Friday, 01, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Suresh Khanna vs O.P. Suri Memorial Educational ...
2013 Latest Caselaw 2015 Del

Citation : 2013 Latest Caselaw 2015 Del
Judgement Date : 2 May, 2013

Delhi High Court
Suresh Khanna vs O.P. Suri Memorial Educational ... on 2 May, 2013
Author: Manmohan Singh
*       IN THE HIGH COURT OF DELHI AT NEW DELHI

%                                      Judgment delivered on: May 02, 2013

+                              Arb.P.No.10/2013

        SURESH KHANNA                                       ..... Petitioner
                    Through             Mr.Bhupesh Narula, Adv.

                           versus

        O.P. SURI MEMORIAL EDUCATIONAL SOCIETY (REDG)
                                                    ..... Respondent
                      Through  Mr.Praveen Mahajan, Adv. with
                               Mr.Shrey Raj Saxena, Adv.

        CORAM:
        HON'BLE MR. JUSTICE MANMOHAN SINGH

MANMOHAN SINGH, J. (Oral)

1. The present petition has been filed by the petitioner, Suresh Khanna against the respondent, O.P.Suri Memorial Education Society (Regd.) only on five grounds. The same are reproduced here below:-

"A. That parties have entered into an Agreement for construction of additional floors in the school, original agreement of which was being kept with school.

B. That vide letter dt. 21.03.2010 work was accepted to be carried out as per the terms and condition of the Agreement between the parties. The applicant has carried out and the completed the work and has raised the final bill vide letter dt. 5th March, 2012 but the respondent has failed to clear the dues of the applicant.

C. That vide letter dt. May, 2012, the applicant has demanded the Value added Tax (VAT), Income Tax, Service Tax etc. which are to be paid by the respondent but they failed to do so.

D. That vide letter dated 12.6.2012 as the respondent has failed to make the payment as demanded by the applicant, certified copy of the Agreement which is with the Respondent and the said clause includes following clause which reduced as under:-

"That in case of dispute between the parties, both the parties shall appoint if other fails to appoint their nominee arbitrator after intimations from other party in next 45 days, the arbitrator appointed by one party shall be a Sole Arbitrator in between the disputes of the parties, the Arbitrations and Conciliation Act, 1996 would apply in the matter."

E. That the respondent has failed to make the payment and vide letter dt. 23.6.2012, applicant had appointed Sh.V.D.Tiwari as an arbitrator who is retired Chief Engineer of CPWD. Respondent has failed to appoint the arbitrator, hence present application has been filed."

2. Along with the petition, the petitioner has filed letters dated 21 st March, 2010, 9th May, 2012, 12th June, 2012 and 23rd June, 2012. In the letter dated 9th May, 2012 written by the petitioner to the respondent in furtherance of the letter dated 5th March, 2012 requesting the respondent for balance payable amount of `1,23,15,480/- to be released by the respondent as per agreement. It was also informed to the respondent that the said dues should be paid on or before 20th May, 2012 failing which the petitioner would nominate an Arbitrator who is a Retired Chief Engineer of Government Department at the risk and cost of the respondent. In the letter dated 12th June, 2012, again the request was made by the petitioner to the respodnent to release the amount due and also invoke clause of the appointment of Arbitrator and also asked the respondent to supply the copy of the agreement. In the letter dated 23rd June, 2012 it was reiterated that the said amount has not been released by the respondent.

3. Learned counsel for the respondent has argued that the present petition is not maintainable, as there is no contract of arbitration between the parties. It is further stated by the counsel that the agreement dated 20 th March, 2010 was entered into between the parties for the purpose of carrying on construction at the site. However, in the said agreement, nowhere it provides for arbitration clause for adjudication of the disputes between the parties. Thus, the petitioner has initiated the proceedings in order to harass the respondent. Copy of the agreement dated 20 th March, 2010 entered into between the parties is enclosed with the reply as Annexure-1 which does not contain Arbitration Clause.

4. Learned counsel for the petitioner states that the petitioner had some correspondence and relevant pages of agreement and his client would try to locate the same. The petitioner is also unable to explain to the Court that if the petitioner did not have copy of agreement which has an arbitration clause in para D of the petition from where the petitioner has extracted the Arbitration Clause as mentioned.

5. The petition itself lacks of details, thus, the prayer sought in the petition cannot be allowed. The petition is, therefore, dismissed. However, the petitioner is granted liberty to file the fresh petition as and when the petitioner is able to trace out the documents including the agreement or any communication exchanged between the parties which contain the reference of dispute adjudicate between the parties. The contention of the petitioner would be considered as per its own merit.

(MANMOHAN SINGH) JUDGE MAY 02, 2013

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter