Citation : 2013 Latest Caselaw 2898 Del
Judgement Date : 10 July, 2013
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of decision: 10th July, 2013.
+ CS(OS) 1100/2005
M/S ENTREPRENEURS CO-OP GROUP
HOUSING SOCIETY LTD. ..... Plaintiff
Through: Mr. Kawal Nain, Ms. Kavita Batra and
Ms. Bhavya Nain, Advocates.
Versus
M/S SCHINDLER INDIA PVT. LTD. ..... Defendant
Through: Mr. Babit Singh Jamwal and Mr.
Puneet Singh Bindra, Advocate.
CORAM:
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
JUDGMENT
% 10.07.2013
1. The plaintiff has sued for recovery of principal sum of Rs.19 lakhs
together with interest @ 24% per annum till the date of institution of the suit
of Rs.9,05,753.43 paise, i.e. total Rs.28,05,753.43 paise pleading:
(i) that the plaintiff, a Co-operative Group Housing Society had
entered into the Agreement dated 6th December, 1999 with the
defendant whereunder the defendant undertook to supply, install and
commission fourteen Schindler smart machine room less TM 001
lifts/elevators @ Rs.9,30,000/- per lift for a total price of
Rs.1,30,20,000/- at the flats to be constructed for the members of the
plaintiff Society at Plot No.9, Sector-22, Dwarka, Phase-I, New Delhi;
(ii) that the aforesaid sum of Rs.19 lakhs was paid as advance by the
plaintiff to the defendant under the said Agreement;
(iii) that the plaintiff vide letters dated 1 st May, 2003 and 27th May,
2003 asked the defendant to supply the lifts;
(iv) that the defendant vide letter dated 30th July, 2003 notified the
plaintiff that the validity of the contract had expired and the price of
the lifts had escalated since December, 1999 and it was not possible
for the defendant to execute the contract at the agreed prices and
further notified the plaintiff that the revised price of the lifts was to be
Rs.10,79,000/- per lift;
(v) that the aforesaid revised price was not acceptable to the
plaintiff and the plaintiff thus asked for refund of the advance which
the defendant failed to refund inspite of legal notice;
Hence this suit. The plaintiff has also claimed interest @ 24%
per annum from the date of institution of suit.
2. The defendant has contested the suit pleading:
(a) that though as per the Agreement, the entire sum of Rs.19 lakhs
was payable by the plaintiff to the defendant by 31st December, 1999
but the plaintiff paid only the first installment of Rs.10 lakhs and paid
the balance amount of Rs.9 lakhs on or about 14 th March, 2000;
(b) that the suit for recovery of the said amount of Rs.19 lakhs thus
should have been filed by 14 th March, 2003 and at the time of
institution on 23rd July, 2005 the claim therefor was barred by time;
(c) that the sum of Rs.19 lakhs was paid under the Agreement dated
6th December, 1999 by way of earnest money which acted as a
commitment on the part of the plaintiff that the plaintiff would honor
its obligations under the Agreement failing which the defendant would
incur losses; that the defendant on the basis of representations of the
plaintiff had to undertake initial preliminary work so as to be ready
and prepared to supply elevators of the specifications as per
Agreement when intimated by the plaintiff;
(d) no refund of the said sum of Rs.19 lakhs was envisaged under
the Agreement and on the contrary the Agreement provided for
forfeiture of earnest money by the defendant in the event of default by
the plaintiff;
(e) that the plaintiff after inducing the defendant to commit the
performance of the Agreement has failed to adhere to the terms
thereof;
(f) that the plaintiff failed to place any instructions for installation
of the elevators during the validity of the Agreement for a period of
three years;
(g) that an Agreement containing reciprocal promises must be
fulfilled by both parties to the Agreement and any party failing to
perform its part of the obligations mandated under the Agreement
cannot seek any remedy against the other;
(h) that the instructions for installation of the elevators were to be
tendered within a reasonable time before expiry of the Agreement; the
prices of the elevators were kept immune from escalation until 31 st
December, 2002 and the defendant subjected itself to considerable risk
and losses by agreeing to a check on price escalation for nearly three
years; the plaintiff however failed to instruct the defendant to install
any elevators;
(i) that the plaintiff has concealed that though it had in the year
1999 entered into an agreement for installation of 14 elevators at an
agreed price of Rs.9,30,000/- per elevator; the Agreement clearly
provided that the only situation warranting a refund was if the
defendant were to fail to deliver the elevators within six months from
the date of written intimation by the plaintiff or an intervening force
majeure event; the plaintiff however, did not place any intimation for
installation of elevators under the Agreement for more than four years;
the plaintiff wrote a letter dated 14 th March, 2000 requesting for
extension since the blocks (where the elevators were to be installed)
were not ready for installation of elevators; the defendant agreed to
extend the validity of the Agreement upto 14 th March, 2003; the date
earlier agreed of 31st December, 2002 was however kept unaltered; in
or about April, 2000, the defendant reminded the plaintiff of its
commitment; in response thereto the plaintiff vide its letter dated 12th
April, 2000 informed that they would be constructing a basement and
therefore four elevators were to be respecified for one more stop at the
basement; the plaintiff further informed that instead of 14 elevators as
initially agreed, only 12 elevators would need to be installed; the
defendant vide its letters dated 24th April, 2000 and 9th March, 2001
informed the plaintiff of the consequent increase in price;
(j) that the defendant again vide its letter dated 29th July, 2002 drew
the attention of the plaintiff that the price agreed was valid till 31 st
December, 2002 only; the plaintiff neither replied to the said letter nor
placed any order and ultimately instructed installation vide its letters
dated 1st May, 2003 and 27th May, 2003 which were beyond the
validity of the Agreement which had expired on 14 th March, 2003; the
defendant vide its letter dated 30 th July, 2003 so informed the plaintiff
and intimated the revised cost of Rs.10,79,000/- per elevator;
(k) that the defendant vide its letter dated 16 th March, 2004 again
called upon the plaintiff to renew/revalidate the expired Agreement
since the material for installation and commissioning of elevators was
ready for delivery and the defendant was incurring costs towards
warehousing and other expenses;
(l) that a reply dated 26 th October, 2004 was also given to the legal
notice;
The defendant has also controverted the authority of the person
instituting the suit, signing and verifying the plaint on behalf of the
plaintiff.
3. No replication was filed.
4. On the pleadings of the parties, the following issues were framed on
26th September, 2006:
"1. Whether the suit is filed by a duly authorized person? OPP
2. Whether the plaintiff is entitled to the suit amount? OPP
3. Whether the plaintiff is entitled to interest, if so, at what rate and from what date? OPP
4. Whether the plaintiff has not adhered to the terms of the agreement? OPD"
5. The plaintiff examined two witnesses and closed its evidence. The
defendant has examined one witness and closed its evidence. No evidence in
rebuttal was led by the plaintiff.
6. The counsels for the parties have been heard.
7. My issue-wise findings are as under:
8. Re: Issue No.1. Whether the suit is filed by a duly authorized person? OPP
8.1. The suit has been instituted and the plaint signed and verified on
behalf of the plaintiff by Mr. Ashok Kumar Ralhan claiming to be the
President of the plaintiff‟s Society. The certificate issued by the office of the
Registrar, Co-operative Societies, Delhi Administration, New Delhi of
registration of the plaintiff as a Society under the Delhi Co-operative
Societies Act, 1972 has been proved as Ex.PW1/2. Mr. Ashok Kumar Ralhan
appearing as PW1 in his affidavit Ex.PW1/A by way of examination-in-chief
has deposed that he was vide resolution of the members of the Managing
Committee of the plaintiff Society in the meeting held on 23rd July, 2005 and
extract whereof is proved as PW1/1 authorized to file, sign and verify and
institute the present suit. PW2 Mr. Krishan Kumar Bhalla in his affidavit
PW2/A by way of examination-in-chief has deposed that he is the Vice-
President of the plaintiff Society and has also proved the resolution dated
23rd July, 2005 Ex.PW1/1 authorizing Mr. Ashok Kumar Ralhan. PW1 in his
cross-examination on 29th January, 2009 has deposed that he was appointed
as the President from the year 2002 till 2006 and after about one and a half
year again became the President. PW2 was not cross-examined at all on the
aspect of authority of Mr. Ashok Kumar Ralhan to institute the suit. The
plaintiff besides placing the extract of the resolution dated 23 rd July, 2005
authorizing Mr. Ashok Kumar Ralhan to institute the suit has also placed on
record the original minute book of the meetings of the Managing Committee
of the plaintiff‟s Society.
8.2. As would be apparent from the above, the defendant has failed to
cross-examine the witnesses of the plaintiff who have deposed about the
authority of Mr. Ashok Kumar Ralhan to institute the suit and sign and verify
the plaint on behalf of the plaintiff. There is no challenge to the signatory of
the plaint being President of the plaintiff Society also; he, for this reason
also, would be competent to institute the suit and sign and verify the plaint
on behalf of the plaintiff which is a juristic person.
8.3. Even otherwise it may be mentioned that the deficiency if any in
authority for institution of the suit, as held in Uday Shankar Triyar Vs. Ram
Kalewar Prasad Singh (2006) 1 SCC 75, Vidyawati Gupta Vs. Bhakti Hari
Nayak (2006) 2 SCC 777 and Grafitek International Vs. K.K. Kaura 96
(2002) DLT 835 are not to be fatal to the suits. The present suit is being
pursued in the name of the plaintiff Society and the recovery of monies in the
event of success, would also be in favour of the plaintiff Society and the
money would go to the plaintiff Society only.
8.4. I accordingly decide Issue No.1 in favour of the plaintiff and against
the defendant.
9. Re: Issue No.2. Whether the plaintiff is entitled to the suit amount? OPP
9.1. Before discussing the respective contentions of the parties aforesaid, it
is expedient to analyze the Agreement dated 6 th December, 1999 Ex.P1.
Under the said Agreement:
(i) The defendant agreed to sell and the plaintiff agreed to purchase
elevators on the terms and conditions contained therein;
(ii) Out of the total price of Rs.1,30,20,000/-, Rs.10 lakhs was
payable immediately on signing of the Agreement, Rs.9 lakhs by 31 st
December, 1999: 60% on receipt of entire material on site at Dwarka,
Delhi, 15% on physical completion of the lifts, 5% on commissioning
and handing over of the lifts/elevators and balance 5% after six months
of commissioning of lifts;
(iii) The quoted prices were not to be subject to any escalation till
31st December, 2002 i.e. for a period of little over three years from the
date of execution of the Agreement;
(iv) The material of each lift/elevator was to be delivered within six
months of the written intimation from the plaintiff to the defendant;
(v) If the defendant was to be unable to deliver the lifts beyond six
months, then the plaintiff was entitled to refund of the advance of
Rs.19 lakhs along with interest @ 24% per annum and to the
compensation as specified for non-delivery;
(vi) In case of force majeure, the advance paid was not to be
forfeited but rather the contract was to be renegotiated giving due
consideration to the payment of advance "three years ago" by the
plaintiff.
9.2. It may be highlighted that the amount of Rs.19 lakhs paid by the
plaintiff, is in the Agreement described as „advance‟ and not as „earnest
money‟ and there is no clause in the Agreement of forfeiture thereof.
9.3. It was at the outset enquired from the counsel for the defendant,
whether the defendant in the absence of any Agreement entitling the
defendant to forfeit the advance and without having made any claim against
the plaintiff for recovery of compensation for any loss or damage even if any
suffered by the defendant for the breach alleged by the defendant of the
Agreement, could forfeit the said amount. Attention of the counsel for the
defendant in this regard was invited to the judgment of the Constitution
Bench of the Supreme Court in Fateh Chand Vs. Balkishan Dass AIR 1963
SC 1405 laying down that even where penalty within the meaning of Section
74 of the Indian Contract Act is stipulated for breach, without proving the
loss the same cannot be recovered. It was also pointed out to the counsel for
the defendant that though the defendant in the written statement as aforesaid
has taken a plea of the Agreement having provided for forfeiture of the
earnest money in the event of default by the plaintiff, no such clause was
found.
9.4. The counsel for the defendant, though could not pinpoint any clause in
the Agreement entitling the defendant to forfeit the advance, argued that the
absence of a clause for refund should be read as an implied clause of
forfeiture. Reliance was further placed on the force majeure clause which
provides that "in case of a force majeure condition due to which the contract
cannot be completed in the stipulated time, the advance shall not be
forfeited" to contend that the same also implies a right otherwise of the
defendant to forfeit. Reference was also made to Shri Hanuman Cotton
Mills Vs. Tata Air Craft Limited (1969) 3 SCC 522.
9.5. Per contra, the counsel for the plaintiff has referred to:
(a) Baldev Steel Ltd. Vs. Empire Dyeing & Manufacturing Co.
Ltd. 92 (2001) DLT 471 laying down in paras 29 and 30 thereof that a
party is not disentitled from recovering the advance even if in breach
because breach of the contract would only entitle the other party to sue
for damages but not to forfeit the advance and this legal position can
be altered by a special forfeiture clause which may defeat the right to
recover even an advance amount. It was further held that advance is in
the nature of a trust or quasi trust, earmarked for payment of price for
the goods to be supplied which could not be diverted or forfeited for
other purposes, including for an alleged breach of contract;
(b) Dilip Kumar Bhargava Vs. Urmila Devi Sharma 182 (2011)
DLT 646 laying down that there cannot be forfeiture even if the paying
party is guilty of breach unless the receiving party has suffered loss in
the bargain;
(c) Sudhir Rawal Vs. Satish Batra (2011) 126 DRJ 246, judgment
dated 9th November, 2011 of this Court in RFA No.422/2011 titled
Bhuley Singh Vs. Khazan Singh and judgment dated 17th May, 2012
of this Court in RFA No.51/2012 titled Ms. Kriti Kohli Vs. Sh. Hari
Nand, all to the same effect.
The counsel for the plaintiff has further contended that Shri
Hanuman Cotton Mills (supra) is not applicable to the facts of the
present case since the amount paid thereunder was by way of earnest
money and the Agreement contained a specific clause for forfeiture
thereof.
9.6. The counsel for the defendant in rejoinder relied on Satish Batra Vs.
Sudhir Rawal (2013) 1 SCC 345 allowing the appeal against the judgment
aforesaid of this Court relied upon by the counsel for the plaintiff. However,
it may be mentioned that in that case also the amount was described as
„earnest‟ and the contract contained a provision for forfeiture thereof and in
that context the Supreme Court held that where the amount represents the
guarantee that the contract would be fulfilled and which is part of the
contract price when the transaction is carried out and to be forfeited when the
transaction falls by the reason of the default or failure of the giver, forfeiture
is permissible.
9.7. The counsel for the defendant has also referred to Section 55 of the
Contract Act, 1872. However, I fail to see the relevance thereof.
9.8. Before discussing the matter further, it is necessary to notice some
further facts.
9.9. The defendant vide its letter dated 16th March, 2000 Ex.P4 to the
plaintiff acknowledged the receipt under cover of letter dated 14 th March,
2000 of the balance advance of Rs.9 lakhs and increased the validity of the
Agreement upto 14 th March, 2003.
9.10. The aforesaid letter shows that the objection of the defendant to the
delay on the part of the plaintiff in payment of Rs.9 lakhs was waived by the
defendant and the defendant cannot be now allowed to derive any advantage
therefrom.
9.11. The Architect of the plaintiff vide their letter dated 1 st May, 2003
informed the defendant that out of six blocks, shaft of 5 blocks were ready
for installation of lifts and requested the defendant to inspect the same,
supply the material and start the erection of the lifts. A reminder dated 27th
May, 2003 was also sent by the said Architects to the defendant. Though
both the said letters were denied by the defendant and no exhibit mark has
been put thereon but the defendant vide its letter dated 30 th July, 2003
(proved as Ex.P-5) to the plaintiff in response to the letters dated 1 st May,
2003 and 27th May, 2003 informed that the validity of the contract had
expired and the price of lifts had escalated substantially since December,
1999 and it was not possible for the defendant to execute the contract at the
agreed price; revised price of Rs.10,79,000/- per lift was also intimated to the
plaintiff. The defendant has not proved any other letters of 1 st May, 2003
and 27th May, 2003 to which the said response was sent and the letters dated
1st May, 2003 and 27th May, 2003 thus have to be held to have stood proved.
9.12. Before proceeding further with the discussion, I may notice that
though the defendant in its written statement has also taken a plea of the suit
claim being barred by time but neither was any issue pressed thereon nor any
argument urged. However the onus to satisfy that the suit claim is within
time being also on the Court, I record that the defense of the defendant of
limitation is misconceived. The amount of Rs.19 lakhs was paid in the year
1999-2000 as advance to be adjusted in the purchase price under an
Agreement, the period of completion whereof, according to the defendant
also was till the year 2003. The plea of having forfeited the said amount was
also taken by the defendant in response to the legal notice dated 16th March,
2004 and the suit was filed about one year therefrom. The said claim in my
opinion would fall in the residuary Article 113 of the Schedule to the
Limitation Act with the limitation therefor being three years from the date
when the right to sue accrues which in my opinion accrues only upon the
defendant refusing to refund the amount and the suit has been filed within
three years therefrom. Reference in this regard can be made to India Trade
Promotion Organisation Vs. India International Textile Machinery
Exhibitions Society 199 (2013) DLT 40 (DB).
9.13. Coming back to, whether in the absence of any clause in the agreement
of forfeiture, the amount of Rs.19 lakhs could be forfeited or not, though a
Single Judge of the Madras High Court in Mohammad Sultan Rowther Vs.
Naina Mohammad AIR 1973 Mad 233 did hold, in the context of an
agreement relating to sale of immovable property that in the absence of a
specific clause in the contract forfeiture is not permissible, but the legal
position as held by other Courts is found to be otherwise. Reference in this
regard may first be made to Howe Vs. Smith [1881-1885] All ER Rep 201
which was a case of contract for sale of land without any clause as to what
was to happen to the amount paid as deposit on default of the purchaser. It
was held that a deposit in common parlance is understood as a security for
completion of the purchase and the purchaser who has made the deposit
cannot insist on abandoning the contract and yet recover the deposit because
that would enable him to take advantage of his own wrong. Finding the
purchaser in that case to be in default, even in the absence of a clause for
forfeiture the purchaser was held not entitled to refund of the deposit. It
would thus be seen that the answer to, whether in the absence of a clause for
forfeiture there could be forfeiture or not was made dependant on the nature
and character of the payment.
9.14. In Dies Vs. British & International Mining & Finance Corporation
Ltd. [1939] 1 KB 724 which was in the context of sale of goods, an
argument was raised that though in the case of contract of sale of immovable
property, the existence of a clause for forfeiture was necessary to effect
forfeiture, but not so in contracts of sale of goods. It was however held that
there is no distinction in this respect between the contracts for sale of goods
and contracts for sale of immovable property. It was further held that where
the contract is silent, the matter of forfeiture has to be decided on the
principle of law insofar as the intention of the parties can be ascertained from
designation used to indicate the nature of the sum that was paid. A
distinction was carved out between a payment designated as deposit and one
designated as part payment and it was held that a deposit, in the event of the
contract being performed, goes in diminution of the purchase price, and in
the interval between contract and completion operates as an earnest or
guarantee that the contract shall be performed i.e. acts as liquidated damages
in the event of breach of contract. It was further held that while a
deposit/earnest could be forfeited, part payment could not be even if the
purchaser who had made part payment was in default and the only remedy of
the seller was to sue for damages.
9.15. The aforesaid view was followed by the High Court of Calcutta in
Naresh Chandra Guha Vs. Ram Chandra Samanta AIR 1952 Cal 93 where
though the payment was designated as Bayana, there was no clause neither
for its forfeiture nor for its return and it was held that the agreements
containing covenants or clauses of forfeiture are to be treated on the same
footing as agreements without the same provided of course there is no clause
for return or refund of the money in question. It was further held that the
nature of the money in question has to be determined i.e. whether it was
intended to serve as earnest or security for performance, necessarily implying
a liability to forfeit or as part payment. It was yet further held that the said
designation has to be made by applying the golden rule of intention of the
parties. Monies described as earnest or deposit, it was held are to be
presumed to be earnest or security for performance liable to be forfeited even
in the absence of a clause therefor. It was however held that the rule of
forfeiture has no application to money received as part payment.
9.16. This Court also in In Re: R.K. Staple Spinning Mills P. Ltd.
MANU/DE/0374/1971 for the reason of the money being described as
earnest, even in the absence of a clause for forfeiture held the same liable to
forfeiture.
9.17. Recently again this Court in State Bank of India Vs. Union of India
199 (2013) DLT 697 citing with approval Howe, Dies and Naresh Chandra
Guha supra and certain other judgments held that earnest money once paid
is and continues to remain the property of the recipient; it is paid under what
is termed as contract of security which is distinct and separate from real or
pure contract and the right to forfeiture arises under a contract of security,
which could be provided expressly or impliedly.
9.18. Before applying the aforesaid principles to the facts in hand, mention
may also be made of Videocon Properties Ltd Vs. Dr. Bhalchandra
Laboratories (2004) 3 SCC 711 dealing with a contract of sale of
immovable property. The Supreme Court reiterated that earnest money is
part of the purchase price when the transaction goes forward and is forfeited
when the transaction falls through by reason of failure or fault of purchaser
and it is not the description by words used in the agreement that would be
determinative of the character of the sum but really the intention of the
parties and the surrounding circumstances as well will have to be looked
into and what may be called advance may really be a deposit or earnest
money and what is termed as deposit or earnest money may ultimately turn
out to be an advance or part of purchase price.
9.19. Similarly in Satish Batra supra the Supreme Court held that to justify
the forfeiture of advance as earnest money the terms of the contract should
be clear and explicit and part payment of purchase price cannot be forfeited
unless it is a guarantee for due performance of the contract.
9.20. The principle has also been succinctly crystallized in paragraphs 508
and 510 of Volume 88 of the 5 th Edition of the Halsbury‟s Laws of England
under the head „Claim by the party in breach to recover money paid‟:-
"A party who commits a breach of contract may be able to bring a restitutionary claim against the innocent party
to recover payments made to the innocent party prior to the termination of the contract. The right to recover will only arise where the contract has been discharged as a result of the innocent party electing to terminate the contract. When seeking to ascertain the rights of the party in breach to recover money paid, the courts have drawn a distinction between deposits and part payments. The distinction between the two is a matter of construction which in large part turns on the purpose for which the payment was made. Where the language used in the contract is neutral, then a payment will generally be interpreted as part payment so that it is, in principle, recoverable."
xxxxx
"Where the money has been paid prior to the discharge of the contract not as a deposit or earnest for performance but as a prepayment of the purchase price, the right of the party in breach to recover the sum so paid depends on the construction of the particular contract between the parties. Where the contract is one of sale and no property in the goods has passed to the buyer, the money will generally be recoverable by the purchaser either because the right of the vendor to retain the prepayment is conditional upon completion of the contract so that, when completion does not take place as a result of the discharge of the contract, the condition upon which the vendor retains the money fails with the result that the money is recoverable by the purchaser or on the ground that the consideration for the payment has wholly failed. Where the contract is one for work and materials, the prepayment is less likely to be recoverable. This is particularly so where the recipient of the money incurs expenditure in the performance of the contract: the prepayment in such a case is unlikely to be recoverable either because it is an unconditional payment or on the ground that the failure of
consideration in such a case is not total."
9.21. The payment of Rs.19 lakhs under the subject contract is described as
advance and not as earnest. It is otherwise also not found to be in the nature
of a guarantee for fulfilling of the contract; rather the same is only in the
nature of a consideration to peg till 31st December, 2002 the prices prevalent
and agreed upon in December, 1999. This is amply clear from the force
majeure clause which while providing for renegotiation, provides for
weightage to be given to the advance held by the defendant for three years in
determining the renegotiated price.
9.22. It is also not borne out from the subject contract that the defendant
thereunder was required to do any work whatsoever till receipt of written
intimation from the plaintiff and which according to the defendant was not
received within the period of validity of three years of the Agreement. This
is obvious from the fact that after the receipt of the said written intimation
from the plaintiff, the defendant had six months‟ time to deliver the material
for each lift. If the contract had intended the defendant to keep the material
for each lift ready immediately after the signing of the Agreement, there was
no need for giving the period of six months to the defendant for delivery
thereafter. Though the defendant in the evidence, has vaguely sought to
suggest that the defendant had worked under the Agreement but no
foundation for the same has been laid in the pleadings as aforesaid. The
defendant has not pleaded as to what work it had done under the Agreement
till the receipt of communication dated 1st May, 2003 and 27th May, 2003
from the Architects of the plaintiff. Significantly, the defendant on the
expiry of the validity of the Agreement also did not issue any communication
intimating to the plaintiff of the forfeiture of the advance or of any losses
suffered by it. No claim for such losses has been made as aforesaid. Though
the witness of the defendant Mr. Amjad Sayyed in his affidavit Ex.DW1/A
by way of examination-in-chief has vaguely suggested that the plaintiff
wanted the defendant to begin procuring the material for installation of the
lifts and be in a ready state as soon as the plaintiff had completed the
infrastructural requirements for installation work but has shied away from
deposing as to what procurements were made at what price and as to how the
same have been wasted. Further, if the defendant were to have already
acquired the material, there would have been no question of escalation.
9.23. As aforesaid, the amounts received as earnest money/deposit vest in
the receiver from the very day of the receipt to be applied either towards
price or to be forfeited. Per contra, amounts received as purchase price are
advance in the hands of the seller, subject to fulfillment of the contract. The
defendant though a company, required in law to maintain accounts and have
them audited, has not led any evidence of the treatment given to the sum of
Rs.19 lacs in its books of accounts. Adverse inference thus has to be drawn
against the defendant that it is continuing to show the amount of Rs.19 lacs
in its books of accounts as advance.
9.24. Issue No.2 is accordingly decided in favour of the plaintiff and against
the defendant and the plaintiff is found entitled to refund from the defendant
of the advance of Rs.19 lakhs.
10. Re: Issue No.4. Whether the plaintiff has not adhered to the terms of the agreement? OPD
10.1. In the light of the discussion above, this issue is redundant.
10.2. Even otherwise I am unable to return a finding of the plaintiff having
not adhered to the terms of the Agreement. As aforesaid, the consideration
for advance of Rs.19 lakhs was not performance of the Agreement, but only
to peg the price. The only effect of the failure of the plaintiff to send
intimation to the defendant before 14 th March, 2003 of its readiness to have
the elevators installed was to disentitle the plaintiff from the price agreed to
in the year 1999 and cannot have any other consequence. Upon the parties in
the year 2003-2004 being unable to arrive at a consensus of the new prices,
the amount of Rs.19 lakhs paid as advance, became refundable by the
defendant to the plaintiff irrespective of the failure of the plaintiff to avail of
the 1999 price.
10.3. Similarly, the changes in the specifications made by the plaintiff
would have no relevance in the light of the aforesaid.
10.4. The Issue No.4 is also thus decided in favour of the plaintiff and
against the defendant.
11. Re: Issue No.3. Whether the plaintiff is entitled to interest, if so, at what rate and from what date? OPP
11.1. The plaintiff has claimed interest @ 24% per annum, not with effect
from December, 1999/March, 2000 when the advance was paid but only with
effect from 30th July, 2003.
11.2. I have already held above that the plaintiff, upon the parties being
unable to arrive at a consensus as to the new price, became entitle to refund.
Accordingly, the claim of the plaintiff to interest with effect from 30 th July,
2003 is found to be justified.
11.3. As far as the rate of interest is concerned, the parties had in the
contract Ex.P1 agreed to interest @ 24% per annum for default on the part of
the defendant. For the said reason, I do not find any ground to interfere with
the claim at the said rate for the pre-suit institution period. However, as far
as the interest pendente lite and future is concerned, considering the rate of
interest paid by the Nationalized Banks on fixed deposits and considering the
nature of the transaction, award of interest @ 10% per annum is deemed
expedient.
11.4. Issue No.3 is decided accordingly.
12. Resultantly, a decree is passed in favour of the plaintiff and against the
defendant for recovery of Rs.28,05,753.43 paise together with interest @
10% per annum on the sum of Rs.19 lakhs from the date of institution of the
suit till realization. The plaintiff shall also be entitled to costs of the suit.
Decree sheet be drawn up.
RAJIV SAHAI ENDLAW, J JULY 10, 2013 bs
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!