Citation : 2013 Latest Caselaw 5083 Del
Judgement Date : 6 November, 2013
R-48
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CRL.A. 186/2007
Decided on 06.11.2013
IN THE MATTER OF :
BHAWARLAL S. KOTHARI ..... Appellant
Through : Mr. P. Ojha, Mr. Alok Singh and
Mr. Suresh Kumar, Advocates
versus
REGISTRAR, APPELLATE TRIBUNAL FOREIGN EXCHANGE & ANR.
..... Respondents
Through Ms. Rajdipa Behura, Advocate
CORAM:
HON'BLE MS. JUSTICE HIMA KOHLI
HIMA KOHLI, J. (Oral)
1. The present appeal has been filed by the appellant, a permanent
resident of Mumbai, against an order dated 22.3.2006 passed by the
Appellate Tribunal for Foreign Exchange (in short 'the Tribunal') in
Appeal No.134/1996, preferred by him against the order dated
27.2.1996 passed by the adjudicatory authority holding inter alia that
the appellant had contravened the provisions of Section 8(1) of the
Foreign Exchange Regulation Act, 1973 (in short 'the FERA') and
imposing a penalty of Rs.87,000/- on him.
2. At the outset, learned counsel for the respondents opposes the
present appeal on twin grounds of maintainability, the first ground
being that the present appeal has been filed beyond the prescribed
period of limitation and the second ground is that this Court is not
vested with the territorial jurisdiction to entertain the same.
3. For deciding the objection of limitation taken by the counsel for
the respondents, as noted above, reference to some dates is
considered relevant. The impugned order is dated 22.3.2006. Section
35 of the Foreign Exchange Management Act, 1999 (in short 'FEMA')
provides for 60 days for filing an appeal in the High Court and the said
period of 60 days are to be reckoned from the date of communication
of the decision or order of the Tribunal to the aggrieved party. It is an
undisputed position that on the date of filing of the appeal, the
provisions of the FERA had ceased to apply and the provisions of FEMA
have been invoked by the appellant.
4. As per the learned counsel for the appellant, a certified copy of
the impugned order came to be served on the appellant on
27.12.2006. The records reveal that the present appeal was filed on
26.2.2007. If the period of 60 days for filing the appeal is reckoned
from 28.12.2006, the same would have expired on 25.2.2007.
However, 25.02.2007 happened to be a Sunday, and the present
appeal came to be filed on the very next working day, i.e. on
26.02.2007; as such it has been filed well within the period of
limitation. Therefore the objection raised as to the maintainability of
the appeal on the ground that it is barred by limitation, is found to be
devoid of merits and is turned down.
5. Coming to the second objection taken by the learned counsel for
the respondents with regard to lack of territorial jurisdiction, counsel
for the respondents refers to the Explanation appended to Section 35
of the FEMA to contend that the appellant who is a permanent resident
of Mumbai, being the aggrieved party, ought to have approached the
Bombay High Court to assail the impugned order. In support of her
submission that this Court is not vested with the territorial jurisdiction
to entertain the present appeal, she relies on the decision of the
Supreme Court in the case of Raj Kumar Shivhare vs. Assistant
Commissioner, Directorate of Enforcement, reported as 2010 (4)
SCALE 705.
6. To appreciate the aforesaid submission made by the counsel for
the respondent, it is necessary to advert to Section 35 of the FEMA,
which reads as below:
"35. Appeal to High Court - Any person aggrieved by any decision or order of the Appellate Tribunal may file an appeal to the High Court within sixty days from the date of
communication of the decision or order of the Appellate Tribunal to him on any question of law arising out of such order :
Provided that the High Court may, if it is satisfied that the appellant was prevented by sufficient cause from filing the appeal within the said period, allow it to be filed within a further period not exceeding sixty days.
Explanation - In this section "High Court" means-
(a) the High Court within the jurisdiction of which the aggrieved party ordinarily resides or carries on business or personally works for gain; and
(b) where the Central Government is the aggrieved party, the High Court within the jurisdiction of which the respondent, or in a case where there are more than one respondent, any of the respondents, ordinarily resides or carries on business or personally works for gain."
7. As noted above, the Explanation clause of Section 35 of the
FEMA explains the term "High Court" in two contexts. In Explanation
(a), the term "High Court" has been defined as a court where the
aggrieved party ordinarily resides or carries out business or personally
works for gain and Explanation (b) applies where the Central
Government being an aggrieved party, proposes to file an appeal and
in such circumstance, the "High Court" has been defined as one within
whose jurisdiction the respondent or any of the respondents ordinarily
reside or carry out business or personally work for gain. In other
words, both the Explanations work to the benefit of the individual,
whether as the appellant/aggrieved party or as a respondent in a
State appeal.
8. In the present case, the appellant herein is the aggrieved party,
who, as is apparent from a perusal of the memo of parties and the
affidavit filed in support of the appeal, is a permanent resident of
Mumbai. In such a circumstance, Explanation (a) of Section 35 of
FEMA comes into play and there is no manner of doubt that the
appellant ought to have approached the court where he ordinarily
resides to file the present appeal. In view of the above, this Court
cannot be treated as the "appropriate court" within the meaning of the
Explanation to Section 35 of the FEMA for purposes of entertaining the
present appeal.
9. Accordingly, the objection taken by the respondent with regard
to the maintainability of the appeal on the second ground is upheld
and the present appeal is disposed of with liberty granted to the
appellant to approach the appropriate High Court vested with the
territorial jurisdiction, as specified in Section 35 of the FEMA, for filing
an appeal against the impugned order. In view of the fact that the
date of the impugned order is 22.3.2006 and the present appeal came
to be filed within the period of limitation, on 26.2.2007 and after the
pleadings were completed, the same was admitted for final hearing on
25.3.2009 and ever since, it has remained pending, the appellant shall
be at liberty to invoke the provisions of Section 14 of the Limitation
Act for explaining the delay in approaching the said court. Further, in
the interest of justice, it is directed that the interim order dated
30.3.2007, staying the operation of the impugned order, shall continue
to operate in favour of the appellant for a period of six weeks from
today so as to enable him to seek interim relief from the High Court
vested with the territorial jurisdiction to entertain the appeal in
accordance with law.
10. The appeal is disposed of.
HIMA KOHLI, J NOVEMBER 06, 2013 sk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!