Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Vijay Kumar Goel vs Delhi Jal Board & Anr.
2012 Latest Caselaw 5305 Del

Citation : 2012 Latest Caselaw 5305 Del
Judgement Date : 5 September, 2012

Delhi High Court
Vijay Kumar Goel vs Delhi Jal Board & Anr. on 5 September, 2012
Author: S. Muralidhar
          IN THE HIGH COURT OF DELHI AT NEW DELHI

                               O.M.P. 253 of 2004

                                               Reserved on: August 6, 2012
                                             Decision on: September 5, 2012

        VIJAY KUMAR GOEL                            ..... Petitioner
                     Through: Mr. Harish Malhotra, Sr. Advocate
                              with Mr. R.K. Modi, Advocate.

                      versus

        DELHI JAL BOARD & ANR.                              ..... Respondents
                      Through: None.


        CORAM: JUSTICE S. MURALIDHAR

                               JUDGMENT

05.09.2012

1. The challenge in this petition under Section 34 of the Arbitration and Conciliation Act, 1996 ('Act') is to an Award dated 7th May 2004 passed by the sole Arbitrator (Respondent No.2 herein) in the dispute between the Petitioner and Respondent No.1 Delhi Jal Board ('DJB') arising out of an award by the DJB in favour of the Petitioner of the work of providing and laying new sewer line in place of existing sewer line in Sectors IX and XIII, Rohini Blocks - D, E, F, G and H by a letter dated 12th February 1998.

2. The scheduled date of the commencement of the work was 15th March 1998. It was to be completed within a period of 10 months ending on 14th January 1999. According to the Petitioner, the contract period expired on 14th January 1999 without the Petitioner even being allowed to commence the work as the DJB failed to make available the required site, drawings and designs and even the stipulated material. It is stated that on 8th January

1999, the DJB on its own granted provisional extension of time ('EoT') for completion of the work up to 30th April 1999 without prejudice to the right of the DJB to levy liquidated damages ('LD'). The Petitioner states that by a letter dated 19th January 1999 it wrote to the DJB making it clear that since the DJB had failed to adhere to the terms and conditions of the contract and the original contract period had also expired, the Petitioner was not interested in the EoT and its accounts may be finalized. It is stated that without reference to this letter, the DJB again wrote to the Petitioner on 19th March 1999 stating that the time had been extended up to 30th April 1999. By a further letter dated 23rd April 1999, the DJB on its own granted another EoT up to 30th June 1999. By a further letter dated 17th June 1999, the fourth EoT was granted up to 31st October 1999.

3. The Petitioner states that despite his request for closure of the contract, by a letter dated 27th July 1999 the DJB served a notice on the Petitioner asking him to show cause why LD should not be levied. On 11th August 1999, the Petitioner replied pointing out that he had never applied for the EoT and that the EoTs unilaterally granted by the DJB did not bind the Petitioner. Thereafter the DJB levied LD on the Petitioner to the tune of 10% of the contract value and issued another show cause notice dated 25th August 1999 as to why the work should not be executed through some other Contractor at the risk and cost of the Petitioner. By his letter dated 31st August 1999 the Petitioner disputed the right of the DJB to do so. By a letter dated 8th October 1999 the DJB rescinded the contract. By a letter dated 24th March 2000, the DJB required the Petitioner to show cause as to why he should not be debarred from tendering further in DJB. By a letter dated 4th September 2000, the DJB debarred the Petitioner for applying for tenders for a period of 3 years.

4. The disputes between the parties were referred to the sole Arbitrator

who gave the impugned Award dated 7th May 2004. However, the impugned Award makes no reference to the application by the Petitioner challenging the jurisdiction of the learned Arbitrator. The Petitioner also filed OMP No. 19 of 2003 challenging the appointment of Respondent No.2 as sole Arbitrator which was later dismissed as withdrawn since the impugned Award had been passed by then.

5. The challenge to the impugned Award is on the ground that the learned Arbitrator has failed to deal with the application filed by the Petitioner challenging the jurisdiction of the learned Arbitrator. A perusal of the arbitral record shows that there indeed was such an application made by the Petitioner. It has, however, not been dealt with by the learned Arbitrator in the impugned Award. Without dealing with the said objections, the learned Arbitrator dismissed all the claims of the Petitioner and allowed the counter-claim of the DJB to the extent of Rs. 16,99,556. Even the issues framed by the learned Arbitrator overlook the fact that the Petitioner had filed an application questioning the jurisdiction of the learned Arbitrator. This by itself constitutes sufficient ground to set aside the impugned Award. It is not necessary therefore to examine the correctness of the impugned Award as regards the individual items of claims and counter-claims.

6. With the aforementioned observations, the impugned Award is set aside. The petition is allowed, but in the circumstances, with no order as to costs.

S. MURALIDHAR, J.

September 5, 2012 hk

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter