Citation : 2013 Latest Caselaw 2772 Del
Judgement Date : 4 July, 2013
*IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of decision: 4th July, 2013
+ CS(OS) 713/2010
JINDAL STEEL & POWER LIMITED ..... Plaintiff
Through: Mr. Pinaki Misra, Sr. Adv. with
Mr. Atul Shanker Mathur, Ms.
Shruti Verma, Mr. Aseem
Chaturvedi and Mr. Abnisaar
Bairagi, Advs.
Versus
N.S. ATWAL ..... Defendant
Through: Mr. Rajshekhar Rao and Mr. Adit
S. Pujari, Advs.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
RAJIV SAHAI ENDLAW, J
IA No.12936/2011 (of the defendant for leave to defend)
1.
The plaintiff has sued under Order 37 of the CPC for recovery of
principal sum of Rs.2,98,39,060/- along with interest at the agreed rate of
10% per annum accrued thereon with effect from April, 2007 to March,
2008 and thereafter @ 12% per annum from April, 2008 till institution of
this suit in February, 2010 i.e. total Rs.4,00,44,341.20p, pleading:
(i) that the defendant is the sole proprietor of M/s Guru Mehar
Construction;
(ii) that in December, 2000, the defendant approached the plaintiff
with offer to conduct the excavation activities required by the
plaintiff at its mining site near Dongamohua village, District
Raigarh, Chhattisgarh;
(iii) that after negotiations and deliberations, the plaintiff awarded to
the defendant, the contract for hiring of heavy earthmoving
equipments and services for excavation works for a total period
of four years i.e. till March, 2005 vide Work Order dated
02.03.2001;
(iv) that vide letter dated 13.06.2005, the defendant requested the
plaintiff to provide a one time soft loan of Rs.7.17 crores
recoverable over the period of five years on the ground that the
defendant needed to replace and revamp the existing
equipments;
(v) that the plaintiff agreed to so provide financial assistance to the
defendant as is evident from the letters exchanged between the
parties and disbursed the loan to the defendant and the
defendant agreed to the plaintiff deducting installments from
the amounts becoming due and payable by the plaintiff to the
defendant on the basis of bills raised by the defendant for the
work done under the aforesaid Work Order;
(vi) that thereafter the defendant vide its letter dated 16.06.2005
informed the plaintiff that he needed a soft loan of Rs.500 lacs
but since the plaintiff had agreed to provide a sum of Rs.300
lacs only, the said sum of Rs.300 lacs would be repayable by
way of monthly installments of Rs.10 lacs along with interest
over a period of 30 months starting from November, 2005;
(vii) that the plaintiff released a total sum of Rs.563 lacs to the
defendant from 18.06.2005 to 17.11.2005, out of which a sum
of Rs.450 lacs was paid directly to the defendant and a sum of
Rs.113 lacs paid to SREI Infrastructure Finance Ltd. for and on
behalf of the defendant towards lease financing of equipment;
(viii) that the defendant vide letter dated 24.11.2005 admitted and
acknowledged the receipt of the aforesaid loan amount and
requested for the same to be repaid over a period of five years
instead of 30 months as agreed earlier and which was agreed to
by the plaintiff;
(ix) that the defendant vide letter dated 19.07.2006 further requested
for release of a sum of Rs.200 lacs for meeting its working
capital requirement and further Rs.275 lacs to make down
payment to financiers from whom he had got the required
equipments financed on leasehold basis;
(x) that in response to the aforesaid request, the defendant was
provided additional financial assistance of Rs.100 lacs on
02.08.2006;
(xi) that thus during December, 2004 till August, 2006 total
financial assistance of Rs.663 lacs was provided by the plaintiff
to the defendant;
(xii) that the plaintiff vide its letter dated 17.07.2006, on the request
of the defendant, agreed to renew the Work Order for the period
starting from 15.02.2006 till 31.03.2007 and a formal Work
Order dated 04.08.2006 was issued by the plaintiff and accepted
by the defendant;
(xiii) that the defendant failed to perform his obligations under the
Work Order and the plaintiff vide its letter / notice dated
08.11.2006 terminated the said Work Order and called upon the
defendant to pay the sum of Rs.548.64 lacs along with interest
and also to pay the liquidated damages;
(xiv) that the defendant challenged the legality and validity of the
termination and raised a claim to the tune of Rs.436 lacs on
account of non adjustments and being due to him under the
Work Order though not disputing the outstanding of Rs.548.64
lacs in the loan account;
(xv) that the plaintiff denied the claim of the defendant of Rs.436
lacs and claimed the amount of Rs.2,98,39,060/- towards
principal outstanding loan amount and Rs.163.86 lacs under
the work order;
(xvi) that the plaintiff thereafter filed an Arbitration Application
No.53/2009 under Section 11 of the Arbitration and
Conciliation Act, 1996 before this Court. The said petition
was dismissed vide judgment dated 03.12.2009 holding that
the loan transaction was independent of the Work Order and
not arbitrable under the arbitration clause in the Work Order;
and
(xvii) that hence this suit for recovery of principal outstanding of
Rs.2,98,39,060/- under the loan account with interest as
aforesaid.
2. The suit was entertained under Order 37 of the CPC and summons for
appearance were issued. The delay of 2/3 days in entering appearance was
condoned vide order dated 12.04.2012 subject to payment of costs of
Rs.20,000/-. In response to the summons for judgment, the defendant seeks
leave to defend on the following grounds:
(i) that the suit is not maintainable under Order 37 of the CPC;
(ii) that there is no contract for payment of interest at 10% as
claimed;
(iii) that the claim is barred by limitation; the loan is pleaded to
have been given between 17.06.2005 and 02.08.2006 and the
limitation for seeking recovery thereof was three years only;
(iv) that the parties have contractual relationships for over 12 years;
(v) that the defendant had resisted the petition under Section 11 of
the Arbitration Act filed by the plaintiff pleading that the
dispute pertaining to soft loan advanced by the plaintiff to the
defendant were an entirely different transaction and not subject
matter of the arbitration clause in the Work Order;
(vi) that the arbitration proceedings initiated by the plaintiff arising
out of disputes in relation to the Work Order are pending before
the sole Arbitrator;
(vii) that the legal notice dated 08.11.2006 showed an outstanding of
Rs.5,48,64,000/- towards the loan amount but in the suit, the
principal amount has been claimed to be Rs.2,98,39,060/- only;
(viii) that „assuming though not admitting‟ even if the said amount is
payable by the defendant towards the purported loan amount
which could have been adjusted with the securities and other
funds belonging to the defendant and held back by the plaintiff;
(ix) that the termination of the Work Order was mala fide; elaborate
pleadings have been made in that regard but which it is not felt
necessary to record the same being not germane to the matter in
controversy; and,
(x) that the defendant has claims of much larger amount against the
plaintiff and which are subject matter of arbitration.
3. The plaintiff has filed reply to the leave to defend application.
4. The counsels have been heard.
5. The counsel for the defendant has argued; i) that the plaintiff has not
filed the original documents on the basis whereof the suit has been filed, the
suit is thus not maintainable under Order 37 of the CPC; ii) that there is no
contract between the parties on the basis whereof a liquidated amount of
money claimed in the suit can be said to be due from the defendant to the
plaintiff; iii) that the suit claim is barred by time; and, iv) that all these raise
triable issues and for which leave has to be granted to the defendant.
6. Per contra, the senior counsel for the plaintiff has drawn attention to:
(i) letter dated 13.06.2005 of the defendant to the plaintiff asking
for a soft loan of Rs.7.17 crores recoverable over a period of
five years;
(ii) letter dated 16.06.2005 of the defendant to the plaintiff
confirming the agreement arrived at between the parties;
(iii) letter dated 24.11.2005 of the defendant to the plaintiff thanking
the plaintiff for the loan to the tune of Rs.4.50 crores and for
making payment of Rs.50 lacs to the financer of the defendant
on behalf of the defendant and requesting for the said loan to be
repayable in five years time;
(iv) letter dated 19.07.2006 of the defendant to the plaintiff
requesting for a loan of Rs.2 crores for working capital;
(v) letter dated 22.11.2006 of the defendant to the plaintiff
confirming that the loan amount was being recovered from the
running bills raised by the defendant on the plaintiff;
(vi) letter dated 05.01.2007 of the defendant to the plaintiff not
controverting the payment on loan account;
(vii) reply filed by the defendant in Arbitration Application
No.53/2009 supra, also not denying the loan transaction and
only pleading the same to be not arbitrable;
7. The senior counsel for the plaintiff has relied on:
(i) Rickmers Verwaltung GMBH Vs. Indian Oil Corporation Ltd.
(1999) 1 SCC 1 laying down that it is the duty of the Court to
construe the correspondence with a view to arrive at a
conclusion whether there was any meeting of mind between the
parties which could create a binding contract between them and
on the basis thereof has contended that if from the
correspondence an unequivocal and clear contract emerges, the
claim would be maintainable under Order 37 of the CPC;
(ii) Corporate Voice (P) Ltd. Vs. Uniroll Leather India Ltd. 60
(1995) DLT 321 where on the basis of letters exchanged
between the parties, the suit under Order 37 CPC was
entertained;
(iii) Deutsche Ranco GMBH Vs. Mohan Murti 52(1993) DLT 288
laying down that the counter claim of the defendant is not a
defence to a suit under Order 37 of the CPC; and
(iv) R. Kumar & Co. Vs. Chemicals Unlimited AIR 2001 Bombay
116 where on the basis of letters addressed by the defendant to
the plaintiff pointing out the amounts stated in their books of
accounts to be their liabilities towards the plaintiff, the suit
under Order 37 was held maintainable.
8. The counsel for the defendant in rejoinder again invited attention to
para 31 of the leave to defend making detailed pleadings with respect to the
illegality of the termination effected by the plaintiff of the Work Order and
referred to the judgment dated 31.08.2012 of this Court in CS(OS)
2859/2011 titled GE Capital Services India Vs. May Flower Healthcare
Pvt. Ltd. laying down that the suit for a balance amount due on a loan
account does not fall under Order 37 of the CPC and that merely because the
plaintiff has a strong case on merits cannot be a ground to entertain the suit
under Order 37.
9. During the hearing on 23.01.2013, it was enquired from the counsel
for the defendant whether the defendant in his own books of accounts was
showing any loan due to the plaintiff. On the counsel for the defendant
being not able to reply, it was deemed appropriate to examine the defendant
under Order 10 of the CPC and the defendant was directed to appear on
31.01.2013 for recording of his statement along with his books of accounts
i.e. ledger and balance sheet of the relevant years and till date, showing the
loan account with the plaintiff and to state as to how much money on the
loan account according to him was due to the plaintiff without adjustment of
his counter claim against the plaintiff.
10. In response to the aforesaid, the defendant appeared on 31.01.2013
and produced a bunch of documents comprising of 30 sheets containing inter
alia the balance sheet of M/s Guru Mehar Construction, sole proprietary of
the defendant and in which the sum of Rs.2,98,39,060/-, being the principal
amount claimed in the suit, was shown as loan outstanding to the plaintiff as
on 31.03.2011. Ex.P1 was put on the said documents and in view thereof
need was not felt to record the statement of the defendant and the counsels
were heard further.
11. The counsel for the defendant in his further submissions frankly stated
that in view of the defendant himself in his balance sheet showing the
outstanding of Rs.2,98,39,060/- towards the plaintiff, the said liability could
not be disputed. His contention however was, liability to repay the said
amount was intertwined with the Work Order disputes with respect whereto
were subject matter of pending arbitration proceedings between the parties.
12. Per contra, the senior counsel for the plaintiff contended that the
conduct of the defendant as has emerged from the aforesaid, is
contumacious; that though the plaintiff was desirous of having the claims on
the loan account also adjudicated in arbitration proceedings but it is the
defendant who had opposed the same and cannot now be heard to argue to
the contrary.
13. The counsel for the defendant in rejoinder has argued that the
defendant, if made to pay the loan amount before his claims under the Work
Order are adjudicated, would be devastated and on humanitarian grounds the
adjudication in this proceeding should await the outcome of arbitration
proceeding.
14. As far as the plea of the maintainability of the suit under Order
37 of the CPC is concerned, though undoubtedly there is no document
on the basis whereof, the defendant can be said to have admitted the
liability in the balance principal amount of Rs.2,98,39,060/- towards
the plaintiff but in my opinion, in view of the subsequent admission by
the defendant of the liability in the principal amount claimed in the suit,
the same pales into insignificance. This Court, if were to, inspite of
such admission by the defendant, go into technicalities as to the
maintainability of the suit under Order 37 of the CPC, would be
lending credence to the perception "the law is an ass - an idiot" echoed
by Mr. Bumble in Charles Dickens „Oliver Twist‟. Justice cannot be
frustrated by legalistics. It is the duty of every court to prevent its
machinery from being made a sham, thereby running down the rule of
law itself as an object of public ridicule. It will and must prove any
stratagem self defeating if a party indulges in making the law a
laughing stock, for the court will call him to order. Justice Krishna Iyer
in Bushing Schmitz Private Limited v. P.T. Menghani (1977) 3 SCR
312 quoted with approval Lord Erskine "there is no branch of the
jurisdiction of this Court more delicate than that, which goes to restrain
the exercise of a legal right". He further held "But the principle of
unconscionability clothes the court with the power to prevent its
process being rendered a parody". Once it is clear that there is no
dispute of the sum of Rs.2,98,39,060/- being due from the defendant to
the plaintiff in the loan account, the Court will not enter into an
academic exercise and pronounce on technicalities. The Supreme
Court in T. Arvindandam Vs. T.V. Satyapal AIR 1977 SC 2421,
Liverpool & London S.P. & I Association Ltd. Vs. M.V. Sea Success I
(2004) 9 SCC 512 and ITC Limited Vs. Debts Recovery Appellant
Tribunal (1998) 2 SCC 70 has held that the Courts are not to prolong
litigations, the fate whereof is otherwise clear and at the expense of
other cases requiring adjudication. Even if not under Order 37 of the
CPC, the plaintiff under Order 12 Rule 6 CPC or under Order 15 is
entitled to a decree in the principal sum of Rs.2,98,39,060/-. Recently
also, in Krishna Devi Malchand Kamathia v. Bombay Environmental
Action Group (2011) 3 SCC 363, the Supreme Court observed that
justice is only blind or blindfolded to the extent necessary to hold its
scales evenly; it is not, and must never be allowed, to become blind to
the reality of the situation, lamentable though that situation may be.
15. As far as the claim for interest is concerned, there is undoubtedly
no agreement as to the rate of interest @ 10% or @12% on which the
plaintiff has claimed interest for the period prior to the institution of the
suit. Though the correspondences between the parties mentions of the
payment of interest but the senior counsel for the plaintiff has not
shown any document containing agreement as to rate of interest or
show rate at which interest was being paid by the defendant to the
plaintiff. The plaintiff has also not explained the basis for claiming
interest @ 10% or 12%. However, it has been held in Khera
Handloom Supply Vs. O.B. Exports 41(1990)DLT343, and Rama
Vision Ltd. Vs. Babbar Vision India Pvt. Ltd. 67(1997)DLT281 that
merely because there is no agreement as to the rate of interest, is no
ground not to entertain the suit under Order 37 of the CPC.
16. Considering the entirety of the facts and circumstances, I am of the
view that grant of interest at the rate of 8% per annum from 01.04.2008
being the year in which the plaintiff has instituted the arbitration application
under Section 11 of the Arbitration Act against the defendant would
subserve the purpose.
17. Once the plaintiff is found entitled to a decree, the same cannot be
denied or stalled for the reason of pendency of a claim in a separate
proceeding by the defendant against the plaintiff, as is clear from Deutsche
Ranco GMBH supra, though in execution, if such claim is allowed by then,
the same may have relevance under Order 21 Rule 18 CPC.
18. The application for leave to defend is accordingly disposed of.
19. Axiomatically, a decree is passed in favour of the plaintiff and against
the defendant for recovery of Rs.2,98,39,060/- together with interest at 8%
per annum thereon with effect from 01.04.2008 till the date of institution of
the suit, pendente lite and till the date of recovery. The plaintiff shall also be
entitled to costs of the suit as per the Schedule.
Decree sheet be drawn up.
RAJIV SAHAI ENDLAW, J th JULY 4 , 2013 „gsr‟
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!