apply to the transaction, as the Supreme Court
in Vinod Seth Vs. Devinder Bajaj (2010) 8 SCC 1 has held within the
competence of the Court to do.
10. The senior counsel for the appellants/plaintiffs has contended that the
appellants/plaintiffs may be denied interim relief but their right in law to
applicability of lis pendens be not denied. It is contended that the
appellants/plaintiffs have paid 60% of the agreed sale consideration and the
documents do show that the property was under dispute in several litigations
and the appellants/plaintiffs even if ultimately not found entitled to the relief
of specific performance would be in any case entitled to the relief of
damages against the respondents/defendants and would be severely
prejudiced if the right in law of lis pendens is revoked.
11. The genesis of the judgment in Vinod Seth supra was the prejudice
suffered by the defendant in a suit for specific performance even in the
absence of any restraint order against him, due to applicability of the
principle of lis pendens and which virtually made the property inalienable or
inencumberable at market rates and with no measure left to compensate the
defendant in the event of the plaintiff in a suit for specific performance
ultimately failing. The costs, as suggested by the senior counsel for the
appellants/plaintiffs in the present case, also were not found sufficient to
compensate the defendant in such a situation. It has thus been put to the
senior counsel that it is but fair that if the appellants/plaintiffs want to put a
fetter on the property of the respondents/defendants, the appellants/plaintiffs,
suit should agree to compensate the respondents/defendants in the specified
amount, if ultimately losing in their case which, as per the procedure laid
down in law has to be entertained even though found to be doubtful.
12. The senior counsel for the appellants/plaintiffs has contended that the
said aspect be left to be adjudicated by the Trial Court.
13. I am not willing to agree. Once this Court has heard the counsels and
is setting down a suit which has been dismissed by the Trial Court, for trial,
inspite of availability of documents to show to the contrary to the case set up
by the appellants/plaintiffs, this Court would be failing in its duty if does not
settle the terms of the Trial.
14. The senior counsel for the appellants/plaintiffs on instructions states
that the appellants/plaintiffs are not willing to agree to any compensation to
the respondents/defendants in the event of ultimately failing in the suit.
15. In the circumstances, this Court is not left with any option but to make
principles of lis pendens inapplicable to the suit which though will have to
be put to trial.
16. The appeal therefore succeeds on aforesaid terms. The judgment and
decree of dismissal of the suit as barred by time is set aside observing that
the question of limitation cannot be decided without trial. The suit is
remanded to the Trial Court for decision afresh. However the property is
exempted from the operation of Section 52 of the Transfer of Property Act,
1882. The counsel for the respondents/defendants who are defendants in the
suit accept notice of the suit and state that written statement shall be filed
within 30 days. The parties to appear before the Addl. District Judge-04,
South District, Saket Court Complex, New Delhi and if the said Court does
not exist, before the District Judge (South) on 10th January, 2013.
17. Interim order is vacated.
18. The Trial Court record if had been requisitioned in this Court be
returned forthwith.
19. No costs.
20. Decree sheet be prepared.
RAJIV SAHAI ENDLAW, J
NOVEMBER 18, 2013 pp
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!