Citation : 2013 Latest Caselaw 3723 Del
Judgement Date : 23 August, 2013
*IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of decision: 23rd August, 2013
+ RFA 259/2011
UNION OF INDIA & ANR ..... Appellants
Through: Mr. Jaswinder Singh, Adv.
Versus
FOREGEWELL ENGINEERING
CORPORATION ..... Respondent
Through: None.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
RAJIV SAHAI ENDLAW, J
1. This first appeal impugns the judgment and decree dated
03.01.2011 of the Court of Additional District Judge (Central)-17, Delhi
of dismissal of Suit No.284/2009 filed by the appellant / plaintiff for
recovery of Rs.12,00,889/- from the respondent / defendant along with
pendente lite and future interest.
2. Notice of the appeal was issued and the Trial Court record
requisitioned. The notice sent to the respondent / defendant was returned
with the endorsement of the respondent / defendant having left the
address given in the memorandum of appeal. When the subsequent
attempts for service of the respondent / defendant also failed, ultimately
vide order dated 29.05.2013, the respondent / defendant was permitted to
be served by publication. Publication as ordered has been effected. None
appears for the respondent / defendant.
3. A perusal of the impugned judgment shows that the respondent /
defendant was ex parte in the suit also.
4. The counsel for the appellant / plaintiff has been heard.
5. The appellant / plaintiff had instituted the suit from which this
appeal arises, pleading:
(i) that pursuant to the bids / tenders invited by the appellant /
plaintiff for Flood Lighting along the Indo-Pak border in
PH:III in 120 kms. stretch of Barmer District of Rajasthan by
supply and installation of 24 nos. of manually operated 110
KVA DG Sets, the bid of the respondent / defendant being
the lowest was accepted and the respondent / defendant
awarded the contract for the said work;
(ii) that the estimated cost of the said work put to tender was
Rs.1,04,22,668/- and the respondent / defendant had bid for
Rs.1,20,88,888/-;
(iii) that the respondent / defendant failed to comply with the
terms and conditions of the contract and failed to supply the
entire ordered quantity inspite of repeated requests,
reminders and opportunities resulting in rescission of the
agreement and notice being given to the
respondent/defendant of execution of the balance work at the
risk and cost of the respondent / defendant;
(iv) that the respondent / defendant sought appointment of the
Arbitrator and an Arbitrator was appointed; during the
pendency of arbitration also respondent / defendant was
given opportunity to carry out the balance work but the
respondent / defendant still failed to do so and the work was
accordingly got carried out through a third party;
(v) that as per Clause 2 of the Agreement, SE (E), BFLC,
CPWD, Jaisalmer decided and determined that the
respondent / defendant was liable to pay Rs.12,00,889/- by
way of compensation, being 10% of the tendered costs
towards the liquidated damages besides the other claims of
the appellant / plaintiff;
(vi) that the appellant / plaintiff made the said claim before the
Arbitrator also but the Arbitrator in award dated 15.02.2006
held the said claim of the appellant / plaintiff for
Rs.12,00,889/- to be an 'excepted matter' and accordingly
gave liberty to the appellant / plaintiff to take other remedies
for recovery of the said amount;
Accordingly, the suit for recovery of the said amount was filed:
6. The respondent / defendant as aforesaid was proceeded against ex
parte before the Trial court also and the appellant / plaintiff led its ex
parte evidence by filing an affidavit by way of examination-in-chief of its
Executive Engineer (E), BFLD-II, CPWD, Jaisalmer and closed its
evidence.
7. The learned Additional District Judge has vide the impugned
judgment and decree dismissed the suit of the appellant / plaintiff on two
grounds. Firstly, that the appellant / plaintiff had failed to place any
material in support of its claim and secondly on the ground of the claim in
suit being barred by time.
8. On the aspect of limitation, it was held that though the appellant /
plaintiff was vide award dated 15.02.2006 granted liberty to avail
alternative remedy for its claim for Rs.12,00,889/- but the suit had been
filed after three years therefrom on 02.06.2009 and was thus barred by
limitation as prescribed in Articles 27 and 113 of the Limitation Act,
1963.
9. The counsel for the appellant / plaintiff has argued that the learned
Additional District Judge failed to consider that the Article applicable to
the claim of the appellant / plaintiff being the Central Government was
Article 112 of the Limitation Act which provides for a period of 30 years
from the date when the period of limitation would begin to run against a
like suit by a private person. It is contended that if the said Article had
been applied, the suit could not have been barred by limitation. Reliance
in this regard is placed on Maharaja Shree Umaid Mills Ltd. Vs. Union
of India 1981 E.L.T. 772 (Raj.)(DB) and on Controller of Aerodrome,
Nagpur Airport, Nagpur Vs. Homi D. Jahangir 1987 LawSuit (Bom)
11.
10. The stipulated date of completion of the works awarded to the
respondent / defendant was 08.03.1996 and there can be no doubt that the
claim of the appellant was within the said period of 30 years prescribed in
Article 112 of the Limitation Act. The finding of the learned Additional
District Judge of the suit claim being barred by time is thus clearly
erroneous and is set aside.
11. Though the learned Additional District Judge save for observing
that the appellant / plaintiff has not placed any material in support of its
claim has not given any other reasons but a perusal of the plaint and the
affidavit by way of examination-in-chief shows the nature of the said
claim to be for liquidated damages in accordance with the contract
between the parties and which contract authorized the SE (E), BFLC,
CPWD, Jaisalmer of the appellant / plaintiff to determine the liquidated
damages in accordance with the formula provided therein. Though
undoubtedly neither in the plaint nor in the affidavit by way of
examination-in-chief the said aspect has been highlighted and no
documents whatsoever have been purported to be proved or tendered into
evidence but the fact of the matter remains that the photocopies of the
documents in this regard i.e. the notice inviting tenders, the bids
submitted by the respondent / defendant, the contract awarding the work
to the respondent / defendant and the decision of the SE (E), BFLC,
CPWD, Jaisalmer levying penalty under Clause 2 of the Agreement at
Rs.12,00,889/- on the respondent / defendant were on the Court file.
12. I have in Aktiebolaget Volvo Vs. R. Venkatachalam 160 (2009)
DLT 100 held that the CPC and the Evidence act refer only to 'document'
and which would include photocopy and the question of producing the
original would arise only upon the photocopy being disputed. Similarly, I
have in Indian Performing Rights Society Ltd. Vs. Gauhati Town Club
MANU/DE/0582/2013 held that where the defendant is ex parte and the
material before the Court is sufficient to allow the claim of the appellant /
plaintiff, the time of the Court should not be wasted in directing ex parte
evidence to be recorded and which mostly is nothing but a repetition of
the contents of the plaint.
13. Following the aforesaid dictas, I am of the view that
notwithstanding the failure of the appellant / plaintiff to have proved its
case for recovery of Rs.12,00,889/- in the traditional manner, on the basis
of material on record the appellant / plaintiff is entitled to decree of
Rs.12,00,889/- as claimed.
14. Notice in this regard may also be taken of the fact that Supreme
Court in ONGC Vs. Saw Pipes Ltd. (2003) 5 SCC 705 has held that in
public works, the loss/damage from non performance and delay cannot be
assessed and a reasonable estimate made by the parties of the damage
which would be suffered by non-execution of the works is to be accepted
without any proof of loss or damage having been caused inasmuch as it is
the public in general which suffers. Considering the nature of the work in
the present case relatable to the security of the country, the importance
thereof and the resultant damage from delay in affecting the same can
well be fathomed.
15. I also deem it proper to award interest on the said amount to the
appellant / plaintiff from the date of institution of the suit at the rate of
9% per annum being the average rate paid by the nationalized banks
during the said years on fixed deposits with them.
16. The appeal is accordingly allowed and the judgment and decree of
the Trial Court is set aside. The suit of the appellant / plaintiff is decreed
for recovery of Rs.12,00,889/- with interest at 9% per annum from the
date of institution of the suit till the date of recovery. However, the
respondent / defendant having not contested the suit, no order as to costs.
Decree sheet be drawn up.
RAJIV SAHAI ENDLAW, J.
AUGUST 23, 2013 'gsr'
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!