Citation : 2012 Latest Caselaw 5762 Del
Judgement Date : 26 September, 2012
IN THE HIGH COURT OF DELHI AT NEW DELHI
(Reportable)
CS (OS) No. 776-A of 2004
Reserved on: 1st August, 2012
Decision on: 26th September, 2012
BOMBAY CONTAINER TERMINALS PVT. LTD. ..... Plaintiff
Through: Mr. Atul Y. Chitale, Senior Advocate
with Ms. Padmaja Kaul, Advocate.
Versus
CENTRAL WAREHOUSING CORPORATION ..... Defendant
Through: Mr. K.K. Tyagi, Advocate.
CORAM: JUSTICE S. MURALIDHAR
JUDGMENT
26.09.2012
1. This judgment disposes of the objections filed by the Plaintiff, Bombay Container Terminals Pvt. Ltd. ('BCT') under Sections 30 and 33 of the Arbitration Act, 1940 ('Act') to the final Award dated 27th May 2004 passed by the sole Arbitrator in the disputes between it and the Defendant, Central Warehousing Corporation ('CWC'), arising out of a contract dated 21st April 1989 whereby the work of handling and transportation of ISO containers from the Jawaharlal Nehru Port Container Yard ('JNP-CY') at Nhava Sheva to the Jawaharlal Nehru Port Container Freight Station ('JNP-CFS'), at Nhava Sheva and vice versa for a period of four years was awarded by CWC to BCT. The learned Arbitrator awarded BCT a sum of Rs.19,28,946 together with simple interest at 9% per annum. BCT has challenged the impugned final Award to the extent that some of its claims have been rejected.
Background Facts
2. The background facts are that on 26th September 1988, the Government of India wrote to the Chairman, Jawaharlal Nehru Nhava Sheva Port Trust ('JNPT') granting approval to the proposal of entrusting the operations of the CFS to CWC. On 21st April 1989, CWC awarded BCT the sub-contract for handling and transportation work at the CFS, Nhava Sheva by issuing a Letter of Intent ('LOI'). On 31st May 1989, a written contract was executed between the parties. Apart from handling and transportation of ISO Containers between JNP-CY to JNP-CFS and vice versa, the contract required BCT to undertake the work of de-stuffing of cargo, stacking in the designated godown, receipt of export cargo at JNP-CFS godown, stuffing of export containers and transportation of export containers to JNP-CY, handling of empty containers and other incidental services.
3. Subsequent to the execution of the contract CWC shifted its export aggregation warehouse to Kalamboli, 24 km away from the JNP-CFS at Nhava Sheva due to lack of essential infrastructure facilities at JNP-CFS. As a result an additional distance of 48 km (24 km each way) was required to be covered for transportation of export containers. A letter was written by CWC on 5th December 1989 to BCT awarding a contract for Kalamboli @ Rs.1095 per Twenty Equivalent Units ('TEU'). The LOI and the contract dated 31st May 1989 formed part of the subsequent contract as well. The contract was for a period of four years i.e. from 31st May 1989 to 20th April 1993. The contract was extended and finally came to an end on 11th July 1993.
4. The contract involved four stages. In the first stage, in case of import of cargo, the containers containing cargo would arrive by ship at the JNP. They
would be offloaded from the ship to the shore by rail mounted quay cranes ('RMQCs'). This work was done by the JNPT employees with their own equipment. The second stage involved carrying the containers offloaded from ship on trailer tractors to the JNP-CY, unloading and stacking them. This work was also done by the JNPT through its own vehicles and employees. The third stage involved carrying the containers from the JNP- CY to the JNP-CFS on SISU vehicles and trailers provided by the JNPT. The loading of containers at the JNP-CY onto SISU vehicles was carried out by Rubber Tyred Gantry Cranes ('RTGCs'). The supervisor of BCT had to produce daily the Equipment Interchange Reports ('EIRs') to the checkers/supervisors of the JNPT at the JNP-CY. After identification by the JNPT checkers, the containers would be loaded onto the SISUs manned by BCT drivers. Thereafter they would be brought, in the case of imports, to a CFS 8 km and/or taken from an Export CFS to JNPT 26 km away from the JNP-CY. However while loading if the containers were found damaged, certain laid down procedures had to be complied with, before being carried to the CFS. The fourth stage was carried out at the CFS. After the containers were brought into the CFS they were to be unloaded by cranes/belotti owned by BCT and manned by its employees. Thereafter the containers would be carried into the marked area in the CFS and kept stacked. The stacked containers would be brought down for de-stuffing and customs examination. Thereafter the cargo would be handed over to the clearing agent of the importers. The activity of de-stuffing the cargo and stuffing it back after the customs examination was carried out by BCT through its workers and equipments.
5. According to BCT, during the period of the contract, CWC arbitrarily
deducted an amount of Rs.39,38,188 under various heads and also withheld an amount of Rs.31,57,155 from the running bills of BCT in violation of the contractual terms without following the due process of law. BCT states that CWC also refused to grant escalation on account of increase in administered price diesel cost and oil hike caused by the Gulf War. Further, BCT suffered enormous losses due to the shifting of the warehouse to Kalamboli and the business turnover being far less than what was assured. BCT states that by letters dated 15th March 1993 and 22nd September 1993 it protested against the arbitrary deductions and withholding of amounts by CWC. It also demanded payment of the increased cost of diesel and oil.
6. BCT points out that in terms of the proviso to Clause XX of the tender document a claim by BCT against CWC or vice versa had to be made in writing within one year of the date of termination of the contract which in this case was 11th July 1993. Accordingly by a letter dated 28th December 1993 BCT submitted to CWC a list of claims followed by reminders on 11th March, 29th April and 31st November 1994. When CWC did not respond to its letters, BCT filed Suit No.943 of 1995 in the Bombay High Court following which CWC appointed the sole Arbitrator by its letter dated 31st July 1995.
Proceedings before the Arbitrator
7. BCT states that instead of referring BCT's claims to the sole Arbitrator, CWC filed its statement of claims before him on 29th September 1995, which according to BCT was beyond the period of one year in terms of the proviso to Clause XX of the tender documents. BCT then filed its written statement and counter-claims on 23rd December 1995. In the arbitral
proceedings, therefore, CWC was the Claimant and BCT the Respondent.
8. The case of CWC was that BCT's performance was from the very beginning unsatisfactory. There was considerable delay in the movement of import as well as export containers resulting in numerous complaints from both importers and exporters. JNPT too expressed its extreme displeasure and threatened to cancel its agreement with CWC. BCT failed to provide sufficient number of tractors and trailers and even those that were provided broke down frequently. BCT's drivers were not trained and damaged JNPT's properties. When matters did not improve, CWC had to issue show cause notices and impose penalties as a compensatory measure. CWC states that the Manager, CFS imposed a penalty aggregating to Rs.15,07,004 for delay in movement of import containers, Rs.6,20,354 for delay in the de-stuffing of loaded containers, Rs.1,47,841 for damage to the cargo, Rs.1,61,467 for damage to the containers and Rs.2,35,391 for damage to property. These amounts were therefore recovered from BCT's bills. According to CWC, these were beyond the scope of arbitration. Apart from the above, deductions were made in the sum of Rs.5,64,998 for electrical charges, Rs.5,40,000 as hiring charges for the forklift and Rs.1,09,222 for miscellaneous items.
9. The case of BCT was that it provided at the import CFS six brand new Voltas forklifts, two heavy lift cranes, one toplifter and one container handler immediately after the contract was executed. Similar equipments were provided at the export CFS at Kalamboli. It provided 10 of its own trailers and leased another two trailers. BCT states that it was made to employ project affected persons, who were totally unskilled, as drivers of the SISUs and for de-stuffing. The RTGCs were not available readily. Further,
the SISU vehicles suffered from manufacturing defects and their spare parts were not available. Consequently, those vehicles broke down frequently and even otherwise their performance was dismal. This led to the delay in movement of the containers from JNPT to CFS. BCT claims to have suffered huge loss on account of grossly inadequate turnover of containers. Although, it was estimated to be 5000 TEUs per month, and equipment and machinery was procured by BCT in anticipation of that volume of work, JNPT failed to attract that volume of business. According to BCT this forced the staff and equipment to remain idle and the loss suffered by it was to the tune of Rs.7,29,23,960. On account of the steep hike in the costs of HSD and diesel up to 23.8% on account of Gulf War, BCT suffered a loss of Rs.88,12,320. Accordingly, the counter-claims were filed by BCT.
Issues framed by the Arbitrator
10. The learned Arbitrator framed the following issues:
"(1) Are the deductions made by the Claimants from the Respondents bills on account of delay in movement of containers, delay in de-stuffing of containers, damage to property, containers and the cargo, electricity charges, Forklift charges and miscellaneous deductions legally valid. Is the actual amount Rs. 38,79,284 as contended by the Claimants or Rs. 39,38,188 as contended by the Respondents?
(2) Are the Claimants competent to with-hold payment of Rs. 25,30,991 due to the Respondents?
(3) Do deductions amounting to Rs. 26,78,060 fall under the excepted matters and are not arbitrable?
(4) Are the Respondents entitled to a sum of Rs. 7,27,23,960 as compensation on account of loss in business?
(5) Should the Respondents be paid an additional amount of
Rs. 88,12,320 on account of hike in the HSD cost?
(6) Are the Respondents entitled to interest also @ 24% p.a. on the aforesaid amount?
(7) Whether the Claimants-Corporation are entitled to levy any penalty whatsoever on the Respondents-Contractors in view of the fact that no penalty was levied by the JNPT?"
11. In the course of the proceedings, the CWC examined Mr. Ajay Khera its Regional Manager whereas BCT examined Mr. T.K. Ram, Regional Manager, Nhava Sheva, CFS Operations, Mr. Sameer Parikh, Regional Manager, In-charge of Nhava Sheva, CFS Operations and Mr. James John, Junior Manager, BCT.
Interim and Final Awards
12. Pursuant to an application dated 27th November 1996 by BCT, the learned Arbitrator passed an interim Award on 9th December 1996 directing the CWC to release to BCT a sum of Rs.23,24,883. The said sum has since been paid by the CWC to BCT. The impugned final Award dated 27th May 2004 granted BCT a sum of Rs.19,28,946, in addition to the sum under the interim Award, together with interest @ 9% per annum on the sum of Rs.19,28,946 with effect from 31st July 1995 till the date of payment and on the sum of Rs.23,24,883 interest @ 9% per annum for the period from 31st July 1995 to 9th December 1996. The said amounts have since been paid by CWC to BCT. The acceptance by BCT of the said sum was under protest without prejudice to its right to challenge the impugned final Award to the extent that some of its claims have been rejected.
13. In the impugned final Award dated 27th May 2004, the learned Arbitrator
noted that as far as Issue 2 was concerned in view of the interim Award dated 9th December 1996 which recorded the concession of CWC that a sum of Rs. 23,24,883 was payable, the only question that remained was of the interest payable. That was decided under Issue 6 in the final Award by holding that BCT was entitled to simple interest at 9% per annum from 31st July 1995 till the date of payment. While rejecting BCT's claim for compensation for loss of business under Issue 4, the learned Arbitrator held that the statement in the testimony of Mr. T.K. Ram that a sum of Rs. 2,23,10,304 was invested on equipment and machinery by BCT was not substantiated by a record of the purchases so made. Therefore, it was difficult to agree that BCT was able to handle the volume of work actually generated. The claim for hike in diesel price under Issue 5 was also rejected by observing that the fact that the initial claim for Rs. 88,12,320 was slashed by BCT to Rs. 59,92,463 made its authenticity 'suspect' and that Clauses XVI and XXII-1 (x) prohibited any price increase.
14. The impugned final Award decided Issues 1, 3 and 7 together. The plea of CWC that these were excepted matters was rejected by the learned Arbitrator who observed that CWC had itself sought a declaratory relief in that regard. It was further observed that BCT had "placed nothing on record" to show similarity in the terms of the contracts between JNPT and CWC on the one hand and the contract between CWC and BCT on the other. It was held that CWC "could impose penalty according to the contract." It was held that the fact that BCT returned the SISUs to the port authorities in road worthy condition to secure the release of Rs. 23,34,883 showed that they did not suffer from any major defects as claimed and seemed to lend support to CWC's contention that they were being used by BCT "for operations not
related to this contract." It was held therefore that the imposition of penalty for delay in movement of containers was justified.
15. The learned Arbitrator observed that despite there being "heavy volumes of correspondence, charts, statements etc.", nothing threw light on the quantum of penalty levied. This led the learned Arbitrator to adopt a "reasonable guess" and grant relief to the extent of 50% of the total amount which worked out to Rs. 7,53,720. Likewise for the delay in de-stuffing the containers, the penalty was restricted to 50% and Rs. 3,59,059 was asked to be refunded by CWC to BCT. It was held that the entire electrical charges claimed by CWC were payable by BCT since it failed to take the initiative to install a sub-meter. As regards deductions for damage to property, the amount payable by BCT was calculated as Rs.2,35,391 and Rs. 1,08,422 which had to be refunded to BCT. The entire sum of Rs. 5,40,000 deducted by CWC towards forklift charges was held to be justified. However the deduction towards miscellaneous items in the sum of Rs. 1,08,819 and Rs. 5,98,926 wrongfully withheld were asked to be refunded to BCT. Under Issue 6, BCT was held entitled to simple interest at 9% per annum on the sums awarded under the final Award as well as on Rs. 23,24,883 awarded in the interim Award from 31st July 1995 till the date of payment. If the awarded sum was not paid within thirty days interest at 12% per annum was payable.
Submissions on behalf of BCT
16. BCT is aggrieved by the impugned final Award to the extent that Issues 4 and 5 have been decided against it and under Issues 1, 3 and 7, the learned Arbitrator held that CWC could validly deduct certain sums as penalty in
terms of the contract.
17. It is submitted by Mr. Atul Y. Chitale, learned Senior counsel appearing for BCT, that the finding of the learned Arbitrator as regards Issues 1, 3 and 7 was erroneous on several grounds. He submitted under Section 74 of the Indian Contract Act 1872 ('CA'), only a sum specified in the contract could be recovered as liquidated damages ('LD') or penalty in the event of breach of contract. Relying on the decision in Fateh Chand v. Balkishan Dass AIR 1963 SC 1405, he submitted that even where a sum was specified, the Court had jurisdiction to award reasonable compensation, subject to a maximum of the sum specified. While Clause XXII (2) (v) and Clause XXII (3) (ix) of the contract provided for penalty to be imposed, there was no sum specified to be recovered as such. Thus the claim for deduction by way of LD could be justified only under Section 73 of the CA, but for doing so CWC had to prove the actual loss suffered by it.
18. Mr. Chitale submitted that the contract between JNPT and CWC dated Nil of 1989 and the contract between BCT and CWC dated 31st May 1989 were back to back contracts. Clauses XXI (1) and XXI (7) of the contract showed that the performance of BCT was dependant on JNPT's ability to generate a certain volume of work. The finding of the learned Arbitrator that BCT's deemed pitiable performance led the JNPT to administer threat for termination of the agreement with the CWC was contrary to JNPT's own administrative reports for the period 1989 to 1993 which showed that the RTGCs were for 63% of the working hours either unavailable or at near break-down stage. In the port users' meetings which were held throughout the contract period, the Chairman of JNPT had stated that they could deliver
import containers only for 3 working days and then again not for 24 hours. The trailers of BCT were detained at JNP-CY for not less than 10 to 12 hours daily on an average. The average movement on a daily basis was only of 60 to 70 TEUs. It is pointed out that on an average 6 to 7 SISU trailers out of the 19 supplied were always in a break-down condition. Therefore, the finding of the learned Arbitrator that the vehicles did not suffer from any major defects, was contrary to the record.
19. Several documents were referred to by Mr. Chitale to show that there were manufacturing defects in the SISU tractors and trailers and CWC also wrote to JNPT "to take back all SISU Tractors Trailers due to their failure to function". He pointed out that the bills for the repairs undertaken to the SISUs by BCT with the promise of reimbursement by CWC were placed on record. He submitted that the delay in delivery of containers and back log was as a result of JNPT's failure to deliver the containers.
Submissions on behalf of CWC
20. Mr. K.K.Tyagi, learned counsel for CWC submitted in reply that the impugned final Award was a reasoned one and called for no interference. Relying on the decisions in The President, Union of India v. Kalinga Construction Co. Pvt. Ltd. AIR 1971 SC 1646 and M/s. Sudarsan Trading Co. v. The Government of Kerala AIR 1989 SC 890 he submitted that the Court would not sit in appeal over the conclusion reached by the learned Arbitrator by re-examining the evidence. The reasonableness of the reasons given by the learned Arbitrator could not be challenged. Relying on the decision in M/s. Hind Builders v. Union of India AIR 1990 SC 1340 he submitted that if there were two possible interpretations it was legitimate for
the learned Arbitrator to accept one and even if the Court felt that the other view was preferable, it would not interfere. Reliance was also placed on the decision in Food Corporation of India v. Joginder Pal Mohinder Pal AIR 1989 SC 1263.
21. Mr. Tyagi submitted that in the present case although the learned Arbitrator had filed the impugned final Award in Court on 29th March 2007, the objections were filed by BCT only on 24th September 2007 and were therefore beyond the period of limitation. He next submitted that the work entrusted to BCT for the movement of containers was pursuant to a contract entered into with CWC after a competitive bidding. It could not be equated with the agreement between CWC and JNPT which was as per the advice of the Ministry. Mr. Tyagi submitted that Clause C (i) to (v) of the Notice inviting Tender ('NIT') read with Clause XV made it clear that there was no assurance held out to BCT by the CWC as to the quantity of work. It was further made clear that any variation of the quantity of work would not entitle the Contractor to claim compensation.
22. According to Mr. Tyagi Clause XXII (2) (v) allowed CWC to levy penalty on the Contractor for failure to perform the obligations under the contract. In any event the power to levy penalty could be inferred from the letters dated 16th August 1991, 19th September 1991, 19th May 1992 and 9th September 1992. The record showed that BCT was unable to move even 100 TEUs from the CY to the CFS and therefore it was plain that BCT was not in a position to fulfil its obligations under the contract. If according to BCT the vehicles supplied by JNPT were defective, the resultant liability could not be that of CWC.
23. As regards escalation, Mr. Tyagi referred to Clause XVI of the contract in terms of which the rates were to remain firm. This was further confirmed by CWC by its letter dated 15th October 1990 which clearly stated that the rate quoted by the Contractor and accepted by the CWC would remain in force during the currency of the contract. Reliance was placed by Mr. Tyagi on the decisions in General Manager Northern Railway v. Sarvesh Chopra (2002) 4 SCC 45, Steel Authority of India Ltd v. J.C. Budharaja, Government and Mining Contractor (1999) 8 SCC 122 and Oil and Natural Gas Corporation v. Wig Brothers Builders and Engineers Private Limited (2010) 13 SCC 377.
24. CWC justified the deductions made by way of penalty by pointing out that a proper show cause notice was issued to BCT on 8th January 1992 and a hearing was also given. There were surveys furnished and the penalty was levied and deducted on actual basis. The deductions were justified in terms of Clause XII of the contract. Reliance was placed on the decisions in M/s. Sudarsan Trading Co. v. The Government of Kerala, M/s. Kwality Manufacturing Corporation v. Central Warehousing Corporation (Order dated 23rd February 2009 in Civil Appeal No. 7121 of 2001), M/s. Forbes Gokak Ltd. v. Central Warehousing Corporation (Order dated 1st February 2010 in OMP 306 of 2000).
Claims within limitation
25. As regards the contention of the CWC that the objections filed were beyond limitation, it is seen that BCT received notice of the filing of the Award on 27th August 2007 at its Mumbai office, from the Registry of this Court. Within 30 days thereafter, BCT filed its objections on 24th September
2007. Therefore, there is no merit in the contention that the objections are barred by limitation.
Decision on Issues 1, 3 and 7
26. The issue relating to validity of the action of the CWC in making deductions from the bills of BCT on the ground of penalty was the subject matter of Issues 1, 3 and 7. One of the central issues was whether CWC was entitled to levy penalty in view of the fact that no penalty was levied on it by JNPT. The contention of BCT was that there was in fact no penalty clause in the contract between CWC and BCT.
27. The learned Arbitrator negatived the plea of BCT by holding that the agreement between the JNPT and CWC on the one hand and CWC and BCT on the other hand was separate and not similar and that BCT had placed "nothing on record to show similarity in their terms and conditions." On the issue whether the contract between JNPT and CWC on the one hand and CWC and BCT on the other were back to back contracts, the learned Arbitrator passed an order on 3rd September 1996 in which he observed:
"there was a separate agreement between the Claimants and the Respondents and it is this that was really relevant to the present proceedings. I did find weight in this plea and accordingly hold that there was a little merit in the Respondents' request for a copy of Contract agreement between CWC and JNP Trust. Anyway, if at the stage of arguments, I find the point being made material for decision in the case, I shall go through this document and decide on the final course of action."
28. The fact is that a copy of the agreement between CWC and JNPT was available in the arbitral record. Clause XXII (2) (v) and XXII (3) (ix) of the contract do not quantify the penalty payable by BCT in the event of breach
of the contract. There is in fact no clause in the contract between BCT and CWC which quantifies either the LD or the penalty. Both the contracts - between JNPT and CWC on the one hand and BCT and CWC on the other - were back to back contracts. The power of CWC to appoint a Contractor, i.e., BCT to undertake the work at the CFS emanated from the authority granted by JNPT under Clause 7 (a) of the agreement between JNPT and CWC which stipulated that JNPT shall provide 20 tractors and 80 trailers required for movement of containers. These were the same tractors and trailers of SISU make provided by CWC to BCT. Further Clause 6 (a) of the contract between JNPT and CWC required about 60,000 TEUs of import and export containers to be handled in the first year and figure was expected to go up in the later years. These worked out to around 5000 TEUs per month. The same requirement was spelt out in the contract between CWC and BCT. Clause XXI (1) and XXI (7) of the contract between CWC and BCT envisaged BCT taking over the loaded containers placed on such vehicles by the operators and JNPT and further that BCT was to arrange to receive export cargo at the CFS in break bulk condition. These clauses showed that the performance of BCT was dependent upon JNPT generating a certain volume of business of containers and handing the same over to BCT. The finding of the learned Arbitrator to the contrary is unsupported by the evidence on record.
29. The other relevant clauses of the contract also did not either permit or quantify the penalty leviable by CWC on BCT for breach of contract. Clause XII talks of the "liability of the Contractor for losses etc. suffered" by the CWC. Sub-clause (a) provided that in the event of any fault or default on the part of the Contractor in providing adequate equipments, vehicles or
personnel or to perform any of the services mentioned in the contract, the Manager CFS Nhava Sheva could in his 'absolute discretion' have the right to recover by way of compensation from the Contractor a sum as deemed fit including making temporary alternate arrangements to cope up with the work at the risk and cost of the Contractor. The Contractor was liable to compensate CWC for the consequential damages at the discretion of the Manager, CFS. On the question whether the Contractor had committed default as well as on his liability to pay compensation, the decision of the Manager CFS was final and binding on the Contractor. Under Clause XII
(b), in case of any damage to the containers, the Contractor was responsible to make good the losses as per the survey report finalised in the presence of the shipping line/shipping agent, the Manager CFS or his authorised representative and the Contractor's representative.
30. Clause XIII provided for set off. It states that if any sum was due and payable to the Contractor (including security deposit refundable to him) it may be appropriated by the CWC and set off against any claim of the CWC for the payment of any sum of money arising out of or under any other contract made by the Contractor with the CWC. Clause XV of the contract stated that the CWC did "not guarantee any definite volume of work or any particular pattern of service at any time or throughout the period of the contract." Further, "the mere mention of any item of work in this contract does not by itself confer a right on the contractor to demand that the work relating to all or any item thereof should necessarily or exclusively be entrusted to them." CWC had the exclusive right to appoint one or more Contractors for all or any of the services and to divide the work as between the Contractors in any manner that CWC might decide initially or any time
during the currency of the contract and no claim was to lie against it by reason of such division of work.
31. Clause XVI states that the Contractor had to perform all the services at the rate quoted by him and accepted by the CWC. Clause XVII provided that payment would be made by the Manager CFS on submission of bills by BCT in triplicate duly supported by work certificates issued by the officer authorised by the Manager CFS. In terms of note (ii) below Clause XVII CWC was not liable to pay any interest "on any bill outstanding for payment for any reasons whatsoever."
32. As explained by the Supreme Court in New India Civil Erectors (P) Ltd. v. Oil and Natural Gas Corporation (1997) 11 SCC 75, "the arbitrator being a creature of the agreement must operate within the four corners of the agreement and cannot travel beyond it. More particularly, he cannot award any amount which is ruled out or prohibited by the terms of the agreement." Consequently, the major premise on which the learned Arbitrator proceeded to decide Issues 1, 3 and 7 in favour of CWC, viz., that CWC was entitled to make deductions by way of penalty was contrary to the clauses of the contract.
33. In the absence of any specific clause quantifying the penalty that could be levied by CWC, or any clause quantifying the sum to be recovered as LD, CWC could have if at all sought to recover LD only under Section 73 of the CA for which the burden of proof was on CWC to show that it had actually suffered damages and loss. In Oil & Natural Gas Corporation Ltd. v. Saw Pipes Ltd. (2003) 5 SCC 705, the legal position was explained as under:
"Under Section 73, when a contract has been broken, the party
who suffers by such breach is entitled to receive compensation for any loss caused to him which the parties knew when they made the contract to be likely to result from the breach of it.
This Section is to be read with Section 74, which deals with penalty stipulated in the contract, inter alia (relevant for the present case) provides that when a contract has been broken, if a sum is named in the contract as the amount to be paid in case of such breach, the party complaining of breach is entitled, whether or not actual loss is proved to have been caused, thereby to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named. Section 74 emphasizes that in case of breach of contract, the party complaining of the breach is entitled to receive reasonable compensation whether or not actual loss is proved to have been caused by such breach. Therefore, the emphasis is on reasonable compensation. If the compensation named in the contract is by way of penalty, consideration would be different and the party is only entitled to reasonable compensation for the loss suffered. But if the compensation named in the contract for such breach is genuine pre-estimate of loss which the parties knew when they made the contract to be likely to result from the breach of it, there is no question of proving such loss or such party is not required to lead evidence to prove actual loss suffered by him."
34. In the instant case, there was no "genuine pre-estimate of loss" in any of the clauses of the contract. Consequently, Section 74 CA had no application. Issues 1, 3 and 7 had to be decided with reference to Section 73 CA. CWC led no evidence to prove the exact losses and damages suffered by it as a result of the alleged breach of the contract by BCT. In the impugned final Award, there is no discussion by the learned Arbitrator either of the evidence or the law as explained in the decisions of the Courts. The distinction between the legal requirements under Sections 73 and 74 CA was not appreciated by the learned Arbitrator. The impugned final Award in respect of Issues 1, 3 and 7 is therefore unsustainable in law.
35. As regards the delay in the movement of import containers, the learned Arbitrator ignored the evidence on record and resorted to a 'reasonable guess'. In para 31 of the final Award the learned Arbitrator observed as under:
"31. Next, the learned Senior Advocate questioned the rationale behind the levy of highest penalty uniformly @ Rs. 300/- for delay in the movement of containers. He argued that the quantum of loss/damage is determined essentially by the extent of delay. He invited my attention to a case, in which delay was only of 10 minutes. He further pointed out that the RTGC would no longer become available by the Respondents once the Port Trust got busy in its operations. Even the movement of this crane from one point to the other would consume normally 90 minutes. This fact stands admitted by the Port Trust. In fact, the Claimants-Corporation wrote to the Port Trust in this behalf. Heavy volumes of correspondence, charts, statements etc. have been placed on record by both the parties. But nothing therein seems to throw light on the quantum of delay in individual cases, in which penalty has been levied. In the absence of this crucial information, I seem to be left with no option except to make reasonable guess in respect of the cases where the penalty imposed has been excessive. This being the position, it would be fair and reasonable to grant relief to the extent of 50% of the total amount of Rs. 15,07,440, i.e., Rs. 7,53,720."
36. Apart from the fact that there was no clause in the contract which quantified the penalty that could be levied, it is apparent from the above extract that the learned Arbitrator ignored the "heavy volumes of correspondence, charts, statements etc." and instead made a "reasonable guess" to grant CWC 50% of the sum claimed for the delay in movement of the containers. The learned Arbitrator ignored the day-wise detailed record of trailer retention produced by Mr. James John. These records showed that RTGCs used for delivery of import container to BCT's trailers and the
export containers downloaded from BCT's trailers worked only for 42% of the working hours and were in a breakdown condition for the rest of the time. The records also showed that BCT's trailers were being detained on an average of 10 to 12 hours at the Import Container Delivery Terminal of JNPT during the entire period of the contract.
37. Ignoring the above evidence the learned Arbitrator granted relief to CWC to the extent of 50% of the total amount of penalty on the basis that BCT had returned the SISUs "in road worthy and working condition" in order "to secure release of Rs. 23,34,883" from CWC. From this, the learned Arbitrator concluded that the vehicles did not suffer from any major defects and further that the SISUs were being used for operation not related to this contract. The said finding is unsupported by any evidence on record.
38. The statement of month-wise physical performance of JNP-CFS showed that the volumes of containers available for movement were hardly sufficient and far below the numbers there were assured at the time of entering into the contract. The learned Arbitrator without discussing any evidence in particular came to the conclusion that 50% of the sum claimed should be allowed. This is an unsatisfactory manner of dealing with specific claims where the parties have led exhaustive evidence to prove their respective cases. It was obligatory on the learned Arbitrator to discuss the evidence in support of his conclusions.
39. The affidavit by way of evidence of Mr. Sameer Parikh read with Annexure A-12 showed that the free time allowed by JNPT for the movement of containers was three days. Although the contract did not
provide for any time limit for carrying out the movement of import containers, CWC arbitrarily fixed the time limit for movement of import containers as within 24 hours of the job order. JNPT's instructions for container delivery themselves stipulated that for the first three days, storage was free and only from the fourth day ground rent was payable if delivery was not in the free period of three days. CWC failed to produce any proof to show delay in movement of containers beyond the free period of three days and any consequent loss to CWC.
40. On the aspect of delay in de-stuffing of containers, the learned Arbitrator made no mention of the written submissions of BCT which referred to several documents on record. In the circumstances, the learned Arbitrator was not justified in adopting a 'reasonable guess' in deciding the issue. There was no proof of the delay on the part of BCT in de-stuffing the containers. For instance the learned Arbitrator ignored the statement enclosed at page 574-582 of Volume VII showing that de-stuffing was carried out within three working days and therefore, no loss was suffered by the CWC.
41. As regards the electrical charges, there was no clause in the Contract permitting recovery. It appears that under the relevant electricity laws, only the JNPT or CWC could have applied for a sub-meter. The upholding of the deduction of the electricity charges was clearly contrary to the clauses of the contract. The learned Arbitrator again made no reference to the unrebutted evidence of Mr. Sameer Parikh, an electrical engineer and the Regional Manager-in-charge at the relevant time. He produced the unit consumption pattern of electrical equipments published by BES&T. In terms of the
relative electricity laws prevalent at the place where the CFS was located it was only the owner of the facility who could apply for a sub-meter. The decision of the learned Arbitrator in this regard is unsupported by the evidence on record. There was nothing on record to show that the electrical charges were worked out by the Electrical Engineer of CWC in consultation with BCT.
42. As regards the deductions towards damage to property, containers and cargo, again the learned Arbitrator has not explained the basis on which he has allowed the claim to the extent of Rs.2,35,391 and required refund of only Rs.1,08,422 to the Contractor. As noticed earlier, CWC had to prove the loss relating to damage to property. The evidence of Mr. T.K. Ram revealed that CWC did not furnish the date and timing when the vehicles/trailers were alleged to have been damaged. Although, in the order dated 24th and 25th July 2001, the learned Arbitrator observed that he would consider the question of permitting additional documents to be filed by CWC at a later stage, in the final Award he failed to consider the objections of BCT and allowed the claim of the CWC by relying on the additional documents. These documents included proof of payments allegedly made by CWC to third parties. No opportunity was given to BCT to counter those additional documents. It was improper for the learned Arbitrator to have allowed those additional documents to be placed on record by CWC.
43. On the question of forklift hiring charges, no reasons have been given by the learned Arbitrator for allowing the claim of CWC in the sum of Rs.5,40,000. While considering Ex. C-15 which was a letter written by BCT at the time of taking over the forklift, he failed to take note of the letter dated
24th September 1990 (Ex. C-26) in which BCT made a complaint that the forklift could be operated only for three days. The ignoring of materials and evidence by the learned Arbitrator constitutes legal misconduct as explained in K.G. Hiranandani v. Bharat Barrel and Drum Mfg. Co. Pvt. Ltd. AIR 1969 Bom 373.
44. It is accordingly held that the findings in the impugned final Award as regards Issues 1, 3 and 7 are unsustainable in law and the impugned final Award to that extent is liable to be set aside.
Issue 4
45. Issue 4 was whether BCT was entitled for loss of profit in the sum of Rs.7,27,23,960. Mr. Chitale, learned Senior counsel appearing for BCT, has placed considerable reliance on the decisions of the Supreme Court in A.T. Brij Paul Singh v. State of Gujarat (1984) 4 SCC 59 and Dwaraka Das v. State of M.P. (1999) 3 SCC 500.
46. There are no reasons whatsoever given by the learned Arbitrator for rejecting the above claim of BCT. In para 21, the learned Arbitrator simply stated as under:
"21. In the light of the above facts, it appears difficult to agree with the view that the Respondents were able to handle the volume of work as actually generated. The learned Senior Advocate for the Respondents took all pains to highlight that the Respondents expected to make reasonable profit, which was denied to them. In support, he quoted the decisions of the Supreme Court in A.T. Brij Paul Singh Vs. State of Gujarat (reported in (1984) 4 SCC 59) and Dwarka Das Vs. State of M.P. (reported in (1993) 3 SCC 500). But the Claimants' contentions, raised above, which seem to possess substance
cannot, in my considered view, be ignored. There thus appears little justification for conceding the Respondents' claim for compensation. Accordingly, it is rejected."
47. The learned Arbitrator chose not to discuss the evidence led by BCT to substantiate its claim for losses. BCT had relied on a large volume of documents to show that the RTGCs were not available for the entire period of the contract; trailers of BCT were detained for long periods at the JNPT- CY; there was an absence of checkers, supervisors, gantry operators and further there were various other port related problems that resulted in heavy pendency and back-log of container delivery. None of the above evidence was discussed by the learned Arbitrator. He also appears to have ignored the written submissions of BCT in this regard.
48. The question whether the disclaimer in Clause XV of the contract that no definite volume of work was guaranteed by CWC, and therefore did not give BCT the right to any legitimate expectation that JNPT would provide 5000 TEUs a month, also required an examination by the learned Arbitrator of the relevant clauses in light of the evidence on record. It also hinged on a number of other factors. For instance, the impact of the shifting of the export CFS to Kalamboli which was 24 km. away from JNP-CFS, as compared to the original contract which was to be performed at JNP-CFS which was only 8 km away from JNP-CY was to be examined. The additional affidavit of Mr. James John shows that there was loss of man hours due to non availability of RTGCs. The JNPT Administrative Reports for the years 1989-1990 till 1992-1993 and the Minutes of Port Users meeting held on 21st October 1992, 17th March 1993 and 21st April 1993 were also part of the evidence in support of BCT's claims. However, there is no discussion of the
above evidence in the impugned final Award.
Issue 5
49. Issue 5 was about the claim for compensation by BCT in the sum of Rs.88,12,320 on account of hike in the price of diesel. The claim was held to be 'suspect' only because it was later limited by BCT to Rs.59,92,463. It was explained by Mr. Chitale that the claim was reduced only because BCT could not trace all the bills from its record. He referred to the statement of the Finance Minister that the increase of the price of diesel by 25% was due to Gulf surcharge. The affidavit of Mr. T.K. Ram set out a table detailing the escalated rate paid by BCT on diesel. The contention of BCT was that Clause XVI of the contract does not exclude the payment of escalation due to increase in the administered price increase of HSD oil and diesel.
50. In Tarapore and Company v. Cochin Shipyard Ltd., Cochin (1984) 2 SCC 680, it was acknowledged that if the rate initially quoted by a Contractor becomes irrelevant due to subsequent price escalation, the Contractor's claim as a result thereof could not be turned down on account of the absence of an escalation clause. Observations of a similar nature were made in K.N. Sathyapalan v. State of Kerala (2007) 13 SCC 43 and Food Corporation of India v. A.M. Ahmed & Co. (2006) 13 SCC 779. The 80% increase in the price of petroleum products was beyond the control of the parties and this was a factor that had to be considered by the learned Arbitrator in light of the law explained in the above decisions.
51. In the considered view of the Court, the decision on Issues 4 and 5
suffers from patent errors and is also vitiated by the failure of the learned Arbitrator to examine the material evidence on record. It warrants a fresh determination of those Issues. As a corollary Issue 6, viz., whether BCT is entitled to interest for the pre-reference, pendente lite and post-Award periods on the sums claimed under Issues 4 and 5 will also have to be decided afresh. Consequently, the claims of BCT under Issues 4, 5 and 6 require to be remitted to the Arbitrator for a fresh Award.
Consequential directions
52. In the absence of information whether the learned Arbitrator who passed the final Award dated 27th May 2004 is available, this Court considers it appropriate to refer Issues 4, 5 and 6 for a fresh arbitration to Justice Mohammed Shamim, a former judge of this Court, r/o A-2, Mod Apartments, Vasundhara Enclave, New Delhi-110096 (Mob. 9971156991). The arbitration will take place under the aegis of the Delhi High Court Arbitration Centre ('DHCAC'). The fees of the learned Arbitrator will be in terms of the DHCAC (Arbitrators' Fees) Rules. Issues 4, 5 and 6 will be decided afresh on the basis of the existing pleadings and evidence and the parties will not be permitted to lead fresh evidence or file any further documents. However, they will address arguments and file their respective written submissions within the time fixed for that purpose by the learned Arbitrator. An endeavour will be made by the learned Arbitrator to conclude the proceedings and pass a fresh Award in respect of Issues 4 and 5 within a period of four months after the first sitting after remand.
53. Consequently, it is directed as under:
(i) The impugned final Award dated 27th May 2004 of the sole
Arbitrator in respect of Issues 1, 3 and 7, to the extent it holds the deductions made by the CWC from BCT to some extent justified, is hereby set aside.
(ii) BCT is held entitled to be refunded the entire amount deducted by CWC together with interest. Accordingly, it is directed that after accounting for the payments already made by CWC to BCT, CWC will, within a period of eight weeks, pay BCT the balance amount in respect of such deductions wrongly made together with simple interest at 9% per annum from 31st July 1995 till the date of payment, failing which CWC will pay BCT simple interest at 12% per annum on the said sum for the period of delay.
(iii) Issues 4, 5 and 6 are remitted to Justice Mohammed Shamim, a former judge of this Court, for a fresh Award in terms of para 52 of this judgment. The arbitral record will be handed over forthwith by the Registry to the DHCAC which will in turn place it before Justice Mohammed Shamim without delay. If any of the parties are aggrieved by the fresh Award, they can seek appropriate remedies as may be available to them in accordance with law.
(iv) The impugned final Award in respect of arbitration fees, stamp duty and costs as set out in para 41 of the impugned final Award, is upheld.
54. The impugned final Award dated 27th May 2004, as modified above, is made rule of the Court. The decree sheet be drawn up accordingly. The suit is disposed of.
55. A copy of this judgment be communicated to Justice Mohammed Shamim as well as Co-ordinator, DHCAC forthwith.
S. MURALIDHAR, J.
SEPTEMBER 26, 2012 bs/rk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!