Citation : 2013 Latest Caselaw 1511 Del
Judgement Date : 3 April, 2013
$~R1
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of Judgment:03.4.2013
+ FAO(OS) 35/2008
DELHI DEVELOMENT AUTHRITY ..... Appellant
Through: Mr. Pawan Mathur, Adv.
versus
M/S ANANT RAJ AGENCIES ..... Respondent
Through: Ms. Biji Rajesh, Adv.
CORAM:
HON'BLE MR. JUSTICE SANJAY KISHAN KAUL
HON'BLE MS. JUSTICE INDERMEET KAUR
INDERMEET KAUR, J.
1 The appellant (DDA) is aggrieved by the impugned order dated
13.3.2007 wherein the objections filed by it under Section 30 and 33 of
the Indian Arbitration Act, 1940 (hereinafter referred to as the said Act)
against the Award dated 02.11.1998 of the sole Arbitrator
Mr.L.R.Pahwa had been modified only to the extent that qua item No.29
of Claim No.1 an amount of Rs.1,88,220/- was ordered to be deducted.
The remaining amounts awarded under the three heads were sustained.
2 Record shows that the appellant and the respondent had entered
into a contract whereby the respondent had undertaken construction of
8314 houses in Sector-XV, Rohini as also construction of 448 EWS
Houses in Pocket 16,17,19 and 20 of Block F in terms of an agreement
No. 6EE/RPD-5/DDA/85-86.
3 Disputes arose between the parties and in terms of the arbitration
clause contained in the said agreement, Mr. L.R.Pahwa was appointed
as the sole learned Arbitrator. Numerous hearings were held before the
Arbitrator as is evident from the record. Claims were raised before him.
The learned Arbitrator awarded a total amount of Rs. 28,54,700.41 in
favour of the claimant under three separate heads. An amount of
Rs.14,28,544.96 was awarded under the Claim No.1 on account of work
done but not paid. A second sum of Rs.13,68,755.45 was awarded
towards damages under item no.32 of Claim No.1. Under the third head
i.e. item no.33 of Claim No.1 a sum of Rs.57,400/- was awarded which
was towards watch and ward for a period of seven months i.e. from
15.5.1992 till 14.12.1992. Interest on the aforesaid amounts @ 12%
from the date of the payment was also granted.
4 Detailed and lengthy arguments have been addressed by the
learned counsel for the appellant. He has attacked the Award primarily
qua four claims; submission being that these claims have been wrongly
adjudicated upon by the learned Arbitrator:
i- The sum of Rs.1,41,653.57 not subtracted by the learned
Arbitrator on account of reduction items was an illegal finding as
clause 25B of the agreement specifically stipulated that the
decision of the Superintending Engineer qua this position would
be final and this would not be an arbitral claim; this was not
considered by the learned Arbitrator.
ii- Double payment of 10 CC has been awarded and the
recovery of Rs.1,46,716/- sought by the appellant has been
wrongly rejected; submission being that this sum of Rs.1,46,716/-
had already been paid against the 11th, 12th and the 13th running
bills to the respondent; this sum was thus liable to be deducted
from the total 10 CC amount of Rs.5,32,848/- payable.
iii- Items No.8, 9 and 10 of Claim No.1 vide which the
appellant sought recoveries on account of the material claimed by
the contractor at additional rates, the difference in the price of the
fittings, and interest on the secured advances were incorrectly
refused as there was no evidence on record to show that the
contractor had in fact consumed the material that had been issued
to him; clause 42 of the agreement was also not examined.
iv- Item No.32 of Claim No.1 which was a claim of
Rs.13,68,755.45 awarded to the respondent as losses suffered by
him was based on a misapplication of the cost index method; it
was incumbent upon the respondent to have proved the actual loss
and damages incurred by him and having failed to adduce any
such evidence this claim was wrongly allowed.
5 Record shows that the Arbitrator appointed is a technical person
being an Engineer Member of the Department. He has penned down an
Award running into more than 40 pages. It was noted that both the
parties i.e. the appellant and the respondent had filed their respective
final bills; discrepancies in measurement of the certain quantities of
items were also noted; since the respondent had not filed on record any
verification of the aforesaid measurements, the quantities recorded by
the appellant in the final bill were accepted as the correct quantities.
6 As per the bills filed by the appellant it had admitted that a sum of
Rs.4,18,165/- was payable to the respondent. However, it had made
certain deductions.
7 Qua the first submission made by the learned counsel for the
appellant the deduction of Rs.1,41,653.57 on account of reduction items
was negatived by the learned Arbitrator. This deduction was sought for
the first time during course of the arbitration proceedings. In fact the
appellant had himself recorded that the work had been executed by the
respondent as per the specifications and the nomenclature of the items; it
had been noted that while releasing payments in the running bills the
appellant had failed to place on record any communication showing
deficiency on the part of the respondent in the execution of any
particular item for which reduction has been sought which was even
otherwise raised for the first time in the course of the arbitration
proceedings. Clause-14 of the agreement had also not been followed by
the appellant before making a resort to the reduction. This claim of
Rs.1,41,653.57 was accordingly disallowed. The submission of the
learned counsel for the appellant that Clause 25 B of the contract was
not adhered to may not have been expressly noted by the learned
Arbitrator but a perusal of his reasoning on this count negatives this
submission.
8 For a better appreciation of this argument it would be relevant to
extract Clause 25 B of the contract which reads as under:
"The decision of Superintending Engineer regarding the quantum
of reduction as well as justification thereof in respect of rates for
substandard work which may decided to be accepted will be final
and would not be open to arbitration."
9 Learned Arbitrator had noted that not only did the appellant not
raise any objection about the execution of the work as per the
specifications during disbursement of payments of the running bills but
the appellant had also failed to place on record any document showing
the deficiency in any particular item. The body of the appeal makes a
reference to a letter dated 20.02.1995 purported to have been sent by the
appellant to the respondent but the learned counsel for the appellant has
failed to point out any such document from the record. Non-adherence
to the provisions of Clause-14 has also not been disputed. The
disallowance by the learned Arbitrator of this deduction was accordingly
based on cogent reasoning.
10 Qua the second figure of Rs.1,46,716/- which as per the appellant
was a double payment qua 10 CC amount; the appellant has again failed
to give any details for seeking a deduction of this amount. It has been
argued before us that at the time of the payment of the 11th ,12th and the
13th running bill this sum of Rs.1,46,716/- already stood paid to the
respondent and as such this amount was clearly liable to be deducted
from the final 10 CC amount payable to the respondent. It has been put
to the learned counsel for the appellant that it appears that no such
argument had been propounded either before the learned Arbitrator or
before the learned single Judge to which he has no answer. The Award
of the learned Arbitrator as also the impugned order of the learned single
Judge shows that not only no such argument was addressed before them
but even today before this Court the learned counsel for the appellant
concedes that there was no such document filed before either of the two
fora to substantiate this submission. Being only an oral argument,
addressed before this Court, the learned Arbitrator had rightly noted that
this amount was not a justifiable deduction from the final bill. This
view was rightly endorsed by the learned single Judge.
11 The attack on the third claim relates to the items no.8, 9 and 10 of
Claim No.1. Under item no.8 a sum of Rs.1,26,462.06 was awarded to
the respondent. This was towards recovery of additional rates on
account of the material used in the work. Learned counsel for the
appellant on this count submits that this was a case of no evidence;
Clause-42 of the agreement has also not been followed; Clause- 42 has
been read over in the Court; learned counsel for the appellant, however,
has failed to show as to how and in what manner this clause is either
applicable or was not followed by the learned Arbitrator. It is an
undisputed fact that the work order was delayed and the delay was
attributable by and large to the appellant. Admittedly, no notice had
been issued by the appellant to the respondent for any wastage or any
pilferage of material by the respondent or that the respondent had not
consumed the entire material in the course of the work or even misused
it. In the absence of any such proof the claim of the department to
deduct this amount of Rs.1,26,462.06 was rightly negated. This amount
which was ordered to be refunded to the respondent was endorsed by the
learned single Judge. It was not a case of no evidence.
12 Under item no.9, the appellant had sought recovery of Rs.32,381/-
on account of difference in cost of fittings at market rate and as per the
rates agreed to in the contract. Record shows that the work was finally
completed by the respondent on 15.11.1991; at that time it was never
pointed out to the respondent that any fitting was missing or that they
had not been provided for by the respondent; there was no justifiable
reasons for the appellant to seek deduction on this count either.
13 Qua item no.10, the appellant had sought a deduction of
Rs.38,102/-which was recovery on account of interest on secured
advances. In terms of the agreement between the parties the secured
advance was to be given by the appellant to the respondent for material
brought by the respondent at the site; this was to be adjusted by the
appellant at the time of making payment of the bills. Admittedly, there
was a delay in adjusting this secured advance. Thus, the respondent was
rightly entitled to interest on this amount. Recovery on this count was
also rightly rejected.
14 Under item no.32 qua Claim No.1 a sum of Rs.13,68,755.35
was awarded to the respondent. This was towards the loss suffered by
him. The cost index method was taken into account by the learned
Arbitrator to determine this loss; cost indices were published by the
Government of India and had also admittedly been taken into
consideration by the appellant while calculating justification rates for
accepting tenders submitted in respect of building works; these cost
indices are published by the Government of India on a monthly basis.
It is not the case of the appellant that this cost index does not depict the
actual escalations coming into the work; it is also admitted that they are
published by the Government of India. It is further not disputed that the
appellant himself has relied upon these cost indices for calculating its
justification rates. This evidence was thus rightly considered and acted
upon by the learned Arbitrator to determine the loss suffered by the
respondent qua the prolongation of the work. Actual proof of damages
in these circumstances was not called for. Amount awarded under this
head also suffers from no irregularity. It was rightly upheld by the
learned single Judge.
15 The scope of interference while dealing with objections under
Sections 30 and 33 of the said Act are limited. It is only in the
eventuality of the Award being totally perverse or absurd that an
interference is called for by the higher court. This court is not sitting as
a court of appeal. Merely because two views are possible, and the
higher court may have come to a different conclusion on the material
available before the Arbitrator, would not by itself be a ground to re-
appraise and re-appreciate the evidence led before the learned
Arbitrator.
16 This court is sitting in the second hierarchy, the objections filed
against the Award have been dealt with in detail by the learned single
Judge. All except one have been upheld. It is not within the domain of
this Court to re-examine each item clause by clause and to hold that it
was either sustainable or not sustainable and especially so when the
learned Arbitrator himself was an experienced man being a technical
expert i.e. an Engineer Member of the Department. It is also not the
case of the appellant that there was no evidence before the learned
Arbitrator; by and large the submission being that the evidence and the
clauses of the contract were not appreciated correctly.
17 In Gujarat Water Supply & Sewerage Board v. Unique Erectors
(Gujarat) (P) Ltd. and Anr. AIR 1989 SC 973 the Supreme Court has
held that the Arbitrator is the final arbiter of the dispute inter se the
parties and the award is not open to challenge on account that the
Arbitrator had reached a wrong conclusion and had failed to appreciate
the facts. The Apex Court has in fact repeatedly cautioned the Courts
that unless an Award is contrary to law or the Arbitrator has mis-
conducted himself which mis-conduct is either related to a personal mis-
conduct of the Arbitrator or a mis-conduct of law; an Award ought not
to be interfered with. In State of U.P. v. Allied Constructions (2003) 7
SCC 396 the Supreme Court has again reiterated that Section 30 of the
said Act is restrictive in its operation. The higher court is precluded
from re-appreciating the evidence. An error apparent on the face of the
record does not imply a closer scrutiny on the merits of the documents
and material on record. If the view of the Arbitrator is plausible the
court should refrain from interfering.
18 On all these parameters, the test applied to the Award as also the
order of the learned single Judge shows that in no manner does the
impugned order warrant any interference.
19 We thus find no merit in the appeal and the same is dismissed
leaving the parties to bear their own costs.
20 The amount deposited in court with interest accrued thereon be released to the respondent.
INDERMEET KAUR, J.
SANJAY KISHAN KAUL, J.
APRIL 03, 2013 nandan
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!