Citation : 2012 Latest Caselaw 5775 Del
Judgement Date : 26 September, 2012
IN THE HIGH COURT OF DELHI AT NEW DELHI
(Not reportable)
O.M.P. 521 of 2006
ARORA CONSTRUCTION CO. (PVT.) LTD ..... Petitioner
Through: Ms. Anusuya Salwan with Ms. Renuka
Arora, Mr. Kunal Kohli and Mr. Vikas
Sood, Advocates.
Versus
BHARAT SANCHAR NIGAM LIMITED & ANR ..... Respondents
Through: None.
CORAM: JUSTICE S. MURALIDHAR
ORDER
26.09.2012
1. The challenge in this petition under Section 34 of the Arbitration and
Conciliation Act, 1996 ('Act') is to an Award dated 31st July 2006 passed
by the learned sole Arbitrator (Respondent No. 2) in the disputes between
the Petitioner M/s. Arora Construction Co. (Pvt.) Ltd. (hereinafter referred
to as 'the Contractor') and Respondent No. 1 Bharat Sanchar Nigam
Limited ('BSNL') arising out of a contract for the work of construction of
administrative building at Sector 15-A, Faridabad (Haryana) SH: Building
portion and services.
2. In terms of the contract, the date of start of the work was 25th March
2000 and the stipulated date of completion was 24th August 2001. The
actual date of completion was 30th June 2003. The date of payment of the
final bill was 15th July 2003 and the amount of the final bill was Rs.
1,11,62,380.82.
3. The Superintendent Engineer (Civil), ['SE (Civil)'] BSNL invoked
Clause 2 of the contract which provided for penal compensation for delay.
After giving due notice to the Contractor by letter dated 9th December
2003, the SE (Civil) imposed a penal compensation of Rs. 4,25,672 for the
period of delay from 14th October 2001 to 30th June 2003. It is not in
dispute that the Contractor filed CS (OS) No. 2203 of 2003 in this Court
challenging the above levy of compensation which was an 'excepted
matter' and in respect of which no arbitral proceedings could have been
initiated.
4. As regards the claims of the Contractor against the BSNL arising out of
the contract, the arbitration clause was invoked by the Contractor and the
disputes were referred to the learned Arbitrator.
5. There were 16 items of claims. Claim No. 1 was for a sum of Rs.
1,38,158 on account of less payment made for broken glazed tiles. The
Contractor had demanded the rate of Rs. 390 per sq.mtr whereas BSNL had
paid at the rate of Rs. 206.89 per sq.mtr. By its letter dated 1st October 2002
the Contractor submitted its analysis of rates for the work of broken glazed
tiles in terms of which the rate per sq.mtr was worked out to Rs. 311.60 per
sq.mtr. It was contended by the Contractor, that BSNL did not refute the
above claim.
6. A perusal of the impugned Award as regards Claim No. 1 shows that
before the learned Arbitrator BSNL produced its rate analysis (Annexure
R-69) dated 26th March 2003 working out the rate as Rs. 206.89 per sq.
mtr. The original records in support of the said rate analysis were also
produced. The learned Arbitrator noticed that in terms of Clause 12 (v) of
the agreement, irrespective of the rate claimed by the Contractor, the
Engineer In-charge ('EIC') had to determine the rate of additional work on
the basis of prevailing market rate. The Contractor could not show any flaw
in the rate determination of BSNL. The learned Arbitrator accordingly
rejected Claim No. 1.
7. It is submitted by Ms. Anusuya Salwan, learned counsel appearing for
the Contractor, on the strength of the decision of the High Court of
Himachal Pradesh in S.M. Sareen v. State of H.P. 1991 Law Suit (HP)
187 that once a rate analysis was submitted at the initial stage by the
Contractor and was not disputed by BSNL, then such rate analysis
submitted by the Contractor had to be accepted.
8. In the instant case the learned Arbitrator was presented with two rate
analysis. One by the Petitioner in the form of letter dated 1st October 2002
(Annexure C-73) and the other of BSNL dated 26th March 2003 (Annexure
R-69). It was within the jurisdiction of the learned Arbitrator to opt for the
rate analysis of BSNL. It cannot be said that by accepting the rate analysis
of BSNL, the learned Arbitrator committed a patent illegality within the
scope of Section 34 of the Act.
9. Claim No. 8 was for a sum of Rs. 1,62,648 towards the sum less paid in
shuttering of shell. As regards the said claim also, the learned Arbitrator
held that the Contractor could not show any infirmity in the rate of Rs.
241.12 per sq.mtr worked out by BSNL as per the Delhi Schedule Rates for
archives, etc. The Contractor by its letter dated 15th June 2001 quoted the
rate of Rs. 500 per sq.mtr. BSNL by its letter dated 22nd June 2001 refuted
that claim and stated that the rate worked out was Rs. 241.12 per sq.mtr. It
was within the scope of the powers of the learned Arbitrator to accept the
rate worked out by BSNL over the rate submitted by the Contractor.
Consequently, the rejection of Claim No. 8 by the learned Arbitrator cannot
be said to be suffering from any legal infirmity.
10. Claim No. 12 was for a sum of Rs. 7 lakhs due to less measurement and
rates, etc. The learned Arbitrator while rejecting the said claim noticed that
the Contractor had not raised such a claim either during the execution of
the work or during the joint measurement or even thereafter when the final
payments were accepted by the Contractor. In the circumstances, rejection
of the said claim of the learned Arbitrator cannot be said to be erroneous.
11. The Award in respect of Claim Nos. 6 and 7 in the sum of Rs. 24,000
less payment in shuttering also does not call for interference. The learned
Arbitrator has given cogent reasons and found in respect of each of the two
claims, that no objections had been raised by the Contractor with regard to
measurement in shuttering either at the time of measurements or at the time
of finalization of bills.
12. The remaining objections of the Contractor as regards the Award are in
respect of Claim Nos. 2, 9 and 10. Claim No. 2 was for a sum of Rs.
4,80,000 on account of payment in respect of Clause 10 (CC) plus interest.
Claim No. 9 was for a sum of Rs. 11,24,570 due to loss of profit plus
interest and Claim No. 10 was for a sum of Rs. 35,28,000 on account of
overrun charges of the contract with interest.
13. The learned Arbitrator in the impugned Award rejected the above
claims 'for the present' on the ground that the action taken by the SE
(Civil) in levying the penalty of Rs. 4,25,672 for the period 14th October
2001 to 30th June 2003 under Clause 2 had not yet been held to be bad and
illegal since CS(OS) No. 2203 of 2003 filed by the Contractor in this Court
challenging the said penalty was still pending.
14. Ms. Salwan draws the attention of this Court to the decision of the
Supreme Court in J.G. Engineers Private Limited v. Union of India
(2011) 5 SCC 758, and the decisions of this Court in Dharam Construction
v. Delhi Development Authority 1998 1 AD (Delhi) 572, Puran Chand
Nangia v. DDA 2006 IV AD (Delhi) 168 and Indian Farmers Fertiliser
Co-operative Ltd. v. Duggal Constructions (India) Ltd. 186 (2012) DLT
658 (DB) to contend that the issue whether the delay in completion of the
work was attributable to the BSNL or the Contractor had to be necessarily
decided by the learned Arbitrator. She submitted that even in respect of the
accepted Clause 2, the question whether the penalty was justified would
hinge upon the question whether the delay in completion of the work was
caused by the Contractor.
15. In J.G. Engineers Private Limited v. Union of India the Supreme
Court analysed an identical clause. The clause in that case required
compensation to be paid by the Contractor for not completing the work
within the stipulated period. Clause 2 of the contract in that case was
analysed, as under:
"18. Thus what is made final and conclusive by Clauses (2) and (3) of the agreement, is not the decision of any authority on the issue whether the contractor was responsible for the delay or the Department was responsible for the delay or on the question whether termination/rescission is valid or illegal. What is made final, is the decisions on consequential issues relating to quantification, if there is no dispute as to who committed breach. That is, if the contractor admits that he is in breach, or if the arbitrator finds that the contractor is in breach by being responsible for the delay, the decision of the Superintending Engineer will be final in regard to two issues. The first is the percentage (whether it should be 1% or less) of the value of the work that is to be levied as liquidated damages per day. The second is the determination of the actual excess cost in getting the work completed through an alternative agency. The decision as to who is responsible for the delay in execution and who committed breach is not made subject to any decision of the respondents or its officers, nor excepted from arbitration under any provision of the contract.
19. In fact the question whether the other party committed breach cannot be decided by the party alleging breach. A contract cannot provide that one party will be the arbiter to decide whether he committed breach or the other party committed breach. That question can only be decided by only an adjudicatory forum, that is, a court or an arbitral Tribunal."
16. The decisions of this Court relied upon by learned counsel for the
Contractor are consistent with the law explained in the above decision.
Consequently, the decision in the present case on the question of delay had
necessarily to be taken by the learned Arbitrator notwithstanding the
decision as to the quantification of such penalty by the assesse in terms of
Clause 2 of the contact which quantification could constitute an 'excepted
matter'. However, since the Contractor has challenged the levy of penalty
in this Court in CS(OS) No. 2203 of 2003 there is a possibility of
inconsistent views being expressed by the learned Arbitrator in the arbitral
proceedings and the Court in CS(OS) No. 2203 of 2003.
17. Faced with this position, Ms. Salwan submitted that the Contractor
would file an application in CS (OS) No. 2203 of 2003 seeking leave to
withdraw the said suit with liberty to have the question whether the delay in
completion of the work was attributable to the Contractor or the BSNL
referred to arbitration in addition to Claim Nos. 2, 9 and 10 which have not
been decided by the learned Arbitrator only due to the pendency of the suit.
18. In light of the law explained by the Supreme Court in J.G. Engineers
Private Limited v. Union of India it appears that the course suggested by
Ms. Salwan is an appropriate one and it would be open to the Contractor to
have the question concerning the party responsible for the delay in
completion of the work, even for the purposes of penalty under Clause 2,
referred to arbitration. This would obviate inconsistent findings in two fora.
19. In that view of the matter, subject to the Petitioner filing an application
in CS(OS) No. 2203 of 2003 seeking leave to withdraw the said suit with
liberty to have the disputes concerning penalty under Clause 2 of the
contract also referred to arbitration, in light of the law explained by the
Supreme Court in J.G. Engineers Private Limited v. Union of India, the
impugned Award in respect of Claim Nos. 2, 9 and 10 is set aside and
liberty is granted to the Contractor to seek reference of Claim Nos. 2, 9 and
10 including the disputes arising out of the levy of penalty under Clause 2
to arbitration in accordance with law. The impugned Award as to the
remaining clauses is upheld.
20. The petition is disposed of in the above terms.
S. MURALIDHAR, J.
SEPTEMBER 26, 2012 Rk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!