Citation : 2013 Latest Caselaw 1170 Del
Judgement Date : 8 March, 2013
*IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of decision: 8th March, 2013
+ EFA(OS) 34/2012
HOUSING & URBAN DEVELOPMENT
CORPORATION LTD. ..... Appellant
Through: Mr. Harish Malhotra, Sr. Adv. & Mr.
Rajeeve Mehra, ASG with Mr. Sanjay
Kumar & Ms. Mehak Nakra, Advs.
Versus
LEELA HOTELS LIMITED ..... Respondent
Through: Mr. Rajiv Nayyar, Sr. Adv. with Mr.
Abhimanyu Mahajan, Adv.
CORAM:-
HON'BLE THE CHIEF JUSTICE
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
RAJIV SAHAI ENDLAW, J
1. The appellant impugns the order dated 06.09.2012 of the learned
Single Judge in the course of execution of an arbitral Award dated
25.06.2002 having force of a decree under Section 36 of the Arbitration &
Conciliation Act, 1996 (Arbitration Act).
2. The arbitral Award dated 25.06.2002, insofar as relevant for the
present purposes, awarded interest to the respondent / decree holder against
the appellant / judgment debtor on the amounts awarded, at the rate of 20%
per annum pre-arbitration and pendente lite and at the rate of 15% per
annum from the date of the Award till the date of recovery.
3. OMP No.308/2002 under Section 34 of the Arbitration Act preferred
by the appellant / judgment debtor impugning the said Award was dismissed
on 20.01.2003.
4. FAO(OS) No.59/2003 preferred by the appellant / judgment debtor
thereagainst was also dismissed on 09.11.2004.
5. Civil Appeal No.1094/2006 arising out of SLP(Civil) 3777/2005
preferred by the appellant/judgment debtor was also dismissed on
12.02.2008. However, the Supreme Court reduced the rate of interest
awarded by the Arbitrator for the pre-award period from 20% to 18%.
6. The respondent / decree holder then applied for execution of the
Award. During the execution proceedings a question arose whether the
amounts deposited by the appellant / judgment debtor in terms of interim
orders during the proceedings aforesaid, are to be appropriated first towards
interest or principal. Order dated 19.11.2008 of the executing Court in this
regard was challenged in EFA(OS) No.4/2009 and the order dated
20.07.2009 of the Division Bench in the said appeal became the subject
matter of Civil Appeal No.9763/2011 (arising out of SLP (Civil)
18509/2009) disposed of by the Supreme Court on 15.11.2011. Need is
however not felt to discuss in detail the controversy in the said proceedings,
the same having been succinctly set out in the impugned order of the learned
Single Judge and the same having not much relevance to the issue in hand.
7. Thereafter a dispute arose as to whether the interest awarded of 15%
per anuum from the date of the Award to the date of the recovery, was to be
on the principal amount awarded only or also on interest awarded (as
reduced by the Supreme Court) for the pre- arbitration period and pendente
lite the arbitration proceedings. EA No.696/2011 was filed by the
respondent / decree holder giving the calculation of the amount of
Rs.1,54,40,86,168/- due till then.
8. An affidavit in opposition was filed by the appellant / judgment debtor
thereto, claiming that only a sum of Rs.1,46,76,45,561/- was due under the
Award and which had already been paid. The difference in the two
calculations was on account of the fact that while the respondent / decree
holder was claiming post award interest at 15% per annum besides on the
principal amount, also on the amount due towards pre-award interest and the
appellant/ judgment debtor was calculating the same only on the principal
amount awarded and not on the amount towards pre-award interest.
9. The learned Single Judge in paras No.10 to 12 of the impugned order
has noticed that though in the earlier round of appeal during the execution
proceedings, the appellant / judgment debtor had before the Supreme Court
raised the said issue but the Supreme Court did not pronounce of the said
submission.
10. The learned Single Judge further held the judgment of the Supreme
Court in State of Haryana Vs. S.L. Arora & Company 2010 (3) SCC 690,
relied upon by the appellant/judgment debtor, to be not applicable in view of
the Award in the present case providing for post-award interest also on the
amount due towards pre-award interest and the said part of the Award
having not been interfered with, neither by the Single Judge nor by the
Division Bench nor by the Supreme Court and for the reason of award of
such post-award interest on pre-award interest amount, not amounting to
compound interest.
11. The senior counsel for the appellant / judgment debtor has invited our
attention to paras No.22 to 24 of the judgment dated 15.11.2011 of the
Supreme Court in the appeal aforesaid in the earlier round of litigation
arising from the execution proceedings, where it is noted that the issue
relating to charging of compound interest did not survive since the parties
had agreed that no compound interest would be payable in terms of the
Award and that only simple interest was to be paid and he has on the basis
thereof contended that the respondent / decree holder could not claim post-
award interest on the pre-award interest amount, and which would amount
to, compound interest. He has thus argued, that the learned Single Judge, in
the impugned order, has erred in observing that there is nothing to show any
agreement between the parties that no compound interest is payable in terms
of the Award. Reliance is again placed on para No.18 of S.L. Arora &
Company supra, laying down that Section 31(7) of the Arbitration Act
makes no reference to payment of compound interest or payment of interest
upon interest nor does it require the interest, which accrues till the date of
the Award, to be treated as part of the principal, from the date of Award for
calculating the post Award interest and that the arbitral Tribunals do not
have the power to award interest upon interest, or compound interest, either
for the pre-award period or for the post-award period.
12. Per contra, the senior counsel for the respondent / decree holder has
invited our attention to para No.21.9(e) of the arbitral Award in the present
case, where the appellant / judgment debtor has been held liable to pay to the
respondent / decree holder interest at 20% per annum on the monies
(including interest) awarded to the respondent / decree holder by the Award,
from the date of the Award to the date of recovery, and has argued that even
though in the operative para of the Award, future interest has been restricted
to 15% per annum only from the date of the Award to the date of recovery,
but it will be not only be on the principal amount but also on the pre-arbitral
proceedings and pendente lite arbitration proceedings interest amount also,
in terms of the said paragraph of the Award and this part has not been
interfered with in the challenge proceedings to the Award. He has further
invited our attention to para No.13 of the judgment dated 15.11.2011 supra
of the Supreme Court to show, that the compound interest qua which the
agreement between the parties is recorded in the said judgment, was qua the
claim earlier being made by the respondent /decree holder for interest with
yearly rests and has argued that it was the said claim only which was not
pressed by the respondent / decree holder and not the claim for post-award
interest on pre-award interest amount.
13. We have weighed the rival contentions. The operative part of the
Award awards future interest at 15% per annum from the date of the Award
to the date of recovery, without specifying whether the said interest is to be
also on pre-award interest amount also or not. Of course, in the substantive
part of the Award, in para No.29.1 (e) supra, while awarding future interest,
it was specified that the future interest would also be on the monies due
under the Award including towards interest. Though there is inconsistency
in the rate of future interest specified in the substantive part of the Award
and in the operative part of the Award but there is no dispute that the rate of
interest specified only in the operative part of the Award will apply and in
our view the said inconsistency does not affect the award of future interest
on interest due till the date of the Award also.
14. It is also very clear from the judgments of the Single Bench and
Division Bench of this Court in challenge proceedings to the Award that the
appellant/judgment debtors did not challenge the Award to the extent
awarding post-award interest on the pre-award interest amount also. No such
objection is shown to have been taken before the Supreme Court also in the
challenge proceedings.
15. Though the appellant/judgment debtor, when approached the Supreme
Court in SLP/Appeal from order in execution proceedings, challenged award
of post-award interest on pre-award interest amount also, but the Supreme
Court did not pronounce on the same and the necessary corollary is that the
said objection was not accepted by the Supreme Court.
16. We however do not find any merit in the contention of the
appellant/judgment debtor that the respondent/decree holder, in the aforesaid
round before the Supreme Court, agreed not to claim post-award interest on
pre-award interest amount. The agreement between the parties, recorded in
order dated 15.11.2011 supra, of the Supreme Court is found to be only in
respect of the claim then being made by the respondent/decree holder of
interest with yearly rests and it was only such claim which was given up by
the respondent/decree holder.
17. What follows in the aforesaid light is that the award of the post-award
interest (at such rate as modified by the Supreme Court) not only on the
principal amount but also on the pre-award interest amount has attained
finality. The question which arises is, whether in execution, the said Award,
which under Section 36 supra has to be enforced in the same manner as if it
were a decree of the Court, can be interfered with.
18. The settled principle of law is that the executing Court cannot go
behind the decree. Reference if any required in this regard can be made to
the five Judge judgment in Gurpreet Singh Vs.Union of India (UOI) (2006)
8 SCC 457, Food Coporation of India Vs. S. N. Nagarkar (2002) 2 SCC
475, Deepa Bhargava Vs. Mahesh Bhargava (2009) 2 SCC 294, Coal
Linker Vs. Coal India Ltd. (2009) 9 SCC 491 and Morepen Laboratories
Ltd. and Ors. Vs. Morgan Securities and Credits Pvt. Ltd.
MANU/DE/1110/2008
19. Before coming to the dicta of the Supreme Court in S. L. Arora &
Company we may notice that the consistent view of this Court has been that
future interest on the interest till the date of the decree or Award is
permissible. Reference in this regard may be made to Saraswati
Construction Co. Vs. Delhi Development Authority AIR 2004 Delhi 412
where, relying on Oil and Natural Gas Commission Vs. M. C. Clelland
Engineers, S.A (1999) 4 SCC 327, it was held that the pre-suit and
pendente lite interest crystallizes into the decretal amount and the future
interest becomes payable on the entire amount comprised of the claims, as
well as the pre-suit and pendente lite interest and interest from the date of
the passing of the decree is not to be calculated merely on the amount of
claims upheld by the Arbitrator / Court but also on amount of interests
awarded by the Arbitrator or the Court.
20. On an appeal against the aforesaid, the Division Bench in Delhi
Development Authority Vs. Saraswati Construction Co. 114 (2004) DLT
385 held that interest awarded in lieu of compensation or damages becomes
principal amount for which a party would be entitled for interest on account
of it being withheld by the opposite party.
21. A constitution Bench of the Supreme Court in Central Bank of India
Vs. Ravindra 2002 (1) SCC 367 upheld compound interest though in the
context of Banking business.
22. Mention may however be made of dicta of a subsequent Division
Bench of this Court in Pt. Munshi Ram and Associates (P) Ltd. Vs. Delhi
Development Authority MANU/DE/2115/2010, where, relying on S.L.
Arora & Company supra, Saraswati Construction Co. was held to be not
good law. However, the Division Bench in this case was answering a
reference and the question, whether the award, in execution could be
interfered with, did not arise.
23. That brings us to S. L. Arora & Company; the Supreme Court in the
said judgment was concerned with the interpretation of Section 31 (7) of the
Arbitration Act and while doing so held that Section 31(7) makes no
reference to payment of compound interest or payment of interest upon
interest and does not require the interest which accrues till the date of
Award, to be treated as part of the principal from the date of Award for
calculating post-award interest. It was further held that in the absence of any
provision for interest upon interest in the contract, Arbitral Tribunals do not
have the power to award interest upon interest or compound interest either
from the pre-award period or from the post-award period.
24. We have considered, whether a distinction can be carved out from S.
L. Arora & Company, for the reason of the question in the present case
having arisen in execution and the Award having attained finality. However,
what we find is that S. L. Arora & Company also was a case of execution
only and though this aspect of the arbitral Award in that case also having
attained finality was not addressed or adjudicated but the Supreme Court
nevertheless interfered with the Award of post-award interest on pre-award
interest amount also, even at stage of execution.
25. We are however of the opinion that in the face of the established
proposition aforesaid noticed, of it being impermissible to in execution go
behind the decree and on which aspect S.L. Arora & Company is quiet, S.L.
Arora & Company cannot be said to be a judgment allowing going behind
the decree in an execution. The Supreme Court in a catena of decisions has
held that a decision is an authority for what it decides and not for what can
logically be deduced therefrom. (See Bhavnagar University v. Palitana
Sugar Mill Pvt. Ltd (2003) 2 SCC 111, Bharat Forge Co. Ltd. v. Uttam
Manohar Nakate (2005) 2 SCC 489 and Inderpreet Singh Kahlon v. State
of Punjab AIR 2006 SC 2571). Lord Halsbury in Quinn v. Leathem [1901]
A.C. 495 said, "...The other is that a case is only an authority for what it
actually decides. I entirely deny that it can be quoted for a proposition that
may seem to follow logically from it. Such a mode of reasoning assumes that
the law is necessarily a logical code, whereas every lawyer must
acknowledge that the law is not always logical at all...". The Supreme
Court in Bharat Petroleum Corporation Ltd. Vs. N.R. Vairamani (2004) 8
SCC 579 cited Lord Denning with approval opining that each case depends
on its own facts and a close similarity between one case and another is not
enough because even a single significant detail may alter the entire aspect. It
was further held that the temptation to decide cases by matching the colour
of one case against the colour of another is to be avoided.
26. We may also notice that the judgment in S.L. Arora & Company has
vide order in Hyder Consulting (Uk) Ltd. Vs. Governor State of Orissa Tr.
Chief Eng. MANU/SC/0288/2012 been referred to a larger bench.
27. Thus, though we are bound by S.L. Arora & Company but since in the
facts of the present case, where the Award expressly grants post-award
interest on pre-award interest amount also and where the appellant/judgment
debtor in the proceedings challenging the Award failed to challenge the
Award on the said ground and the Award has thus become final and has the
effect of a decree, it is not open to the appellant/judgment debtor to at the
stage of execution proceedings challenge the Award on the said ground.
Such challenge if entertained by us, would amount to going behind the
decree and which is impermissible. In Morepen Laboratories Ltd. supra,
also the Division Bench of this Court was concerned with challenge to the
rate of interest awarded at the stage of execution and held the same to be
impermissible.
28. For the aforesaid reasons, we hold the appellant/judgment debtor to be
bound by the Award of post-award interest on the pre-award interest amount
also, notwithstanding the dicta in S.L. Arora & Company.
29. We therefore do not find any merit in this appeal and dismiss the
same. However, in the legal scenario aforesaid, no costs.
RAJIV SAHAI ENDLAW, J
CHIEF JUSTICE
MARCH 8th, 2013 'gsr'..
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!