Citation : 2013 Latest Caselaw 2563 Del
Judgement Date : 30 May, 2013
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ O.M.P. 822/2011
% Judgment dated May 30, 2013
M/S J.K. SPUN PIPE INDUSTRIES ..... Petitioner
Through : Mr.H.C. Dhall, Adv.
versus
DELHI JAL BOARD & ANR ..... Respondents
Through : Mr.Suresh Tripathy, Adv.
CORAM:
HON'BLE MR. JUSTICE G.S.SISTANI
G.S.SISTANI, J.
1. Present objection petition has been filed by the petitioner under
Section 34 of the Arbitration and Conciliation Act, 1996, seeking to
set aside the Award dated 2.7.2011 passed by the learned
Arbitrator, by which the learned Arbitrator has held that the
respondent no.1 (claimant before the learned Arbitrator) has
overpaid a sum of Rs.23,67,690/- to the petitioner herein. The
learned Arbitrator has also held that the respondent on.1 Board is
entitled to the amount with interest @10%, per annum, on the
amount awarded, besides costs of Rs.95,000/- and the petitioner
would be allowed to take back the stocks of 12,656 meters of pipe
lying with the respondent no.1 Board.
2. The necessary facts, to be noticed for the disposal of the present
objections, are that the petitioner was awarded work of supply of
47,000 meters of AC pressure pipe for a total cost of Rs.39,00,624/-
vide supply order no.33 dated 6.2.1995 and an Agreement in this
regard was also executed between the petitioner and the
respondent no.1 Board incorporating the terms and conditions of the
said agreement. As per the respondent no.1 Board the petitioner
supplied only 44,328 meters of pipe against the above mentioned
supply order. As per the respondent no.1 Board the pipes so
supplied by the petitioner were below the specifications and the
petitioner was asked to replace the pipes immediately vide
communications dated 10.11.1995, 22.11.1995 and 13.12.1995. The
petitioner replaced only 5000 meters of pipe but failed to replace
the remaining pipe lying in the Central Store as well as those laid in
various colonies in Trans Yamuna and Rural North Area.
Subsequently the petitioner replaced 12,624 meters length of pipe
but failed to replace the balance pipes. Respondent no.1 Board had
made the following claims against the petitioner herein before the
learned Arbitrator:
i) Pipes as laid and failed at 30,828 Meters
site:
ii) Pipes lying at Store for 12,656 Meters
Replacement
iii) Pipe Lifted but not 144 Meters
replaced
iv) Length paid by the 42,808 Meters
Respondent claimant
and its cost is: Rs.34,16,078.40
add 7% Sales Tax: Rs.1,36,643.40
Total Rs.35,52,721.54
LESS : 5% Rs.1,77,636.00
Total : Rs.33,75,085.00
3. As per the petition, respondent no.1 Board had also incurred an
amount of Rs.17,05,000/- for laying of the pipes. Besides storage
charges of Rs.21,007/- were also claimed. Respondent no.1 also
forfeited Rs.20,000/-, deposited by the petitioner with respondent
no.1 as earnest money. Respondent no.1 also claimed Rs.3,90,062/-
as the penalty in terms of the Agreement however, a benefit was
given to the petitioner of Rs.1.50 lakhs, which was already with the
respondent no.1 Board. Respondent no.1 also claimed Rs.2,40,062/-
as penalty. And interest @ 20% p.a. has also been claimed.
4. The case of the petitioner, before the learned Arbitrator, was that
the petitioner had supplied 43,328/- meters of pipe, against the
aforementioned supply order which had been duly inspected by
Engineers India Limited, which was one of the main terms and
conditions mentioned in the agreement executed between petitioner
and respondent no.1. The petitioner had also submitted before the
learned Arbitrator that the pipes, as laid and failed at site, were
30,828 meters. Respondent no.1 Board had made vague statements
without giving the exact sites and number of pipes laid down by the
petitioner. It is further the case of the petitioner that in terms of the
communication dated 11.12.1995 only 5,928 meters of pipe was not
as per the standard and in fact respondent no.1 Board was
responsible for laying of pipes as the manner of laying the pipe by
respondent no.1 was defective and, thus, the petitioner cannot be
held liable for the same. It is also the admitted case of the petitioner
before the learned Arbitrator that 17,500 meters of pipe, by way of
replacement, was supplied by the petitioner to respondent no.1 and
on the complaints received from the respondent no.1 Board the
petitioner held meetings with respondent's no.1 engineers and
agreed to replace 5000 meters of pipe as recorded in the
communication dated 17.1.1996. It has also been pleaded by the
petitioner before the learned Arbitrator that the pipes were duly
inspected by the Engineers India Limited and inspection reports
were also issued by Engineers India Limited on 13.3.1995, 27.4.1995
and 11.6.1995, which would show that there was no manufacturing
defect when the goods were supplied to the respondent claimant. It
was also the case of the petitioner before the learned Arbitrator that
there was no need, necessity or requirement for the petitioner to
replace the defective pipes, the petitioner had replaced the
defective pipes only as a matter of goodwill and to maintain
excellent relations with the respondent no.1 Board.
5. It is contended by Mr.Dhall, learned counsel for the petitioner, that
the award rendered by the learned Arbitrator is patently illegal and
is in conflict with the public policy of India. It is next contended that
the learned Arbitrator has not decided the disputes between the
parties in accordance with the agreement signed between the
parties nor the Arbitrator has decided the matter issue-wise based
on the issues which were framed by the learned Arbitrator. Mr.Dhall
has primarily laid stress on the fact that once the pipes were
inspected by the Engineers India Limited and on the basis of which
inspection reports were made and the pipes were certified, no claim
could have been raised by the respondent no.1 against the
petitioner. It has further been strenuously argued by Mr.Dhall that
the learned Arbitrator has failed to take note of the inspection
certificate as also the inspection reports dated 27.4.1995, 11.6.1995
and 13.3.1995 and grievance, if any, would be against Engineers
India Limited and not against the petitioner herein. It is also
submitted that the principle of estoppel as enumerated under the
Indian Evidence Act, 1872 would apply and no claim could have
been made by the respondent no.1 against the petitioner in view of
Section 115 of the Indian Evidence Act, 1872, which reads as under:
"115. Estoppel. - When one person has, by his declaration, act or omission, intentionally caused or permitted another person to believe a thing to be true and to act upon such belief, neither he nor his representative shall be allowed, in any suit or proceeding between himself and such person or his representative, to deny the truth of that thing."
6. In support of his arguments, learned counsel for the petitioner
places reliance on Anantam Veeraju & Ors. vs. Valluri Venkayya @
Venkamma (died) & Anr. reported as AIR 1960 Andhra Pradesh 222.
Relevant paragraph of which is reproduced as under:-
"Where a person obtains a benefit from the other party by a transaction of exchange, he must be taken to have accepted the validity of exchange. He cannot retain the property he got in exchange and at the same time seek to recover what he gave in return. He disables himself from even offering to return what had been obtained in exchange where he has sold them away"
Further reliance is placed on Baidyanath Rai & Anr. v.
Satyanarain Rai & Ors. reported as AIR 1960 Patna 36. Relevant
paragraphs of which is reproduced as under:-
"Here also, the plaintiffs, obtained time to pay the decretal amount on the condition that in the event of their failure to pay the sale would stand good. They defaulted. Having obtained time and prevented the defendants from contesting the validity of their objections, they cannot now, after their default has resulted in the confirmation of the sale, turn round and contest the legality and validity of the sale on the very same grounds on which the sale was impeached in the previous proceeding. In my opinion, the plaintiffs are estopped from questioning the legality of the sale in this case."
Reliance is also placed on Swaminatha Ayyar vs. Saivu
Rowthan & Anr. reported in AIR 1963 Madras 123. Relevant
paragraph of which is reproduced as under:-
"5. A person cannot say at one time that a transaction is invalid and thereby obtain some advantage to which he could only be entitled on the footing that it is invalid and at another time say it is valid for the purpose of defeating another who is entitled to obtain an equal advantage with him on the footing that it is invalid."
7. In my view, the principle of estoppel is not involved in the facts of
this case and therefore the judgments sought to be relied upon by
the counsel for the petitioner are not applicable. As far as the
submission made by learned counsel for the petitioner that no
finding has been given by the learned Arbitrator issue-wise is
concerned, I find no merit in the same. The learned Arbitrator has
observed in the award that although nine issues were framed,
however, during the arguments they were not even referred to and
in fact it was agreed between the parties that the learned Arbitrator
should only deal with the arguments of the parties and the points
raised during arguments. The Arbitrator has categorically mentioned
in the award that it is for this very reason that he proceeded to deal
with the issues and did not deal the issues separately. In view of the
agreement between the parties and the suggestion made by them
before the Arbitrator the objections raised by the petitioner was
liable to be rejected. Even otherwise the learned Arbitrator is not
bound by the strict rules or procedures and it cannot be said that
this award is liable to be set aside on this ground alone.
8. Respondent no.1 had filed its written statement to the claim before
the Arbitrator wherein it was stated that 44,328 meters of pipe was
supplied out of which the payment was made for a length of 42,808
meters of pipe. The pipe failed after laying and commissioned at the
site. The matter was taken up with the petitioner vide letter dated
17.10.1995, by which the petitioner was informed about the failure
of pipes at the site, the petitioner was asked to inspect the site and
report the cause of failure of the pipes. Consequent thereto an
inspection was carried out by the representatives of the petitioner
herein during which few pipes were put to hydraulic test when it was
observed that the pipes started bursting at a very low pressure, and
thus, the pipes supplied were found to be below the specifications.
The petitioner was asked to replace the pipe immediately vide
communication dated 10.11.1995. Respondent no.1 also issued
letters dated 22.11.1995, 11.12.1995, 10.1.1996 and a telegram
dated 18.12.1995 bringing to the notice of the petitioner the sub-
standard pipes which were supplied by petitioner to respondent
no.1. After much persuasion the petitioner agreed to replace the
defective pipes vide their letter dated 17.1.1996. The petitioner
replaced only 5000 meters of pipe but failed to replace the
remaining pipes which were lying in the Central Store as also those
which were laid in various colonies in Trans Yamuna and rural north
areas. A show cause notice was also issued to the petitioner on
3.6.1996, however, the same was replied to by the petitioner
wherein an attempt was made to shift the blame by the petitioner
herein. Some of the pipes lying in the Central Store out of the
replaced lots was also laid and put to commissioning at less than the
pressure as per the agreement but the pipes were found to be
leaking at many places and, thus, the same failed. This test was
carried out in the presence of the parties and a test report dated
11.6.1996 was duly signed by the petitioner and respondent no.1,
which was placed before the learned Arbitrator. The petitioner did
not abide by the terms and conditions and guarantee furnished for
the pipes supplied by them. A notice under Clause 3 was issued to
the petitioner on 8.7.1996, which was not replied to by the
petitioner, however, vide letters dated 21.7.1996 and 26.8.1996 the
petitioner informed respondent no.1 about the various extra
precautions and measures taken by them for manufacturing the
pipes and again requested to allow the petitioner to replace the
defective pipes. Respondent no.1 allowed the petitioner to replace
12,500 meters of pipe. Subsequently the petitioner replaced 12,624
meters of pipe. Since the petitioner failed to replace the defective
pipes in spite of being marked as ISI, a complaint was made to the
Director, ISI, with a request to initiate action against the petitioner.
Again various requests were made and number of letters were
issued by respondent no.1 to the petitioner to replace the balance
defective pipes. Meanwhile ISI took action against the petitioner and
a case was registered against the petitioner based on the complaint
of the respondent.
9. Mr.Tripathi, learned counsel for the respondent, submits that the
objections filed by the petitioner cannot be entertained. The learned
Arbitrator has rendered a reasoned award based on the facts and
the evidence placed on record and the mere fact that the petitioner
replaced some of the defective pipes would amount to admission on
the part of the petitioner. It is further submitted that the objections
are to be considered on the touchstone of the law laid down by the
Supreme Court of India. In support of his arguments learned counsel
for the respondent places reliance on Subhash Aggarwal Agencies
vs. Bhilwara Synthesis Ltd and Ors. reported in (1995) 1 SCC 371:-
"17. The Indian Law is stated by N.D. Basu on Arbitration (Eighth Edition) at para 2228 at pages 835-836. It reads: Whether arbitrators should give reasons for decisions: An award of arbitrators is not a reasoned judicial decision and the arbitrators need not give reasons for their decisions, and even ignore any proposition advanced by the parties. The Court in filing an award wherein the arbitrators have failed to give a decision or any matter, the subject of dispute cannot be deemed to have exercised a jurisdiction not vested in it by law or to have failed to exercise a jurisdiction vested in it by law. An arbitrator is not bound by the technical rules of procedure which the court must follow, nor need record separate findings on the various points on which the parties are at issue or write a reasoned judicial decision, All that he is required to do is to give an intelligible decision which determines the rights of the parties in relation to the subject-matter of the reference. While it is not necessary for an arbitrator to give reasons for his own conclusions or to give separate finding on each and every issue involved in the dispute, every party that appoints an arbitrator has right to expect an intelligible decision which determines the rights of the parties in the various important points which are at issue. Mere omission to give reasons does not vitiate the award. It is not open to the court to speculate where no reasons have been given by the arbitrator as to what impelled him to arrive at a conclusion and to determine whether the conclusion was right or not."
Learned counsel for the respondent also places reliance on the
decision Gyarsi Bai & Ors. vs. Dhansukh Lal & Ors. reported in 1965
(2) SCR 154. Relevant paragraph of which is reproduced as under:-
"To invoke the doctrine of estoppel three conditions must be satisfied : (1) representation by a person to another, (2) the other shall have acted upon the said representation, and (3) such action shall have been detrimental to the interests of the person to whom the representation has been made. In the instant case it may be said that the first two conditions are satisfied : the appellant represented to the respondents that he was liable to render accounts to them in regard to the net proceeds of the mortgaged properties from the date of the plaint to the date of the preliminary decree, and on the said representation the respondents agreed to the
appellant drawing out from the Court about Rs. 35,515 deposited by them. But can it be said that the respondents had in any way acted to their detriment on the basis of the representation made by the appellant? The respondents had to pay the decretal amount to the appellant if they wanted to get possession of the properties. What they paid was less than what they had to pay under the decree. By paying the said amount they did nothing more than discharging their liability under the decree. The discharge by the respondents of their legal liability under the decree cannot in any sense of the term be described as detrimental to them."
10. I have heard learned counsel for the parties, considered their rival
contentions and also perused the Award dated 2.7.2011 rendered by
the learned Arbitrator. While hearing the objections the Court must
not sit as a court of appeal over the award by reassessing and re-
appreciating the evidence. The Award can only be challenged by the
petitioner under the grounds mentioned in Section 34(2) of the
Arbitration and Conciliation Act, 1996 under which no ground had
been raised by the petitioner herein. Learned Arbitrator has noticed
that most of the arguments advanced centered around the question
as to whether or not the supplies made by the petitioner herein were
defective or not. The learned Arbitrator has further noticed that the
contracted quantity of pipes to be supplied was 47000 meters
whereas only 44,328 meters of pipe had been supplied by the
petitioner to the respondent no.1 upto 13.7.1995, out of which
31,528 meters of pipe had been actually laid, as per the following
details, and thus a balance of 12,656 meters of pipe was lying in the
Stores of respondent no.1:
Shahdara I - 14696 meters
Shahdara II - 11556 meters
North Area - 3688 meters
Rural North Area - 1588 meters
Zone
11. The learned Arbitrator has also noticed that the petitioner did not
replace 144 meters of pipe, although the same had been lifted by
them to arrive at a decision that the pipes supplied were defective.
Learned Arbitrator has also placed reliance on the communication
dated 17.10.1995 addressed by the respondent to the petitioner,
wherein it was pointed out that pipes have been used at sites
located in Delhi. Complaints have been received for developing of
cracks in the defective pipes at much lower water pressure than the
designed pressure of 15 kg/cm. The petitioner was requested to
inspect the site and report the cause of failure. The learned
Arbitrator goes on to notice that consequent upon the complaint an
inspection was carried out by the representatives of the respondent
no. 1 during which when few pipes were put to hydraulic test they
started bursting at a very low pressure. This fact was evident from
the letter dated 10.11.1995 addressed by the respondent to the
petitioner herein. The petitioner was also informed that the supply
made by them was below the specifications and the petitioner was
asked to replace the same. Since no steps were taken by the
petitioner herein to replace the defective pipes, respondent no.1
complained to the petitioner that the petitioner had taken no action
for replacing the pipe and threatened to take action against the
petitioner. Respondent no.1 also issued a telegram dated
18.12.1995 to the petitioner complaining that the pipes had failed at
many places. The learned Arbitrator has noticed the letters filed by
respondent no.1 dated 22.11.1995 and 11.12.1995, by which
respondent no.1 complained a lot of problems of bursting of pipes
and called upon the petitioner to replace the same. The learned
Arbitrator further goes on to state that a meeting took place
between the petitioner and respondent no.1 on 16.1.1996 as
reference of the meeting was made in the petitioner's letter dated
17.1.1996. This letter would show that although the petitioner did
make an effort to shift the blame regarding laying of pipes and
manner of stacking the pipes, however, the petitioner acknowledged
that they would replace all the pipes at the site and also lying stores
at Okhla. Although despite the meeting and the acknowledgement
the petitioner took no action in the matter, which was apparent to
the learned Arbitrator by the letter of the respondent written in the
month of May, 1996. Respondent no.1 agitated that despite
numerous complaints from time to time and meeting between the
petitioner and respondent no.1 and replacement being assured by
petitioner to respondent no.1 no action had been taken by
petitioner. A notice was also issued to the petitioner under Clause 2
of the Agreement. This notice also mentioned bursting of pipes,
meetings held on 16.11.1996 and 21.5.1996 and the fact that
representatives of the petitioner had agreed to replace the defective
pipes found at the site as well as from the Central Store. Learned
Arbitrator has also taken note of the fact that in response to the
notice the petitioner admitted having agreed to replace the pipes.
Thereafter a joint inspection was also held on 11.6.1996, when 120
meters of pipes were taken from the Central Store and 80 meters,
out of the 120 meters, were laid. It was also observed that the
pipeline which had been laid was leaking at seven places. As per the
calculation and admittedly by June, 1995, a total of 44,328 meters of
pipe had been supplied by the petitioner to respondent no.1 and in
between 19.2.1996 and 27.2.1996 the petitioner herein had taken
back 4876 meters of pipe and by 13.7.1995 the petitioner had
replaced in all 17,500 meters of pipe leaving a balance of 26,828
meters out of a total of 44,328 meters. This finding was recorded by
the learned Arbitrator based on the acknowledgement of the
respondent in its letter dated 30.12.1996. A final show cause notice
was issued by respondent no.1 to the petitioner on 8.7.1996,
pointing out that the supplies were defective and reminded the
petitioner about the meetings held on 16.1.1996 and 21.5.1996,
according to which the petitioner had agreed to replace the pipes at
site as well as from the Central Store. The notice also mentioned
about the replacement of approximately 5,000 meters of pipe.
Respondent no.1 went on to complaint that despite ample
opportunities having been granted to the petitioner and repeated
assurances by the petitioner, defective pipes have not been
replaced by petitioner. It was also brought to the notice that the
replaced pipes were found leaking at joint inspection.
12. I find that the Arbitrator has also taken into account the fact that
respondent no.1 filed a complaint with the Indian Standard Institute
with regard to defective and sub-standard material supplied by the
petitioner to respondent no.1, the fact that after the complaint the
petitioner agreed for replacement of the defective pipes and by a
communication dated 16.9.1997 petitioner assured the respondent
that "they would be very keen to replace the pipes as mutually
agreed upon". On scrutiny of the documents the learned Arbitrator
has also recorded a finding that in all 17,500 meters of pipe was
replaced; 12,565 meters of pipe was still lying with the respondent
no. 1 in their stores, which was yet to be replaced; besides 144
meters though lifted by the petitioner had not been replaced thus
making a total of 12800 meters. The detailed reasoning of the
learned Arbitrator in coming to the conclusion with regard to pipes
which were supplied, found defective, lying with the claimant in its
stores, requires no interference. The Arbitrator has also rightly
rejected the claim of the respondent in the sum of Rs.17,05,000/- for
the amount incurred in laying of pipes. The Arbitrator has further
rightly rejected the claim of the Board for storage charges. The
Arbitrator has also rejected the claim made by the respondent
towards penalty on account of breach of contract and rightly as
there is no provision in the agreement for any such penalty.
13. As far as the submission made by Mr.Dhall that the learned
Arbitrator has failed to decide the counter claim raised by the
petitioner herein is concerned, the same is factually incorrect as the
learned Arbitrator at page 13 of the Award has dealt with the same.
The petitioner had claimed a sum of Rs.4,63,098/- as balance
amount due from respondent no.1 along with interest @24% per
annum, besides Rs.93,600 towards transfer charges for taking back
the pipes from Delhi to Nanded; Rs.4,21,600/- for delivering 12,500
meters of pipe from Nanded to Delhi and carrying back the same
quantity from Delhi to Nanded, besides Rs.17,500/- towards testing
charges; Rs.65,000/- towards boarding and lodging expenses; and
Rs.1.50 lakhs already deposited with the respondent no 1. The
learned Arbitrator has rightly rejected the claim of the petitioner in
view of the fact that the respondent no. 1 made a payment for
42,808 meters of pipe and also for the reason that baring 12,624
meters of pipe rest of the pipe supplied by the petitioner was not
only rejected but the petitioner agreed to take it back and replace
the same, which replacement has never took place and for this
ground the petitioner cannot be held entitled for the balance amount
nor interest. The Arbitrator also rightly rejected the claim for
transport charges as the pipes had to be transported only because
they were defective and for which the respondent cannot be held
liable.
14. In my view the submissions made by learned counsel for the
petitioner, based on 115 of the Indian Evidence Act, 1872 are of no
use as Section 115 of the Evidence Act is not applicable to the facts
of the present case as no estoppel is involved in the facts of this
case. It is the petitioner who had agreed to replace the defective
pipes, which is a facet admission on the part of the petitioner with
regard to poor quality of pipes supplied. Merely because the pipes
were tested by Engineers India Limited cannot be a ground in itself
to accept the pipes which were defective. Joint inspections have
revealed that the pipes burst even at a pressure, which was lower
than the pressure as per the stipulation. In case the pipes were not
defective the petitioner would never have agreed to replace the
same and would have contested the matter.
15. Having regard to the reasoning given by the learned Arbitrator and
the settled position of Law, I find the present objections without any
merit and the same are accordingly dismissed.
(G.S.SISTANI) JUDGE MAY 30, 2013 msr//dk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!