Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Union Of India & Anr vs Foregewell Engineering ...
2013 Latest Caselaw 3723 Del

Citation : 2013 Latest Caselaw 3723 Del
Judgement Date : 23 August, 2013

Delhi High Court
Union Of India & Anr vs Foregewell Engineering ... on 23 August, 2013
Author: Rajiv Sahai Endlaw
          *IN THE HIGH COURT OF DELHI AT NEW DELHI

%                                    Date of decision: 23rd August, 2013

+                                RFA 259/2011

       UNION OF INDIA & ANR                             ..... Appellants
                    Through:          Mr. Jaswinder Singh, Adv.

                           Versus

    FOREGEWELL ENGINEERING
    CORPORATION                       ..... Respondent

Through: None.

CORAM :-

HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW

RAJIV SAHAI ENDLAW, J

1. This first appeal impugns the judgment and decree dated

03.01.2011 of the Court of Additional District Judge (Central)-17, Delhi

of dismissal of Suit No.284/2009 filed by the appellant / plaintiff for

recovery of Rs.12,00,889/- from the respondent / defendant along with

pendente lite and future interest.

2. Notice of the appeal was issued and the Trial Court record

requisitioned. The notice sent to the respondent / defendant was returned

with the endorsement of the respondent / defendant having left the

address given in the memorandum of appeal. When the subsequent

attempts for service of the respondent / defendant also failed, ultimately

vide order dated 29.05.2013, the respondent / defendant was permitted to

be served by publication. Publication as ordered has been effected. None

appears for the respondent / defendant.

3. A perusal of the impugned judgment shows that the respondent /

defendant was ex parte in the suit also.

4. The counsel for the appellant / plaintiff has been heard.

5. The appellant / plaintiff had instituted the suit from which this

appeal arises, pleading:

(i) that pursuant to the bids / tenders invited by the appellant /

plaintiff for Flood Lighting along the Indo-Pak border in

PH:III in 120 kms. stretch of Barmer District of Rajasthan by

supply and installation of 24 nos. of manually operated 110

KVA DG Sets, the bid of the respondent / defendant being

the lowest was accepted and the respondent / defendant

awarded the contract for the said work;

(ii) that the estimated cost of the said work put to tender was

Rs.1,04,22,668/- and the respondent / defendant had bid for

Rs.1,20,88,888/-;

(iii) that the respondent / defendant failed to comply with the

terms and conditions of the contract and failed to supply the

entire ordered quantity inspite of repeated requests,

reminders and opportunities resulting in rescission of the

agreement and notice being given to the

respondent/defendant of execution of the balance work at the

risk and cost of the respondent / defendant;

(iv) that the respondent / defendant sought appointment of the

Arbitrator and an Arbitrator was appointed; during the

pendency of arbitration also respondent / defendant was

given opportunity to carry out the balance work but the

respondent / defendant still failed to do so and the work was

accordingly got carried out through a third party;

(v) that as per Clause 2 of the Agreement, SE (E), BFLC,

CPWD, Jaisalmer decided and determined that the

respondent / defendant was liable to pay Rs.12,00,889/- by

way of compensation, being 10% of the tendered costs

towards the liquidated damages besides the other claims of

the appellant / plaintiff;

(vi) that the appellant / plaintiff made the said claim before the

Arbitrator also but the Arbitrator in award dated 15.02.2006

held the said claim of the appellant / plaintiff for

Rs.12,00,889/- to be an 'excepted matter' and accordingly

gave liberty to the appellant / plaintiff to take other remedies

for recovery of the said amount;

Accordingly, the suit for recovery of the said amount was filed:

6. The respondent / defendant as aforesaid was proceeded against ex

parte before the Trial court also and the appellant / plaintiff led its ex

parte evidence by filing an affidavit by way of examination-in-chief of its

Executive Engineer (E), BFLD-II, CPWD, Jaisalmer and closed its

evidence.

7. The learned Additional District Judge has vide the impugned

judgment and decree dismissed the suit of the appellant / plaintiff on two

grounds. Firstly, that the appellant / plaintiff had failed to place any

material in support of its claim and secondly on the ground of the claim in

suit being barred by time.

8. On the aspect of limitation, it was held that though the appellant /

plaintiff was vide award dated 15.02.2006 granted liberty to avail

alternative remedy for its claim for Rs.12,00,889/- but the suit had been

filed after three years therefrom on 02.06.2009 and was thus barred by

limitation as prescribed in Articles 27 and 113 of the Limitation Act,

1963.

9. The counsel for the appellant / plaintiff has argued that the learned

Additional District Judge failed to consider that the Article applicable to

the claim of the appellant / plaintiff being the Central Government was

Article 112 of the Limitation Act which provides for a period of 30 years

from the date when the period of limitation would begin to run against a

like suit by a private person. It is contended that if the said Article had

been applied, the suit could not have been barred by limitation. Reliance

in this regard is placed on Maharaja Shree Umaid Mills Ltd. Vs. Union

of India 1981 E.L.T. 772 (Raj.)(DB) and on Controller of Aerodrome,

Nagpur Airport, Nagpur Vs. Homi D. Jahangir 1987 LawSuit (Bom)

11.

10. The stipulated date of completion of the works awarded to the

respondent / defendant was 08.03.1996 and there can be no doubt that the

claim of the appellant was within the said period of 30 years prescribed in

Article 112 of the Limitation Act. The finding of the learned Additional

District Judge of the suit claim being barred by time is thus clearly

erroneous and is set aside.

11. Though the learned Additional District Judge save for observing

that the appellant / plaintiff has not placed any material in support of its

claim has not given any other reasons but a perusal of the plaint and the

affidavit by way of examination-in-chief shows the nature of the said

claim to be for liquidated damages in accordance with the contract

between the parties and which contract authorized the SE (E), BFLC,

CPWD, Jaisalmer of the appellant / plaintiff to determine the liquidated

damages in accordance with the formula provided therein. Though

undoubtedly neither in the plaint nor in the affidavit by way of

examination-in-chief the said aspect has been highlighted and no

documents whatsoever have been purported to be proved or tendered into

evidence but the fact of the matter remains that the photocopies of the

documents in this regard i.e. the notice inviting tenders, the bids

submitted by the respondent / defendant, the contract awarding the work

to the respondent / defendant and the decision of the SE (E), BFLC,

CPWD, Jaisalmer levying penalty under Clause 2 of the Agreement at

Rs.12,00,889/- on the respondent / defendant were on the Court file.

12. I have in Aktiebolaget Volvo Vs. R. Venkatachalam 160 (2009)

DLT 100 held that the CPC and the Evidence act refer only to 'document'

and which would include photocopy and the question of producing the

original would arise only upon the photocopy being disputed. Similarly, I

have in Indian Performing Rights Society Ltd. Vs. Gauhati Town Club

MANU/DE/0582/2013 held that where the defendant is ex parte and the

material before the Court is sufficient to allow the claim of the appellant /

plaintiff, the time of the Court should not be wasted in directing ex parte

evidence to be recorded and which mostly is nothing but a repetition of

the contents of the plaint.

13. Following the aforesaid dictas, I am of the view that

notwithstanding the failure of the appellant / plaintiff to have proved its

case for recovery of Rs.12,00,889/- in the traditional manner, on the basis

of material on record the appellant / plaintiff is entitled to decree of

Rs.12,00,889/- as claimed.

14. Notice in this regard may also be taken of the fact that Supreme

Court in ONGC Vs. Saw Pipes Ltd. (2003) 5 SCC 705 has held that in

public works, the loss/damage from non performance and delay cannot be

assessed and a reasonable estimate made by the parties of the damage

which would be suffered by non-execution of the works is to be accepted

without any proof of loss or damage having been caused inasmuch as it is

the public in general which suffers. Considering the nature of the work in

the present case relatable to the security of the country, the importance

thereof and the resultant damage from delay in affecting the same can

well be fathomed.

15. I also deem it proper to award interest on the said amount to the

appellant / plaintiff from the date of institution of the suit at the rate of

9% per annum being the average rate paid by the nationalized banks

during the said years on fixed deposits with them.

16. The appeal is accordingly allowed and the judgment and decree of

the Trial Court is set aside. The suit of the appellant / plaintiff is decreed

for recovery of Rs.12,00,889/- with interest at 9% per annum from the

date of institution of the suit till the date of recovery. However, the

respondent / defendant having not contested the suit, no order as to costs.

Decree sheet be drawn up.

RAJIV SAHAI ENDLAW, J.

AUGUST 23, 2013 'gsr'

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter