Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Awasthi Construction Co. vs Govt Of Nct Of Delhi & Anr.
2012 Latest Caselaw 6210 Del

Citation : 2012 Latest Caselaw 6210 Del
Judgement Date : 16 October, 2012

Delhi High Court
Awasthi Construction Co. vs Govt Of Nct Of Delhi & Anr. on 16 October, 2012
Author: Rajiv Sahai Endlaw
          *IN THE HIGH COURT OF DELHI AT NEW DELHI

%                                 Date of decision: 16th October, 2012

+                            LPA No.701/2012

      AWASTHI CONSTRUCTION CO.                ........ Appellant
                  Through: Mr. R. Rajappan,Adv. with Ms. Rajni,
                           Adv.

                                  Versus

      GOVT OF NCT OF DELHI & ANR.                       ........ Respondents

Through: None.

CORAM :-

HON'BLE THE CHIEF JUSTICE HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW

RAJIV SAHAI ENDLAW, J

1. This intra court appeal impugns the order dated 22 nd August, 2012 of

the learned Single Judge of dismissal of WP(C) No. 5117/2012 preferred by

the appellant.

2. The said writ petition was preferred by the appellant assailing the

order dated 20th November, 2009 of an Arbitral Tribunal of terminating

arbitral proceedings in exercise of powers under Section 25(a) of the

Arbitration and Conciliation Act, 1996, upon the failure of the appellant to

appear therein or to submit its statement of facts/claim inspite of notices

dated 2nd September, 2009 and 12th October, 2009 and the latter of which

had informed the appellant that upon its failure to submit the statement of

facts/claims by 15th November, 2009 without any valid reason, the

proceedings shall be terminated without further notice. The said arbitral

proceedings had arisen out of a work order placed by the Government of

NCT of Delhi (GNCTD) on the appellant and which work order provided for

resolution of disputes arising therefrom by arbitration of an arbitrator to be

appointed by the GNCTD. It is the claim of the appellant, that the GNCTD

failed to provide the work site or perform its other obligations under the

work order within the stipulated time leading the appellant to request for

closure of the contract; that the GNCTD in compliance of the said request

closed the contract and though returned the earnest money deposit and

performance guarantee of the appellant but denied the claim made by the

appellant for loss of profit, damages and interest and which led the appellant

to invoke the arbitration clause; that the Arbitral Tribunal comprising of the

sole arbitrator nominated by the GNCTD though claimed to have issued the

notices aforesaid to the appellant but none of the said notices were received

by the appellant; that the appellant upon learning of termination of the

arbitration proceedings approached the GNCTD averring that it had not

received the notices and hence had no occasion to appear before the Arbitral

Tribunal and requested for appointment of another arbitrator. The GNCTD

however declined to substitute another arbitrator in place of the Arbitral

Tribunal earlier appointed. The appellant, through the medium of the Right

to Information Act, 2005, claims to have learnt that the notices aforesaid

purportedly sent by the Arbitral Tribunal though intended to be sent by

registered post, were sent by ordinary post. The appellant further claims that

upon receipt of the said information the appellant again approached the

GNCTD for directing the Arbitral Tribunal to resume the arbitral

proceedings but the said request was also declined on 4 th May, 2010.

3. With the aforesaid case the writ petition impugning the order dated

20th November, 2009 of the Arbitral Tribunal was filed and seeking further

direction to the GNCTD to appoint another Arbitrator.

4. The learned Single Judge dismissed the writ petition holding the same

to be barred by laches, observing that the writ petition had been filed after

more than two years and four months of the last communication from the

GNCTD and after nearly three years of the admitted knowledge on 9th

December, 2009 of the order dated 20th November, 2009 of the Arbitral

Tribunal. It is further observed by the learned Single Judge that the notices

sent by the Arbitral Tribunal were at the same address as the address given

by the appellant in the writ petition and there is no reason to believe that

these notices as well as the order dated 20th November, 2009 of the Arbitral

Tribunal were not dispatched to the appellant. The delay in approaching the

Court was held to be unexplained.

5. Though the writ petition was dismissed on the aforesaid grounds but

the learned Single Judge without expressing any final opinion has also

expressed doubts as to the very maintainability of the writ petition and as to

the judgment of a Single Judge of the Patna High Court in Senbo

Engineering Limited v. State of Bihar AIR 2004 Patna 33 on which

reliance was placed by the appellant in support of the maintainability of the

writ petition against the order of the Arbitral Tribunal.

6. The appellant in this appeal contends that there was no undue delay in

filing the writ petition inasmuch as the appellant, even after receipt of the

communication dated 4th May, 2010 (supra) was pursuing with the officers

of the GNCTD. It is further contended that no remedy is available against

an order of the arbitral tribunal under Section 25(a) since the same is not an

award as contemplated in Section 32 of the Act and irreparable injury is

being caused to the appellant.

7. We, as appellate Bench, see no reason to interfere with the discretion

exercised by the learned Single Judge in exercise of powers under Article

226 of the Constitution of India in holding the petition to be barred by

laches. Though it is vaguely suggested that the appellant even after 4 th May,

2010 was pursuing with the officers of the GNCTD but there is nothing to

substantiate the same. Not a single letter has been written by the appellant

after 4th May, 2010 and after a silence of two years and four months, the

writ petition was filed on 14th August, 2012. Even if it were to be believed

that the appellant was personally pursuing in the office of the GNCTD, the

same will be of no avail. The GNCTD had unequivocally vide its letter

dated 4th May, 2010 informed the appellant that its request for substitution of

the arbitrator could not be acceded to. It is the settled principle of law (see

Rabindranath Bose v. Union of India (1970) 1 SCC 84, Karnataka Power

Corporation Ltd. v. K. Thangappan (2006) 4 SCC 322 and Shankara

Cooperative Housing Society Limited v. M. Prabhakar (2011) 5 SCC 607)

that mere repeated reminders cannot keep the lis alive especially in the

absence of any assurance having been meted out that the matter was under

consideration. It cannot be lost sight of, that according to the appellant

himself the contract was closed on 20th June, 2008. The claim if any for loss

of profits and damages arising therefrom had to be made within three years

thereof. Though the said claim was made and Arbitral Tribunal appointed

but its proceedings terminated as aforesaid. The writ petition was filed more

than four years after the contract was closed. A clear case of the appellant

having by its conduct conveyed that it was no longer interested in pursuing

the matter is made out and no illegality has been committed by the learned

Single Judge in not disturbing the quietus which the appellant by its conduct

had allowed the matter to attain.

8. We have also drawn the attention of the counsel for the appellant to

the judgment of the Supreme Court in S.B.P. & Co. vs. Patel Engineering

Ltd. (2005) 8 SCC 618 in paragraphs 45 and 46 whereof it has been held as

under:

"45. It is seen that some High Courts have proceeded on the

basis that any order passed by an arbitral tribunal during

arbitration, would be capable of being challenged under

Article 226 or 227 of the Constitution. We see no warrant for

such an approach. Section 37 makes certain orders of the

arbitral tribunal appealable. Under Section 34, the aggrieved

party has an avenue for ventilating his grievances against the

award including any in-between orders that might have been

passed by the arbitral tribunal acting under Section 16 of the

Act. The party aggrieved by any order of the arbitral tribunal,

unless has a right of appeal under Section 37 of the Act, has to

wait until the award is passed by the Tribunal. This appears to

be the scheme of the Act. The arbitral tribunal is after all, the

creature of a contract between the parties, the arbitration

agreement, even though if the occasion arises, the Chief

Justice may constitute it based on the contract between the

parties. But that would not alter the status of the arbitral

tribunal. It will still be a forum chosen by the parties by

agreement. We, therefore, disapprove of the stand adopted by

some of the High Courts that any order passed by the arbitral

tribunal is capable of being corrected by the High Court under

Article 226 or 227 of the Constitution. Such an intervention by

the High Courts is not permissible.

46. The object of minimizing judicial intervention while the

matter is in the process of being arbitrated upon, will certainly

be defeated if the High Court could be approached under

Article 227 or under Article 226 of the Constitution against

every order made by the arbitral tribunal. Therefore, it is

necessary to indicate that once the arbitration has commenced

in the arbitral tribunal, parties have to wait until the award is

pronounced unless, of course, a right of appeal is available to

them under Section 37 of the Act even at an earlier stage."

In view of the aforesaid dicta of the Supreme Court, the doubts

expressed by the learned Single Judge as to the very maintainability of the

writ petition against the order of the Arbitral Tribunal are well placed.

9. As far as the judgment of the High Court of Patna relied upon by the

appellant is concerned, the same merely follows the judgment of a Single

Judge of the Bombay High Court in Anuptech Equipments Private Ltd. v.

Ganpati Co-operative Housing Society Ltd. AIR 1999 Bombay 219. The

reasoning which prevailed with the Bombay High Court, can be analyzed as

under:

A. That the Act uses three different expressions i.e. arbitral

award, order and decision, with remedies thereagainst

provided in Section 11(7), Section 13(3), Section 14(2),

Section 16(5), Section 34 and Section 37(2).

B. No remedy had been provided against certain orders of the

arbitral tribunal and one instance whereof was an order

under Section 25(a) of the Act.

C. Section 5 of the Act prohibits intervention in arbitral

process, ruling out approaching the Civil Courts against

such orders.

D. The remedy under Section 34 against such order is also not

available, being available only against an award or an

interim award.

E. That for an order to be an award, it must be akin to a decree.

F. An order under Section 25(a) terminating the proceedings

for default in filing a statement of claim could not be treated

as an award.

G. That if such orders were to be read as an award, it would

create an anomaly inasmuch as termination can happen

under Section 32(2) or under Section 16 also and remedy of

appeal is provided whereagainst, indicating that order of

termination of proceeding is different from an award.

H. That while under Section 31, an award is required to state

reasons, an order under Section 25(a) may be without any

reason.

I. Finding no remedy available against such an order, it was

held that the jurisdiction under Article 226 available against

any person or authority could be invoked against an order

under Section 25(a) of the Act.

10. Though the Patna High Court in Senbo Engineering Ltd. (supra)

merely followed the Bombay High Court in holding the writ petition to be

maintainable but also examined, whether the arbitral tribunal has the power

and authority to recall its earlier order terminating the proceedings and

following the judgments holding the Adjudicator under the Industrial

Disputes Act, 1947 to be having such powers, held that the arbitral tribunal

has the power of procedural review and authority to recall, on sufficient

cause being shown, an order terminating the proceedings under Section

25(a).

11. We may notice that a Single Judge of this Court in Indian Oil

Corporation Ltd. v. ATV Projects India Ltd. 112 (2004) DLT 701also held

a writ petition to be maintainable against an order under Section 25(a). The

bar of Section 5 was held to be applicable only when there is a live arbitral

proceeding and not available where arbitral proceedings have terminated. It

was further held that the arbitral tribunal on such termination of the

proceedings becomes functus officio and cannot review its order.

LPA No. 862/2004 against the said judgement of the learned Single Judge is

however pending consideration.

12. We may also notice that the same learned Judge who sitting in

Bombay High Court had pronounced the judgment in Anuptech Equipments

Private Ltd., sitting as the Chief Justice of High Court of Allahabad, in

S.K. Associates v. Indian Farmer and Fertilizers Cooperative Ltd.

MANU/UP/2357/2010, reiterated that an arbitral tribunal would be such a

„person‟ to whom a writ could go under Article 226 of the Constitution of

India and that due to the non availability of a remedy to an aggrieved person,

held the remedy of Article 226 to be available. Though the observations

aforesaid of the Supreme Court in S.B.P. & Co. (supra) were noted but were

held to not apply to termination of proceedings under Section 25(a). It was

further held that, termination of proceedings if does not result in an award,

though cannot give rise to a challenge under Section 34 but if the claim is

within limitation it is open to a party to apply afresh.

13. Notice may also be taken of the dicta of another Division Bench of the

Bombay High Court in Rashtriya Chemical Fertilizers Ltd. v. J.S. Ocean

Liner Pte. Ltd. MANU/MH/0355/2010 though holding the writ remedy to

be available, but to be confined to minimum and to be exercised in very

exceptional and deserving cases.

14. The High Courts of Bombay, Allahabad and Patna have held the writ

remedy to be available only for the reason of no other remedy being

available to a party aggrieved from an order under Section 25(a). The Patna

High Court however held that, notwithstanding the arbitral proceedings

having been closed, the remedy of approaching the arbitral tribunal is

available and further held the arbitral tribunal, upon being satisfied with the

sufficiency of the cause for default given, is empowered to set aside the

dismissal in default. It was however not considered that if such remedy of

approaching the arbitral tribunal is available, the writ remedy could not be

justified on the ground of „no remedy‟.

15. The first question which thus according to us needs to be answered is,

whether the remedy of approaching the arbitral tribunal for review/recall of

termination of proceedings is available, inasmuch as the only consideration

which has prevailed in the judgements aforesaid for holding the writ remedy

to be available is that a party cannot be left remediless. If the remedy of

approaching the arbitral tribunal is available, the said reasoning would

disappear.

16. Though the remedy of review has in State of Arunachal Pradesh v.

Damani Construction Co. (2007) 10 SCC 742 been held to be not available

to an arbitral tribunal and it is otherwise a settled principle that the power of

review is not an inherent power and must be conferred by law either

expressly or by implication (and of which there is no indication in the

Arbitration Act) but the Supreme Court in Grindlays Bank Ltd. v. CGIT

1980 Supp SCC 420 followed in Kapra Mazdoor Ekta Union v. Birla

Cotton Spg. And Wvg. Mills Ltd. (2005) 13 SCC 777 though in the context

of Industrial Adjudicator, carved out a difference between a procedural

review and a review on merits. It was held that procedural review is inherent

or implied in a Court or a Tribunal, to set aside a palpably erroneous order

passed by it under a misapprehension. On the contrary, a review on merits is

for correction of error of law apparent on the face of the record. The law that

there is no power to review unless the statute specifically provides for it, was

held to be applicable to review on merits and not to a review sought due to a

procedural defect. It was held that such procedural defect or inadvertent

error must be corrected ex debito justitiae to prevent the abuse of process

and such power inheres in every Court or Tribunal. Cases where a decision

is rendered by the Court or a quasi judicial authority without notice to the

opposite party or under a mistaken impression that notice had been served

upon the opposite party were held to be falling in the category where the

power of procedural review may be invoked. It was held that the party

seeking such review has to establish that the procedure followed by the

Court or the quasi-judicial authority suffered from such illegality that it

vitiated the proceedings and invalidated the order made therein inasmuch as

the opportunity of hearing was denied without the fault of that party. The

Supreme Court held that in such cases the matter has to be re-heard in

accordance with the law without going into the merits of the order passed

and the order is liable to be recalled and reviewed not because it is erroneous

but because it was passed in a proceeding which was itself vitiated by an

error of procedure or mistake. It was yet further held that once it is

established that the party was prevented from appearing at the hearing due to

sufficient cause, the matter must be re-heard and decided again. It is

important to at this stage highlight that the Supreme Court in Damani

Construction Co. (supra) was concerned with review of an award and which

power of "review on merit" was held to be not vested in the arbitral tribunal.

17. We may in this regard also notice that the legislature, in Section 25,

has not provided for termination of proceedings automatically on default by

a party but has vested the discretion in the arbitral tribunal to, on sufficient

cause being shown condone such default. We are of the view that no

distinction ought to be drawn between showing such sufficient cause before

the proceedings are terminated and after the proceedings are terminated. If

the arbitral tribunal is empowered to condone default on sufficient cause

being shown, it maters not when the same is shown. It may well nigh be

possible that the sufficient cause itself is such which prevented the party

concerned from showing it before the proceedings terminated. It would be a

pedantic reading of the provision to hold that the arbitral tribunal in such

cases also stands denuded. Once the legislature has vested the arbitral

tribunal with such power, an order of termination cannot be allowed to come

in the way of exercise thereof.

18. There is another reason for us to hold so. The emphasis of the

Arbitration Act is to provide an alternative dispute resolution mechanism.

The provisions of the Act ought to be interpreted in a manner that would

make such adjudication effective and not in a manner that would make

arbitration proceedings cumbersome. A view that the arbitral tribunal is

precluded, even where sufficient cause exists, from reviving the arbitral

proceedings and the only remedy available to a party is a writ petition and

which remedy is available only in the High Court often situated at a distance

from the place where the parties are located, would be a deterrent to

arbitration. It is also worth mentioning that Section 19(2) of the Act permits

the parties to agree on the procedure to be followed by the arbitral tribunal.

The parties may, while so laying down the procedure, provide for the

remedy of review/revival of arbitral proceedings and which agreement

would be binding on the arbitral tribunal. If the arbitral tribunal in such a

situation would be empowered to, on sufficient cause being shown, revive

the arbitral proceedings, we see no reason to, in the absence of such an

agreement hold the arbitral tribunal to be not empowered to do so. If it were

to be held that such power of review/recall is not available to an arbitral

tribunal, the arbitral tribunal would not be competent to set aside an order

under Section 25(b) also, compelling the respondent against whom

proceedings have been continued, to file a writ petition, making the

continuation of proceedings before the arbitral tribunal a useless exercise.

19. Before parting with the said line of reasoning, the consequences of the

arbitral tribunal entertaining such procedural review may also be discussed.

If the Arbitral Tribunal finds sufficient cause and restores the arbitral

proceedings, the challenge to such order of restoration would lie along with

challenge to the award itself if against such aggrieved party. However if the

arbitral tribunal does not accept as sufficient, the cause furnished for default,

the arbitral tribunal would necessarily give reasons therefor within the

meaning of Section 31 and such order of the Arbitral Tribunal would

definitely constitute an award remedy whereagainst would be available

under Section 34 of the Act. The definition in Section 2(1)(c) of the Act of

an "arbitral award" is an inclusive one i.e. of the same including an interim

award; else an arbitration award is not defined. However, sub-Section (1) of

Section 32 provides for termination of arbitral proceedings either by an

arbitral award or by an order of the arbitral tribunal under sub-Section (2) of

Section 32. An order of dismissal of an application for review/recall of an

order under Section 25(a) does not fall under any of the clauses in sub-

Section (2) of Section 32. The same thus has to necessarily fall within the

meaning of award.

20. We are further of the view that the proceedings under the Arbitration

Act cannot at all times be viewed through the prism of CPC. The Act

equates the award to a „decree‟ only for the purposes of the enforcement

thereof under Section 36 and our concepts and terminology of a suit cannot

otherwise be applied to arbitration proceedings. The Supreme Court in

Paramjeet Singh Patheja v. ICDS Ltd. (2006) 13 SCC 322 held that the

legal fiction of equating the award to a decree is for the limited purpose of

enforcement and not intended to make an award a decree for all purposes.

Ordinarily even the default termination order under Section 25(a) would be

an award, with the remedy however available to the party of approaching the

arbitral tribunal with sufficient cause for setting aside of the default

termination order. We may in this regard notice that Section 34 allows an

arbitral award to be set aside when a party was under some incapacity or

when proper notice of the arbitral proceedings was not served or when the

party was otherwise unable to present his case. The said grounds for setting

aside would be invoked only if orders as under Section 25(a) were to be an

award and there would have been no occasion for the legislature to provide

such grounds under Section 34 if default orders were not to be an award.

The same also follows from sub-Section (4) of Section 34 whereunder, upon

challenge under Section 34 being made to such termination, the Court has

been empowered to relegate the parties to the arbitral tribunal. We see no

reason to not hold an order under Section 25(a) to be an award merely

because the remedy of appeal against orders of terminations under Section

16(2) & (3) has been provided. Further, the order under Section 25(a),

stating default on the part of the party, would satisfy the requirement of the

award to contain reasons. Moreover, merely because the arbitral tribunal

fails to give any reasons cannot be a ground for making its orders

unassailable under Section 34.

21. It cannot be lost sight of that though in the present case one of the

contracting parties is Government but it may not always be so. The law of

arbitration in the Act is the same, whether the contracting parties are

Government/State within the meaning of Article 12 of the Constitution of

India or private parties. What has been held by the Bombay, Patna and the

Allahabad High Courts would equally apply to arbitration between the

private parties and would tantamount to the jurisdiction under Article 226

being invoked against such private arbitrators and the parties. We are in the

present state of affairs not prepared to hold so especially when in our view

the remedy within the Act is available. In this regard it may be noticed that

the Madras High Court in Mangayarkarasi Apparels P. Ltd. v. Sundaram

Finance Ltd. MANU/TN/0504/2002 has disagreed with Anuptech

Equipments Private Ltd. and held that the arbitral tribunal is not "other

authority" within the meaning of Article 226 and writ remedy against the

orders of the arbitral tribunal is not available.

22. The appellant in the present case did not approach the Arbitral

Tribunal and kept approaching the GNCTD which under the contract was

the party vested with the power to appoint the arbitrator. However GNCTD

had already exercised such power by appointing an arbitrator and it is not

open to the parties to upon such default closure again approach the

appointing authority for appointment of an arbitrator. If that were to be

permitted, it may become a tool of harassment and may render the

proceedings pursuant to the earlier request for appointment redundant. We

therefore, besides agreeing with the reasoning given by the learned Single

Judge, further hold the writ petition filed by the appellant to be not

maintainable.

The appeal is accordingly dismissed. No costs.

RAJIV SAHAI ENDLAW, J

CHIEF JUSTICE OCTOBER 16, 2012 „M‟

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter