Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Delhi Development Authority vs M/S Harcharan Dass Gupta & Ors.
2012 Latest Caselaw 6083 Del

Citation : 2012 Latest Caselaw 6083 Del
Judgement Date : 10 October, 2012

Delhi High Court
Delhi Development Authority vs M/S Harcharan Dass Gupta & Ors. on 10 October, 2012
Author: V. K. Jain
       *       IN THE HIGH COURT OF DELHI AT NEW DELHI

%                                     Date of Decision: 10.10.2012

+      CS(OS) No. 1336/2008


       DELHI DEVELOPMENT AUTHORITY                             ..... Plaintiff
                            Through:               Mr. Rakesh Mittal, Mr. Rajesh
                                                   Kumar Verma, Advocates
                   versus


    M/S HARCHARAN DASS GUPTA & ORS.                             ..... Defendants
                            Through: None
CORAM:
HON'BLE MR. JUSTICE V.K.JAIN

                            JUDGMENT

V.K.JAIN, J. (ORAL)

1. This is a suit for recovery of Rs.7,82,41,640/-. The defendant no.1, which is

a partnership firm of defendants no.2 to 5, was awarded a contract for construction

of 400 LIG houses in Group-III, of the value of Rs.9,49,41,058/- and the stipulated

date for completion of the work was 16.8.2005. It is alleged in the plaint that from

the very beginning, the defendants did not adhere to the time-schedule as per the

contract between the parties. The defendant No. 1 was required to sign the formal

agreement within seven days of issue of award letter dated 7.8.2003. It, however,

delayed the signing of the agreement and avoided to start the work on totally flimsy

ground, that the terms and conditions of the tenders were contradictory. The

objections raised by the defendant vide letter dated 11.8.2003 were clarified by the

DDA vide letter dated 22.08.2003 and the defendant asked to start the construction

work. The defendant however, did not commence the work and raised frivolous

pleas vide letter dated 13.9.2003. The plaintiff was, therefore, constrained to issue

notice dated 9.10.2003 giving last and final opportunity to the defendant to start the

work. Thereafter, the agreement was signed by the defendant only on 17.10.2003

and the site was taken over on that very date, though it should have been taken over

by 17.8.2003. It is alleged that deficient drawings were submitted on 4.11.2003,

though they were required to be submitted by 15.9.2003 and a number of

deficiencies were found in those drawings, which were later re-submitted on

24.11.2003. Again there were major mistakes in the earlier drawings and the same

were accordingly returned to the defendants. Initially, the defendants informed the

plaintiff that there were some mistakes in the design calculation, but later informed

that there was no mistake in the design. The design was accordingly approved by

the plaintiff on 20.02.2004. On account of delay on the part of the defendants, the

work could not begin from 15.9.2003 to 27.01.2004. Since the defendants were

delaying the construction of work on one pretext or the other, the plaintiff issued a

show-cause notice to defendant No. 1 stating therein that it was required to achieve

25% progress within six months but the progress on the site was practically Nil.

The reasons given by the defendant for the delay were not found satisfactory by the

Superintendent Engineer. He, however, granted indulgence to them and cautioned

that he reserved the right to impose compensation in case sufficient progress was

not achieved within next three months. Since the defendants failed to achieve the

desired progress, the plaintiff issued another show cause notice stating therein that

the progress achieved at the site was only 7% as against the stipulated requirement

of 50% which ought to have been achieved at that time. The defendant was time

and again requested to accelerate the progress of the work. Since the defendants

failed to adhere to the time-schedule for completion of the work, compensation

amounting to Rs.94,94,106/- under Clause 16 of the agreement was levied upon

them by the Superintendent Engineer vide letter dated 7.3.2005. Since defendant

No. 1 had completely abandoned the work, a notice under Clause 17 of the

Agreement was also issued to it on 9.3.2005 and the contract was later rescinded

vide letter dated 7.5.2005.

2. The plaintiff had paid mobilization charges of Rs.47.47 lac to the defendants

against a bank guarantee of Rs.48 lac. The mobilization advance was to carry

interest @ 16% per annum. Consequent to recision of the contract, the plaintiff is

claiming Rs.18,93,622/- per annum being the balance of mobilization advance and

interest on it after adjusting the bank guarantee furnished by the defendants. The

plaintiff is also claiming Rs.4,36,023/- towards interest on the balance of

mobilization advance @ 16% per annum for the period from 3.11.2006, till filing

of the suit.

3. The plaintiff is claiming a sum of Rs.95,71,264/- from the defendants after

adjusting the credit balance and recoveries to be made under various heads

including the compensation levied under Clause 16 of the Agreement. The plaintiff

is also claiming Rs.47,68,151/- towards interest on the amount of compensation of

Rs.94,94,106 and Rs 4287/- towards interest on the amount of Rs 77158/- which

becomes payable to the it due to under recoveries.

4. It is alleged in the plaint that under Clause 17 of the Agreement, the plaintiff

was entitled to get such part of the work which remained unexecuted from another

contractor and recover the excess amount, if any, paid by it from the defendants.

After rescinding the contract on 7.5.2005, the plaintiff invited tenders for the

balance work to be executed at the risk and cost of the defendants. That work was

awarded to M/s C.R.Sons Builders & Developers @ Rs.8801/- per sq. meter plinth

area, whereas the work to the defendant had been awarded @ Rs.5109/- per square

meter plinth area. The excess amount which the plaintiff had to pay on this account

is Rs.6,30,51,492/-.

5. The following is the break-up of the amount of Rs.7,96,71,839/-, which had become payable from the defendants:-

     A. Balance Mobilization Advance                 -      Rs.18,40,622/-



      B. Interest on the amount of Rs.18,40,622/-    -      Rs.4,36,023/-
     C. Net amount under 6th & Final Bill
        including compensation levied under clause 16-     Rs.95,71,264/-
     D. Interest on the amount of Rs.94,94,106/-    -      Rs 47,68,151/-
        and on the amount of     Rs.47,68,151/-     -      Rs 4278/-

     E. Risk and cost Amount                        -      Rs.6,30,51,492/-
                                                           -------------------
                                                           7,96,71,839/-

                                                           -------------------

Some material of the defendants was abandoned by them on the site and that

material was transferred by the plaintiff to the new contractor. The defendant is

entitled to credit of Rs.14,30,199/- being the value of that material. The suit amount

of Rs.7,82,41,640/- arrived after deducting the aforesaid amount of Rs.14,30,199/-

from the gross amount of Rs.7,96,71,839/-.

6. The defendants filed written statement contesting the suit and took a

preliminary objection that the suit is barred by limitation. On merits it was alleged

that rescinding of the contract was illegal since the work could not be completed on

account of various hindrances on the part of the plaintiff, non-availability of the

site, non-approval of drawings and non-payment of the amount due for the work

executed by the defendants. It is alleged that no interest on the compensation is

envisaged in the contract between the parties. The defendants have denied

abandonment of the work and have alleged that they had to move out of the site

after the contract was rescinded by the plaintiff.

7. The following issues were framed on the pleadings of the parties:-

1. Whether the suit is barred by limitation? OPD

2. Whether plaintiff is entitled to recover an amount of Rs.7,82,41,640/-, as claimed by it in para 26 of the plaint? OPP

3. Whether plaintiff is entitled to pendente lite and future interest, if so, on what amount and at what rate? OPP

4. Relief.

8. The plaintiff has filed the affidavit of Mr. Radhey Shyam, Executive

Engineer, RPD XI, by way of evidence. In his affidavit, the witness has supported

on oath the case set out in the plaint and has proved various documents filed by the

plaintiff. He has stated that the defendant did not have necessary resources ready in

hand to start the work and therefore, delayed taking over the site for execution of

work. He has further stated that the defendant delayed signing of the formal

agreement in terms of award letter dated 7th August, 2003 on one pretext or the

other, stating that the terms and conditions of the tender were contradictory. It was

clarified to him that there was no question of ambiguity in the terms and conditions

of the tender. Despite that, the defendant did not come forward to sign the formal

agreement. It was only after issue of the notice dated 9 th October, 2003 that the

formal agreement was signed by the defendant on 17 th October, 2003. Thus,

according to the witness, defendant was responsible for the delay of more than 61

days by not executing the formal agreement within the stipulated period.

He has further sted that the drawings were submitted by the defendants only

on 15th September, 2003. Vide letter dated 5th January, 2004, the defendant then

informed the plaintiff that there was some mistake in the design/calculation, and

therefore, the design re-submitted by them be withheld. However, vide subsequent

letter dated 27th January, 2004, they informed the plaintiff that there was no mistae

in the design. Accordingly, the designs were approved on 20th February, 2004.

He has stated that the plaintiff, time and again, requested the defendant to

accelerate the progress of the work but the defendant completely failed to adhere to

the completion programme. Compensation amounting to Rs. 94,94,106/- was then

imposed upon the defendant by the Superintending Engineer. According to the

witness, since the defendant had completely abandoned the work, the plaintiff had

no option but to rescind the contract vide letter dated 7th May, 2005. He has also

stated that the defendant had failed to construct the requisit cement godown even

after 2½ months of issue of award letter, nor there was any activity at site and even

the site office was not constructed. According to him, the defendant brought Birla

Chetak brand cement at the site which was not an approved brand.

In his deposition, Mr. Radhey Shyam has stated that the Nala shown to the

lay out plan of the field investigation report existed only under 2 out of the 20

blocks consisting of 20 houses each, which the defendant was required to construct

and the remaining 18 blocks were free from any kind of hindrance. He has also

stated that the plaintiff did not suggest any increase in the length of row of blocks

and it was the defendant who chose to change increase of extension joint from 40

mm to 150 mm, which was agreed by the CDO of the plaintiff. According to this

witness, the defendant completely abandoned the work after November, 2004 and

removed construction equipment from the site he has claimed that the defendant

had completed about 7% of the work by the time it was abandoned by him.

The witness of the plaintiff has also stated that on recession of the contract,

the work was re-awarded to M/s.C.R.Sons Bldrs. & Developers at the rate of

8801/- per square meter plint area whereas the defendant was awarded this work at

the rate of Rs.5109/- per square meter plinth area. According to him, it was

difficult for the plaintiff to find another contractor for completion of the work

which was left incomplete by the defendant. He has stated that the difference of

the cost on account of the work being awarded to M/s.C.R.Sons Bldrs. &

Developers comes to Rs.6,30,51,492/-.

This witness has also stated that at the time of rescission of the contract,

some material such as TMT bars, stone aggregate, coarse sand, site office, godown,

labour huts, tube well, pump house, laboratory i/c 270 Mt. Length for electric

connection procured by defendant, was lying at this site, that material was

transferred to M/s.C.R.Sons Bldrs. & Developers and a sum of Rs.14,30,199/- was

deducted from their bill in this regard and adjustment from that amount has been

given to the defendant.

9. It is an admitted case that D-1 which is a partnership firm of defendants No.2

to 5 was awarded a contract for construction of 400 LIG Houses at the plinth area

rate of Rs.5109 per sq. mtr. and the time allowed for completing the construction

was 24 months. This is confirmed from a perusal of the work of the award letter

(Ex. P1), which is dated 07.08.2003. A perusal of this document would show that

the time of 24 months to complete the work was to be reckoned from 10th day after

the date of issue of letter. Therefore, the defendant should have commenced

execution of the work by 17.08.2003 and should have completed it by 16.08.2005.

It is an admitted position that the defendant did not complete the work by

16.08.2005.

10. The plea taken in the written statement is that the work suffered because of

various breaches committed by the plaintiff and various hindrances attributable to

it. It is alleged that contradictory conditions were stipulated in the award letter and

the work were delayed due to non-availability of clear sight failure to approve

drawings and non payment of dues for the work which had been executed. A

perusal of the record would show that vide letter dated 11.08.2003 (Ex.P-2), the

defendant wrote to the plaintiff that clause 1.3 and 2.2 of the award letter dated

07.08.2003 were contradictory. It was stated that they had quoted rates with

maintenance period of one year whereas the award letter stipulated watch and ward

of un-allotted houses for a period of three years. It was also stated in the letter that

during negotiations the maintenance period after completion of the houses had been

reduced from three years to one year since handing over of service to the civic

body was not likely to take place in the absence of peripheral services to be

rendered by the department with the provision for extension for further two years at

extra cost but the scope of work in clause 2 stipulated that the service were to

handed over to the respective department which was in-contravention of the

discussions during negotiations. Vide letter dated 22.08.2003 (Ex.P-3), DDA

informed the defendants that there was no contradiction in the award letter. It was

pointed out that Clause 1.3 of the award letter provided for maintenance for one

year after completion of the work and incase of need for maintenance beyond one

year the defendant was to be paid @ Rs.53 per sq. mtr. of plinth area per year upto

maximum of two years. It was further pointed out that as per Clause 2.2, the watch

and ward of un-allotted houses was to remain with the defendants for three years

after completion of the work and thereafter unalloted flats were to be made defect

free and handed over to the department. It was stated in the reply that there was no

negotiations in this regard with the defendant and the award letter was based on the

provisions of the tender document and as per defendants', negotiation letter dated

24.07.2003. The defendants were asked to attend the office of the plaintiff to sign

the formal agreement within seven days from the date of issue of the letter.

However, vide letter dated 13.09.2003, the defendants avoided execution of the

agreement on the ground that those were sharaadh days and therefore they would

sign the agreement only after 25.09.2003. A perusal of the notice Ex.P-5, send by

the plaintiff to the defendant on 09.10.2003 would show that the defendants did not

execute the agreement even after 25.09.2003. The defendants were, therefore,

given one last and final opportunity for taking over the site and execute the

agreement within seven days from the date of the letter. Admittedly, the agreement

was actually executed by the defendant on 16/17.10.2003. The drawings were

submitted by the defendants vide letter dated 04.11.2003 (Ex.P-6). The drawings

were returned with certain objections vide letter dated 06.11.2003 (Ex.P-7). This

was followed by a letter dated 07.11.2003 to the defendants asking them to give

undertaking as indicated in the letter with respect to handing over of the site and

the number of labours tents pitched by the defendants on the site, as also with

respect to the site office consisting yard laboratory etc. The drawings were re-

submitted by the defendants on 22.11.2003 vide letter Ex.P-9. However, before

these drawings could be approved by the plaintiffs, the defendant vide letter dated

05.01.2004 (Ex. P-9) informed the plaintiff that there was a calculation mistake in

working out the loads according to their structure designs and they were in the

process of submitting the same. The plaintiff was requested to withhold the earlier

structure designs submitted by the defendants. It would, thus, be seen that during

05.01.2004, the defendants had not been able to finalize the structure designs and

were still in the process of revising the same. Vide letter dated 16.01.2004, the

defendants were informed that they had failed to attain 25% progress within 1/4 th of

the period stipulated for completion of the construction and the progress at the site

was practically nil. The defendants were asked to show cause why compensation

under clause 16 of the agreement be not levied upon them. There was no response

from the defendants to this letter. Vide letter dated 27.01.2004 (Ex.P-11), the

defendants in continuation of their letter dated 05.01.2004, informed the plaintiff

that there were no calculation mistake in working out the loads, and therefore, the

structure designs submitted by them may be approved. Thus, it was only on

27.01.2004 that the defendants finally sought approval of the structure designs

submitted by them. The structure designs were approved by the plaintiff vide letter

dated 20.02.2004.

11. Vide letter dated 24.02.2004, (Ex.D-1), the defendants complained of

flooding at site and various damages caused by the agency executing the work on

the upstream of their site and stated that the accumulation of water had also

increased the level of water table, resulting in expenditure on pumping out the

same. The plaintiff was asked to define the work of the defendants and compensate

them for the losses sustained by them.

Vide letter dated 24.03.2004 (Ex. P-13), the plaintiff gave an opportunity to

the defendant to discuss the matter on 31.03.2004 before any action was taken

under Clause 16 of the agreement. Vide letter dated 17.05.2004 (Ex.D-2), the

defendants sought withdrawal of the notice dated 16.01.2004 issued under Clause

16 of the Contract. It was stated in the letter that on account of increase in width of

the expansion joint the dimensions shown in the lay out plan were not in

accordance with the dimensions prevailing on the ground, revision of lay out plan

had become necessary and work could not proceed further in the absence of revised

lay out plan.

Vide letter dated 30.06.2004 (Ex.P-14), the Superintendent Engineer of

DDA informed the defendants that they had miserably failed to organize the work

from the very beginning and had lost valuable time. The levy of compensation,

however, was deferred despite failure of the defendant to carry out their contractual

obligations and they were advised to mobilize all resources and material, to execute

the work.

Vide letter dated 04.10.2004 (Ex.D-3), the defendants complained that

payment of advances had been assessed by the plaintiff on a lower site, as a result

of which their funds to the tune of Rs.12 lacs had got blocked and secured

advanced had not been allowed on store aggregates. The plaintiff was requested to

pay full value of the material after assessing it on the value of prevailing market

rates.

Vide letter dated 08.10.2004 (Ex. D-4), the defendants sought

reimbursement for the extra expenditure alleged to have been incurred at them on

procurement TMT.

Vide letter dated 03.11.2004 (Ex. D-5), the defendant again sought payment

of secured advance on the basis of prevailing rates of the material brought by them

to the site. They also sought reimbursement on account of abnormal increase in

price of bricks/cement.

Vide show cause notice dated 04.11.2004 (Ex. P-15), the Clause 17, the

defendants were informed that actual progress of the work at that time was only

about 7% though ½ of the work should have been completed by 31.10.2004 as per

Clause 16 of the agreement. The defendants were asked to show cause why action

under sub-Clause 17(a) and/or 17(b) and/or 17(c) of the agreement be not taken

against them on account of breach of the contract on their part.

Vide notice dated 04.11.2004 (Ex.P-16) sent by the Superintendant Engineer

of DDA, the defendants were again asked to show cause within ten days as to why

the compensation under Clause 16 of the agreement be not levied upon them. It

was pointed out in the notice that despite sufficient opportunity given to them the

defendants had not shown progress in the matter of construction and the progress at

the site was only about 7% though it should have been 50% by 31.10.2004.

Reference was also made to the earlier notice dated 30.06.2004 whereby right to

impose compensation was reserved by the plaintiff.

The letter dated 08.10.2004 was replied by the plaintiff on 06.11.2004 and

the reply is Ex.D-6. It was stated in the reply that the defendants had delayed start

of the work by taking late possession, not signing the agreement in time and late

submission of foundation and other structural drawings. The defendants were also

informed that they have to procure TMT from the manufacturer as per the

agreement and the reimbursement of extra expenditure was beyond the scope of the

agreement. The defendants were asked to submit documentary evidence incase

TMT bars specific dia's were not available with the main procedures.

Vide letter dated 11.11.2004 (Ex.D-7), the defendants claimed that the delay

in commencement and execution of the work was not attributable to them and the

progress of the work had suffered, due to lack of planning at the end of the

plaintiff, which was reflected in the revision of the lay out plan almost 09 months

after the stipulated date of commencement of the work. It was also stated in the

letter that the DDA had granted permission to other contractors to procure the TMT

bars from sources other than the manufacturers.

Vide letter dated 11.11.2004, the defendants, again, wrote to the plaintiff that

they were being discriminated in the matter of secured advance since other

contractors were being paid at the rate of 75% of the prevailing rates of the

material, whereas they were being paid up to only about 40% of the cost of the

material procured by them. This letter was written in response to DDA's letter

dated 04.11.2004. Yet another letter was written by the defendants to DDA on

11.11.2004 (Ex.D-9), stating therein that there was no lapse or deficiency on their

part and they were not responsible for the delay in execution of the work.

Reference in this letter was made to the show-cause notice received from the

Executive Engineer in clause 17 of the agreement. Vide letter dated 16.11.2004,

the defendants, again, sought secured advance to the extent of 75% of the

prevailing market rate of re-enforced steel and other material.

Vide letter dated 23-11-2004 (Ex. P-17), the concerned Executive Engineer

informed the defendants that the position of the material at the site was very

alarming and if the same position continued, there would be no alternative except

to take action under various Clauses of the contract. It was stated that the progress

achieved was hardly 7.5% though it should have been more than 50%. Vide letter

dated 27.11.2004, the concerned Executive Engineer, again asked the defendants to

devote time and energy to accurate the progress of the work instead of exchanging

unnecessary correspondence.

Vide letter dated 29.11.2004 (Ex.D-14), the defendants sought permission to

procure 300 MT of TMT bars from the secondary producers. Vide letter dated

13.12.2004 (Ex.D-15), written to Engineer Member of DDA, the defendants

complained that they had not been permitted to procure re-enforced steel bars from

secondary manufacturers and had not been paid secured advance on bricks and

coarse aggregates, which they had brought on the site. They also complained about

non-payment of testing charges for steel and cement. Vide letter dated 13.12.2004,

the defendants, again, reiterated that delay in execution of the work was due to

reasons stated in their earlier letters and was not on account of lack of planning and

resources on their part. This letter was written in response to letter of DDA dated

27.11.2004.

Vide letter dated 14.03.2005 (Ex.D-19) in reply to the show-cause notice

under clause 17 of the agreement, the defendants informed the plaintiff about filing

of Suit No. 1435 of 2004 in this Court and requested that the outcome of the said

suit be awaited.

Vide letter dated 11.04.2005, written in response to DDA's letter dated

07.03.2005 the defendants refuted their liability to pay any amount to DDA

towards compensation. Vide letter dated 28.04.2005 (Ex.D-23), the defendants

stated that the work stood abandoned being sub judice and requested that 50 MT of

steel used by them in columns and rafts be recorded for payment and 20 MT of

TMT bars lying at the site be taken on record and the expenditure be reimbursed or

in the alternative they may be permitted to lift the same. Similar request was made

in respect of other material such as stone aggregate, stone dust, shuttering material,

etc.

Vide letter dated 01.06.2006, written in response to letter of DDA dated

05.05.2006, the defendants criticized the action of awarding the work of another

contractor and sought details and mode of working out the rate at which the work

had been awarded to that contractor.

12. The first claim of the plaintiff is with respect to the amount which was given

as mobilization advance to the defendants, after adjusting the amount of the bank

guarantee which the plaintiff invoked. It is alleged in para 26 of the plaint that the

plaintiff had extended mobilization advance of Rs 47.47 lakh to the defendants on

06.05.2004 at the interest of 16% per annum and the defendants had furnished a

number of bank guarantees for an aggregate sum of Rs 48 lakh to the plaintiff. The

amount of interest at the rate of 16% per annum from 06.05.2004 to 02.11.2006,

when the bank guarantees were encashed, comes to Rs 18,93,622/-. The balance

amount of Rs 29,06,378/- was adjusted by the plaintiff against the principal amount

of Rs 47.47 lakh. Thus, the plaintiff is entitled to recover the balance mobilization

advance, amounting to Rs 18,40,622/- from the defendants. Since the mobilization

advance carried interest at the rate of 16% per annum, the defendants are also liable

to pay interest on that amount on the aggregate rate of 16% per annum. The

amount of interest on Rs 18,40,622/- for the period from 03.11.2006, till filing of

this suit, comes to Rs 4,36,023/-. The plaintiff is entitled to recover the said

amount from the defendants.

13. Clause 16 of the agreement between the parties reads as under:-

"The works comprised in this tender are to be commenced immediately on receipt of written orders from the Divisional Officer to commence work. The time allowed for carrying out of the work as entered in the tender shall be strictly observed by the contractor and shall be reckoned from the 10th day after the date on which the order to commence the work is issued to the contractor(s). The work shall throughout the stipulated period of the contract be proceeded with all due diligence (time being deemed to be the essence of the contract(s) on the part of the contractor(s) and the contractor(s) shall pay as compensation as amount equal to one percent or such smaller amount as the Superintending Engineer (whose decision in writing shall be final) may decide, on the amount of the contract as shown in the tender for every day that the work remains un-commenced or unfinished, after the proper dates and further, to ensure goods progress during the execution of the work, the contract(s) shall be found, in all cases in which the time allowed for any work exceeds one month to complete one fourth of whole of the work before one fourth of the whole time allowed under the contract has elapsed one half of the work before one half of such time has elapsed, and three fourth of the work before three fourths of such time has elapsed. In the event of contractor(s) failing to

comply with the condition he/they shall be liable to pay as compensation an amount equal to one percent or such small amount as the Superintending Engineer, (whose decision in writing shall be final may decide on the said amount of the contract for every day that the due a quantity of work remains incomplete; provided always that entire amount of compensation to be paid under the provisions of this clause shall not exceed ten percent on the amount of the contract as shown in the tender.

In M/s J.G.Engineers Pvt. Ltd. v. Union of India & Anr. AIR 2011 SC

2477, Supreme Court considering a clause identical to clause 2 of the agreement

between the parties to this suit, inter alia held as under:

"14. Thus what is made final and conclusive by clauses (2) and (3) of the agreement is not the decision of any authority on the issue whether the contractor was responsible for the delay or the department was responsible for the delay or on the question whether termination/rescission is valid or illegal. What is made final, is the decisions on consequential issues relating to quantification, if there is no dispute as to who committed breach. That is, if the contractor admits that he is in breach, or if the Arbitrator finds that the contractor is in breach by being responsible for the delay, the decision of the Superintending Engineer will be final in regard to two issues. The first is the percentage (whether it should be 1% or less) of the value of the work that is to be levied as liquidated damages per day. The second is the determination of the actual excess cost in getting the work completed through an alternative agency. The decisions as to who is responsible for the delay in

execution and who committed breach is not made subject to any decision of the respondents or its officers, nor excepted from arbitration under any provision of the contract."

Supreme Court in this regard also referred to the following view taken by it

in Bharat Sanchar Nigam Limited v. Motorola India Limited (2009) 2 SCC 337:

"x x x the decision contemplated under Clause 16.2 of the agreement is the decision regarding the quantification of the liquidated damages and not any decision regarding the fixing of the liability of the supplier. It is necessary as a condition precedent to find that there has been a delay on the part of the supplier in discharging his obligation for delivery under the agreement."

It is thus for the Court to decide whether delay in execution of the work,

within the time stipulated in the agreement, was attributable to the defendants or to

the plaintiff. If the Court comes to the conclusion that delay in completion of the

work is attributable to the defendants, the decision of the Superintending Engineer

in respect of quantum of the compensation would be final and binding on the

parties and it would not be open to the Court to sit in appeal over the decision of

the Superintending Engineer with respect to the quantum of compensation and take

a view different from the view taken by him. On the other hand, if the Court finds

that the delay in execution of the work was attributable solely to the plaintiff, the

decision of the Superintending Engineer levying compensation would be without

jurisdiction. Similarly, if the Court finds that the defendants had failed to maintain

progress of the work in terms of the contract agreed between the parties and the

plaintiff was not responsible for the failure of the defendants to maintain the

required progress, it is not permissible for the Court to interfere with the amount of

compensation levied by the Superintending Engineer since his decision with

respect to quantum of the compensation is final and binding on the parties.

14. A perusal of the award dated 07.08.2003 would show that the defendants

were required to commence the work within 10 days from the date of issue of the

letter which would mean that they were required to commence the work by

17.08.2003. The award letter further shows that the work was required to be

completed within two years from the date of commencement, which would mean

that it was required to be completed by 16.08.2005.

A perusal of the clause 16 of the agreement would show that the defendants

were required to execute one fourth of the work before one fourth of the time

allowed under the contract had elapsed, one half of the work before one half of the

time allowed for completion of the work have elapsed and 3/4 th of the work before

three fourth of the time allowed for completing the work have elapsed. Therefore,

the defendants were required to complete 25% of the work by 16.02.2004 and 50%

of the work by 16.08.2004. The defendants were required to complete 75% of the

work by 16.02.2005. The contract was rescinded by DDA on 07.05.2005. It was

stated in the show-cause notice dated 04.11.2004 issued by the plaintiff to the

defendants that the progress achieved by that time was only 7%, though actual

progress achieved should have been more than 50% by that time. The averment to

this effect finds mention in para 13 and 14 of the plaint.

In their written statement, the defendants have not disputed that the work

executed by 31.10.2004 was only 7%. This was also their case that they had

executed more than 7% of the work by 31.10.2004. It has come in the unrebutted

deposition of PW-1 that the defendant had completed only about 7% of the work,

when the contract was rescinded. Thus, it can hardly be disputed that the

defendants did not adhere to the time schedule fixed in the agreement for

completion of the work.

The only plea taken in the written statement for delay in execution of the

work are that the award letter contained contradictory conditions and there were

hindrances on the part of the plaintiff i.e. non-availability of clear site, non-

approval of drawings on flimsy excuses and payment was not made for the extra

work executed by the defendants. No evidence has, however, been led by the

defendants to prove any lapse on the part of the plaintiff. No particular

contradiction in the terms and conditions of the award letter has been pointed out

by the defendants in the written statement. The work was awarded to the

defendants on 07.08.2003 and they executed a formal agreement on the same terms

which were contained in the award letter on 17.10.2003. Had there been any

contradictory conditions in the award letter, the defendants would not have

executed the formal agreement without the alleged contradictions being removed

from the terms of the agreement.

There is absolutely no evidence on record to prove that there was any delay

on the part of the plaintiff in handing over site to the defendants. It would be

pertinent to note here that CS(OS) No. 1435/2004 was filed by the defendants

when the plaintiff sought to invoke the bank guarantees which they had furnished

to the plaintiff. It was alleged in the plaint of that suit that DDA had played fraud

upon them by not informing them about existence of a Nala at the project site and,

therefore, the contract between the parties was void due to non-closure of material

facts. The case of DDA in that suit was that the Nala was duly shown in the site

plans. Rejecting the contention of the defendants, a Division Bench of this Court,

inter alia, held as under:-

"18. The tender documents which were given to all the tenderers by respondent No.1 before awarding the contract are part of the records. The appellant also obtained the said tender documents and on the basis of the same, its tender was submitted. In the said tender documents, lay out plan is attached to the soil inspection report at page 201. Existence of a nallah is clearly shown in the said lay out plan attached. Clause 27 of the tender documents also clearly requires the tenderer to inspect the

work site and to study the drawing, soil inspection reports, tender documents and other conditions referred therein. Clause 1 of the Specifications and conditions of the tender, which appears at page 130 of the paper book, requires the contractor to get acquainted with the proposed site of contract and study specifications and conditions carefully before tendering. The aforesaid documents, which are on record and part of the tender documents, clearly indicate that the appellant was informed about the existence of a nallah at the project site. The terms and conditions also require the tenderer to inspect the site before submitting its tender. It was also specifically stated in the terms of the tender that the tenderer should submit the tender only after getting acquainted with the site. Before submitting the tender the appellant must have meticulously followed and complied with the aforesaid conditions, including inspection of the site and, therefore, we are prima facie satisfied that the appellant had knowledge and information that there existed a nallah at the project site.

19. It is stated by respondent No.1 that the pace of the work of the appellant at the site was extremely slow for which several notices had to be issued by the said respondent to the appellant. The appellant also received mobilization advance before filing of the aforesaid suit. Therefore, it cannot be said that the appellant received mobilization advance without having knowledge and information about the location and situation of the project site including the existence of nallah at the site. Therefore, we are satisfied that the allegation now made by the appellant that it did not have the information about the existence of a nallah at the site is an afterthought and is a ploy to get out of the contract by hook or by crook. It is also interesting to note that not a single letter was written by the appellant to respondent No.1 prior to the receipt of the mobilization advance that it had no knowledge regarding the site or that it had not inspected the site at all.

20. The contract was awarded to the appellant on 7th August, 2003 and site was handed over to the appellant on 1st November, 2003. When possession of the site was handed over to the appellant on the said date, it cannot be expected that they received possession of the site for starting construction work without having inspected the site. A letter was also written by the appellant to the DDA on 13th November, 2003 wherein also no mention was made by the appellant of the fact that the appellant was unaware of the existence of nallah at the site. Although, in the plaint, a stand is taken that the appellant became aware of the existence of the nallah only on 6th November, 2003 but the contemporaneous documents on or about the said date clearly belies the fact that the appellant had no knowledge about the existence of a nallah at the project site. The appellant also obtained mobilization advance to the tune of Rs.47.47 lacs from respondent No.1 on 6th May, 2004 and it cannot be expected that the appellant had obtained the mobilization advance without even inspecting the site in question which was handed over to it on 1st November, 2003, i.e. about six months prior to the date of release of mobilization advance."

Thus, existence of a Nala at the site cannot be said to be hindrance on the

part of the plaintiff and the defendants had no justification to commit delay in

commencement or execution of the work on account of existence of Nala on the

site. As regards approval of drawings, there is no evidence of any abnormal delay

on the part of the plaintiff in approving the drawings. In fact, the defendants

themselves committed delay in submitting the drawings. As per the contract, the

foundation drawings were to be submitted on 15.09.2003, whereas the defendants

submitted the same on 04.11.2003 and even at that time, the drawings were not free

from deficiencies and had to be re-submitted on 24.11.2003. At this stage, the

defendants sought withholding of the drawings on the ground that there was some

mistake committed by them in drawings calculation. They sought approval of the

drawings vide letter dated 27.01.2004 and the drawings were approved on

20.02.2004, i.e., within about 24 days of the defendants seeking approval of the

drawings submitted by them. This is not the case of the defendants in the written

statement that under the agreement between the parties, the plaintiff was required

to approve drawings in a period of less than 24 days. The time taken by the

plaintiff for approval of the drawings cannot be said to be unreasonable,

considering the nature of the project and the work which the defendants were

required to execute.

As regards non-payment of the dues, I find that the written statement does

not indicate which payment was delayed and by how much time. There is

absolutely no evidence of any delay having been committed by the plaintiff in

payment of the work executed by the defendants. Therefore, it cannot be said that

the progress of the work was caused on account of delay in payments to the

defendants. I have extensively referred to the correspondence exchanged between

the parties. On the other hand, PW-1 Radhey Shyam is emphatic in his deposition

that the delay in commencement and execution of the work was attributable solely

to the defendants. This also becomes quite clear from a perusal of the

correspondence exchanged between the parties and a number of letters which the

plaintiff wrote to the defendants from time to time, asking them to accelerate the

execution of the work.

Since it is the defendants, who were solely responsible for delay in execution

of the work and a show-cause notice was also issued to them before levying

compensation, the Court would be justified in presuming that while levying the

compensation, the Superintending Engineer considered all the facts and

circumstances of the case. There is nothing on record to indicate that the

compensation levied by the Superintending Engineer was unreasonable. No

evidence has been led by the defendants to establish that amount of compensation

levied upon them was unreasonable or excessive. No evidence has been led by

them to prove that there was no legal injury cased to the plaintiff on account of

their failure to complete the contract. Therefore, the Superintending Engineer, in

my view, was fully entitled in law to levy compensation, amounting to Rs

94,94,106/- on the defendants.

15. The plaintiff has made certain adjustments from the amount of the final bill

submitted by the defendants to it. A sum of Rs 77,540/- was payable to the

defendants after adjustment of the value of the work which was show in the

previous bills and the outstanding secured advance. The plaintiff has claimed Rs

53,675/- towards interest on secured advance which was agreed at 16% per annum.

In the written statement, this is not the case of the defendants that the secured

advance was not to carry any interest or that it was to carry interest at less than

16% per annum. Therefore, the claim of the interest on secured advance is justified.

The Workers Welfare Cess and Work Tax are to be deducted from the bill and the

plaintiff has rightly claimed Rs 3102/- towards Work Tax, Rs 76930/- towards the

Workers Welfare Cess after adjusting the amount which it had already recovered.

Adjustment of Rs 3,044/- has been made towards income-tax and Rs 17,947/-

towards balance security deposit. The amount which remains payable to the

plaintiff in terms of the claim made in para 26(C) of the plaint comes to Rs

96,48,804/-, after adjusting the amount of Rs 77,540/- which was payable to the

defendants towards final bill. The net amount which remains payable to the

plaintiff against this claim comes to Rs 95,71,264/-. The plaintiff is entitled to

recover this amount from the defendants.

16. The plaintiff has also claimed interest on the amount of compensation. The

interest claimed is Rs 47,68,155/- at the rate of 16% per annum from the date of

levy till the date of filing of this suit. The plaintiff has also claimed interest

amounting to Rs 4,287/- on the amount of Rs 77,158/- which is the amount of

under-recoveries which remained payable to the plaintiff after adjustment from the

final bill. There is no agreement between the parties for payment of interest either

on the amount of compensation levied under clause 16 of the agreement or on the

recoveries towards security deposit, work tax, income-tax, workers welfare cess. It

seems that the plaintiff is also claiming interest on the amount of Rs 53,675/- which

was interest on the secured advance. Obviously, the plaintiff cannot claim interest

on interest, since the agreement between the parties did not envisage compound

interest on the amount of secured advance.

Section 3 of Interest Act, to the extent it is relevant, provides that in any

proceeding for the recovery of any debt or in any proceeding in which a claim of

interest in respect of any debt is made, the Court may allow interest to the person

entitled to the debt at a rate not exceeding the current rate of interest. The interest

under this provision can be allowed by the Court, if the proceedings relate to any

debt payable by virtue of a written instrument at a certain time, from the date when

the debt is payable to the date of institution of the proceedings and if the

proceedings do not relate to any such debt, then from the date mentioned in this

regard in a written notice given by the person entitled or the person making the

claim to the person liable, that interest will be claimed, up to the date of institution

of the proceedings.

In the present case, the amount of compensation was not payable at a

particular time. A notice dated 20.05.2005 was sent by the plaintiff to the

defendants, demanding the amount of Rs 94,94,106/- which was the quantum of

levy of compensation by the Superintending Engineer. It was also stated in the

notice that DDA shall also be entitled to interest on the said amount at the rate of

16% per annum. Therefore, interest under Section 3 of the Interest Act, 1978 can

be awarded to the plaintiff on the amount of compensation, with effect from

20.05.2005, till the date of filing of this suit. In the facts and circumstances of the

case, I am of the view that interest under Section 3 of Interests Act, 1978 should be

awarded to the plaintiff at the rate of 12% per annum on the amount of Rs

94,94,106/-. The learned counsel for the plaintiff states that the interest for the

period from 20.05.2005, till the filing of this suit on 05.05.2008 comes to Rs

33,70,407.63/-. The plaintiff is entitled to this amount from the defendants.

17. Clause 17 of the agreement between the parties reads as under:-

"In any case in which under any clause of this contract the contractor shall have rendered himself/themselves liable to pay compensation amounting to the whole of his/their security deposit (whether paid in one sum or deducted by instalment) or committed a breach of any of the terms contained in Clause 20, the Divisional Officer on behalf of DDA shall have power:-

(a) To rescind the contract (of which recession notice in

writing to the contractor(s) under the hand of the Divisional Officer shall be conclusive evidence) and in such case the security deposit of the contractor(s) shall stand forfeited, and be absolutely at the disposal of DDA.

(b) To employ labour paid by the Delhi Development Authority and supply materials to carry out the work or any part of the work debiting the contractor(s) with the cost of the labour and the price of the materials (the amount of such cost and price certified by the Engineer- in-charge shall be final and conclusive) and crediting him/them with the value of the work done. The certificate of the Divisional Officer as to the value of the work done shall be final and conclusive against the contractor(s).

(c) To take such part of the work as shall be unexecuted out of his/their hands, and to give it to another/other contractor(s) to complete. In which case any expenses which may be incurred in excess of the sum which would have been paid to the original contractor(s) if the whole work had been executed by him/them (of the amount of which excess the certificate in writing of the Divisional Officer shall be final and conclusive) shall be borne and paid by the original contractor(s) and may be deducted from any money due to him/them by DDA under the contract or otherwise or from his/their security deposit or proceeds the sale thereof or a sufficient part thereof. The cost of the work to be executed by the contractors shall be determined based on market rates prevailing at the time of actual execution of the work.

In the event of any of the above courses being adopted by the Divisional Officer the contractor(s) shall have no claim to compensation for any loss sustained by him/them by reasons of his/their having purchased or procured any material or entered into any engagements, or made any

advances on account of, or with a view of the execution of the work or the performance of the contract. And in case the contract shall be rescinded under the provisions aforesaid, the contractor(s) shall not be entitled to recover or be paid by any sum for any work therefore actually performed under the contract, unless the Divisional Officer will have certified in writing the performance of such work and the value payable in respect thereof, and he/they shall only be entitled to be paid the value so certified."

In the present case, compensation has been levied by the Superintending

Engineer upon the defendants under clause 16 of the agreement. The levy of

compensation has been found to be legal and justified. It was the defendant, who

failed to maintain the required progress in execution of the work and thereby

compelled the plaintiff to rescind the contract. The concerned Executive Engineer

sent notice under clause 17 of the agreement to the defendants on 09.03.2005,

stating therein that they had abandoned the work and gave them 10 days' time.

The contract was ultimately rescinded by the plaintiff on 07.05.2005. In view of

clause 17 of the agreement, the plaintiff was entitled to get the unexecuted work

executed from the other contractor and any expenses incurred by DDA in excess of

the amount which it had contracted to pay to the defendants, can be recovered by it

from the defendants.

It has come in evidence that unexecuted work was awarded by the plaintiff

to M/s C.R. Sons Builders and Developers at the rate of Rs 8801/- per square metre

of plinth area. The rate agreed to be paid to the defendants was only Rs 5,109/- per

square metre of plinth area. The excess amount, which the plaintiff agreed to pay

to M/s C.R. Sons Builders and Developers for execution of the work, which was

left unexecuted by the defendants, comes to Rs 6,30,51,492/- as stated in the

affidavit of Mr. Radhey Shayam. The plaintiff is entitled to recover that amount

from the defendants.

18. For the reasons stated hereinabove, I hold that the plaintiff is entitled to the

following amounts from the defendants:-

a) balance of the mobilization advance: Rs 18,40,622/-

b) interest on mobilization advance: Rs 43,6,023/-

c) the principal amount in terms of claim in para 26(C) of the plaint comprising

compensation under clause 16 of the agreement and certain other recoveries:

Rs 95,71,264/-

d) interest on the amount of compensation Rs 33,70,407.63/-

e) excess amount paid to M/s C.R. Sons, Builders and Developers Rs 6,30,51,492/-

The issue is decided accordingly.

As far as the recovery of balance mobilization advance is concerned, since

the contract was rescinded on 07.05.2005, the plaintiff had no cause of action to

claim this amount prior to that date. Having been filed on 05.05.2008, the suit is

within limitation as far as the balance mobilization advance is concerned.

Consequently, the suit to the extent it pertains to interest on mobilization advance

is also within limitation.

As far as recovery of compensation levied under clause 16 of the contract is

concerned, admittedly, the compensation was levied by the Superintending

Engineer prior to 07.03.2005. Vide letter dated 07.03.2005 the defendants were

informed about levying of compensation and were asked to deposit the same within

15 days from the date of the letter. Irrespective of whether the period of limitation

is computed from the date the compensation was levied or from the date stipulated

in the letter dated 07.03.2005 for making payment, the suit having been filed on

05.05.2008 is barred by limitation, as far as this claim is concerned. For the same

reason, the interest on the compensation levied under clause 16 of the contract is

also barred by limitation.

As far as the amount of Rs 77,158/- payable to the plaintiff on account of

under recoveries mentioned in para 26(C) of the plaint is concerned, the same is

within limitation since the final bill was prepared only in the year 2007.

Consequently, the claim for the interest on the amount of Rs 77,158/- would be

within limitation. The amount of interest on Rs 77,158/- at the rate of 12% per

annum, according to the learned counsel for the plaintiff, comes to Rs 3,215/. As

regards the amount of Rs 6,30,51,492/-, the same is within limitation since the

contract to M/s C.R. Sons Builders and Developers was awarded only on

14.02.2007, whereas the suit was filed on 05.05.2008. The issue is decided

accordingly.

In view of my finding on the issue No. 1&2, the plaintiff is entitled a decree

for recovery of the following amounts:-

1.     Secured Advance:                                          Rs 18,40,622/-
2.     Interest on secured advance:                              Rs 4,36,023/-
3.     Amount due to under-recoveries:                           Rs 77,158/-
4.     Interest on under-recoveries:                             Rs 3,215/-
5.     Difference between the cost of work
       awarded to the defendant and the cost of the work
       awarded to M/s C.R. Sons Builders and Developers:         Rs 6,30,51,492/-

                                       Order

For the reasons stated hereinabove, a decree for recovery of Rs 6,54,08,510/-

with proportionate cost and pendente lite and future interest at the rate of 12% per

annum is passed in favour of the plaintiff and against the defendants.

Decree sheet be drawn accordingly.

V.K.JAIN, J OCTOBER 10, 2012 rd/rb/bg

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter